Question

​Susan Winslow has two alternative routes to travel from her home in Olport to her office in Lewisburg.

Susan Winslow has two alternative routes to travel from her home in Olport to her office in Lewisburg. She can travel on Freeway 5 to Freeway 57 or on Freeway 55 to Freeway 91. The time distributions are as follows:

Freeway 5

Freeway 57

Freeway 55

Freeway 91


Relative


Relative


Relative


Relative

Time

Frequency

Time

Frequency

Time

Frequency

Time

Frequency

5

0.30

4

0.10

6

0.20

3

0.30

6

0.20

5

0.20

7

0.20

4

0.35

7

0.40

6

0.35

8

0.40

5

0.20

8

0.10

7

0.20

9

0.20

6

0.15



8

0.15





Do a five-day simulation of each of the two combinations of routes using the random numbers below. Based on this simulation, which routes should Susan take if her objective is to minimize her total travel time?

Freeway 5

63

88

55

46

55

Freeway 57

59

09

57

87

07

Freeway 55

71

95

83

44

34

Freeway 91

51

79

09

67

15

 

Then do a 365-day simulation of each of the two combinations of routes using Microsoft Excel. Based on this simulation, are the routes Susan should take different from the above? If so, why?

 


 

3. Joe King has ambitions to be mayor of Williston, North Dakota. Joe has determined the breakdown of the steps to the nomination and has estimated normal and crash costs and times for the campaign as follows (times are in weeks).



Normal

Crash

 Immediate



Activity

Time

Cost

Time

Cost

 Predecessors


A.

Solicit volunteers

6

$5,000

4

$  9,000

— 


B.

Initial "free" exposure

3

  4,000

3

    4,000


C.

Raise money

9

  4,000

6

  10,000

 A


D.

Organize schedule

4

  1,000

2

    2,000

 A


E.

Hire advertising firm

2

  1,500

1

    2,000

 B


F.

Arrange TV interview

3

  4,000

1

    8,000

 B


G.

Advertising campaign

5

  7,000

4

  12,000

 C, E


H.

Personal campaigning

7

  8,000

5

  20,000

 D, F


Joe is not a wealthy man and would like to organize a 16-week campaign at minimum cost. Write and solve a linear program to accomplish this task.

4. The critical path for this network is A - E - F, and the project completion time is 22 weeks.


Activity

Normal
Time

Crash
Time

Normal
Cost

Crash
Cost

A

12

8

8,000

12,000

B

14

10

5,000

7,500

C

8

8

10,000

10,000

D

5

3

6,000

8,000

E

4

3

5,000

7,000

F

6

5

9,000

12,000

G

10

8

5,000

8,000

If a deadline of 17 weeks is imposed, give the linear programming model for the crashing decision.


0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 10 more requests to produce the answer.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
​Susan Winslow has two alternative routes to travel from her home in Olport to her office in Lewisburg.
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Advanced-Math: Susan Winslow has two alternative routes to travel from her home in Olport to her office in Lewisburg. She can travel on Freeway 5 to Freeway 57 or on Freeway 55 to Freeway 91. The time distributions are as follows:

    Susan Winslow has two alternative routes to travel from her home in Olport to her office in Lewisburg. She can travel on Freeway 5 to Freeway 57 or on Freeway 55 to Freeway 91. The time distributions are as follows:Freeway 5Freeway 57Freeway 55Freeway 91RelativeRelativeRelativeRelativeTimeFrequencyTimeFrequencyTimeFrequencyTimeFrequency50.3040.1060.2030.3060.2050.2070.2040.3570.4060.3580.4050.2080.1070.2090.2060.1580.15Do a five-day simulation of each of the two combinations of routes using the random numbers below. Based on this simulation, which routes should Susan take if her objective is to minimize her total travel time?Freeway 56388554655Freeway...

  • Advanced-Math

     2. Susan Winslow has two alternative routes to travel from her home in Olport to her office in Lewisburg. She can travel on Freeway 5 to Freeway 57 or on Freeway 55 to Freeway 91. The time distributions are as follows:Freeway 5Freeway 57Freeway 55Freeway 91RelativeRelativeRelativeRelativeTimeFrequencyTimeFrequencyTimeFrequencyTimeFrequency50.3040.1060.2030.3060.2050.2070.2040.3570.4060.3580.4050.2080.1070.2090.2060.1580.15Do a five-day simulation of each of the two combinations of routes using the random numbers below. Based on this simulation, which routes should Susan take if her objective is to minimize her total travel time?Freeway...

  • Amy has two ways to travel from her home in Norco to her office in Los...

    Amy has two ways to travel from her home in Norco to her office in Los Angeles. One is to go via the 10 Freeway, and the other is to go via 60 Freeway. In order to determine which way she should travel on a daily basis, Amy has recorded the travel times for samples of ten trips via the 10 Freeway and ten trips via the 60 Freeway. The following table gives the travel times (in minutes) for the...

  • Amy has two ways to travel from her home in Norco to her office in Los...

    Amy has two ways to travel from her home in Norco to her office in Los Angeles. One is to go via the 10 Freeway, and the other is to go via 60 Freeway. In order to determine which way she should travel on a daily basis, Amy has recorded the travel times for samples of ten trips via the 10 Freeway and ten trips via the 60 Freeway. The following table gives the travel times in minutes) for the...

  • Please answer neatly and correctly! Amy has two ways to travel from her home in Norco...

    Please answer neatly and correctly! Amy has two ways to travel from her home in Norco to her office in Los Angeles. One is to go via the 10 Freeway, and the other is to go via 60 Freeway. In order to determine which way she should travel on a daily basis, Amy has recorded the travel times for samples of eight trips via the 10 Freeway and eight trips via the 60 Freeway. The following table gives the travel...

  • Joe and Susan are married. They have two children, Jack and Jill ages 4 and 6....

    Joe and Susan are married. They have two children, Jack and Jill ages 4 and 6. In 2020, they had the following transactions 1 Joe has taxable wages of $125,000. 2 Susan has taxable wages of $200,000 3 Interest income of $700 4 Their joint stock portfolio was valued at $39,000 on January 1, 2019. On December 31, 2019 it was valued at $47,000. 5. They paid mortgage interest of $22,000 on their primary residence. 6. They paid $6,000 of...

  • Paragraph 2 Styles . 4 5 6 The "SUPER" project has the following activity lists, normal...

    Paragraph 2 Styles . 4 5 6 The "SUPER" project has the following activity lists, normal time and cost and crash time and cost. Predecessor Normal Time Crash Time Normal Cost Crash Cost Activity Activity (Weeks) (Weeks) A 4 3 8,000 9,000 B А 5 3 16,000 20,000 C A 4 3 12,000 14,000 D B 6 5 34,000 35,000 E 6 3 42,000 45,000 F D 5 4 16,000 16,500 E 7 5 66,000 72,000 9 H G 4...

  • Table of Crashing DecisionACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHA...323,000...

    Table of Crashing DecisionACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHA...323,0003,300B...648,0009,000CA114,0004,000      DA543,5004,000EB434,7505,500FC222,0002,000      GD114,0004,000HD,F323,5003,750IE,G323,0004,250JE215,0007,000Since no indirect cost nor penalty cost information is offered, please consider the schedule and crash cost issues only.1. Using Table of Crashing Decision, what is the earliest completion time of this project if normal times are used for all activities?A. fewer than 13 weeks; B. 13 weeks; C. 14 weeks; D. more than 14 weeks2. Using Table of Crashing Decision, what is the minimum time schedule for this project?A. fewer than 8 weeks; B. 8...

  • Software Installation: You are the project manager of the software installation project (see figure & table)...

    Software Installation: You are the project manager of the software installation project (see figure & table) below. You would like to find the minimum-cost schedule for your project. There is a $1,000-per-week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,500 per week. Oo un D FINISH START START I Normal Normal Crash Crash Max reduction $ per Week Activity Time Cost Time Cost AI 5...

  • Can someone walk me through manual steps to solve e, f, and g? The Farmer's American...

    Can someone walk me through manual steps to solve e, f, and g? The Farmer's American Bank of Leesburg is planning to install a new computerized accounts system. Bank management has determined the activities required to complete the project, the precedence relationships of the activities, and activity time estimates, as shown in the following table: Time Estimates (weeks) Activity Activity Activity Description Position recruiting System development Predecessor a C A 5 17 ? -- 7 3 12 15 System training...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT