100, 000 100, 000 (a) Rp = = 50units / hr - 50 * 5 * 2000-

60(0.95) 50 b)Tc- 1.14min

Ts-1.14 minutes

= Minint > 42.0/1.04(0.93) 43.4 44u, orkers

(c)n w/11 44 / 1.4 31.43-32workstations

L= 32(3) = 96 m

IN CASE OF ANY DOUBTS OR CORRECTIONS FEEL FREE TO COMMENT BELOW

PLEASE RATE MY ANSWER BY HITTING ??

THANK YOU

Add a comment
Know the answer?
Add Answer to:
t nc automated stations, and (e) labor efficiency on the line. 4.6 A manual assembly line...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A product whose annual demand = 75,000 units is produced on a manual assembly line. The...

    A product whose annual demand = 75,000 units is produced on a manual assembly line. The line operates 50 wk/year, 5 shifts/wk, and 7.5 hr/shift. Work content time = 48.9 min. Line efficiency = 0.97, balancing efficiency = 0.93, and repositioning time = 8 sec. Determine (a) Hourly production rate, (b) Number of workers needed, and (c) Number of workstations if the manning level is 1.333. [15 pts] – Note: must show computational details and circle your final answers inual...

  • 9. A new product is to be assembled on a 100% manual assembly line. The line is designed to produce 120,000 units/yr. Work content time for the product is 39.5 min. The assembly line will operate...

    9. A new product is to be assembled on a 100% manual assembly line. The line is designed to produce 120,000 units/yr. Work content time for the product is 39.5 min. The assembly line will operate 50 wklyr, 5 shifts/wk, 8 hr/shift. Expected line efficiency is 96%. There will be one worker per station. Determine (a) average hourly production rate, (b) cycle time, and (c) ideal minimum number of workstations.(6 pts) 9. A new product is to be assembled on...

  • A rider lawn mower is produced on a manual assembly line. Work content time=49.5 min. The...

    A rider lawn mower is produced on a manual assembly line. Work content time=49.5 min. The line has 25 workstations with a manning level = 1.2. Available shift time per day = 8 hr, but equipment downtime during the shift reduces actual production time to 7.5 hr on average. This results in an average daily production of 244 units/day. Repositioning time per worker = 5% of cycle time. Determine (a) line efficiency, (b) balancing efficiency, and (c) repositioning time.

  • 4.22 The table below lists the work elements in minutes to be performed on assembly line...

    4.22 The table below lists the work elements in minutes to be performed on assembly line with precedence requirements. Annual demand is 60000 units. The line will operate on shift (2000 hr/yr). Line efficiency is expected 95% and repositioning time is 6 sec. The table below defines the precedence relationships and element times for a new model toy. (a) Construct the precedence diagram for this job. (b) If the ideal cycle time = 1.1 min. repositioning time = 0.1 min,...

  • Suppose a 20-station automatic assembly line with no storage or slack between stations is being planned...

    Suppose a 20-station automatic assembly line with no storage or slack between stations is being planned for a major automation thrust in the manufacturing plant where you are employed as the automation engineer. A cycle time objective has been set at 10 seconds in order to meet production quotas of 2000 units per eight-hour shift. a) Assuming no station jamming at all, what is the ideal production rate of this line? Can the production quota of 2000 units per eight-hour...

  • 8. If a line is balanced with 80 percent efficiency, the "balance delay" will be: 20 percent. B. 80 pe...

    8. If a line is balanced with 80 percent efficiency, the "balance delay" will be: 20 percent. B. 80 percent. C. 100 percent. D. unknown, since balance delay is not related to efficieney. E. depends on the next operation. 9. A common goal in designing process layouts is: A. minimizing the number of workers. B. minimizing number of machines. minimizing transportation costs. maximizing workstation productive time E. maximizing transportation distances. 07) vnit 10. The maximum allowable cycle time is computed...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT