Question

Suppose a 20-station automatic assembly line with no storage or slack between stations is being planned...

Suppose a 20-station automatic assembly line with no storage or slack between stations is being planned for a major automation thrust in the manufacturing plant where you are employed as the automation engineer. A cycle time objective has been set at 10 seconds in order to meet production quotas of 2000 units per eight-hour shift.

a) Assuming no station jamming at all, what is the ideal production rate of this line? Can the production quota of 2000 units per eight-hour shift be met? What is the throughput time?

b) Assuming ideal component quality and considering station malfunction. The station malfunction rate will be fifty out of 10,000 cycles. The repair time for station malfunction is 12 minutes. What is the production rate? Can the production quota of 2000 units per eight-hour shift be met? What is the percent downtime? What is the efficiency of this line? What is the throughput time?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

no. of (station a。 stime auaikbuhour/shift riguered prvelaetion 200o umit /shif.t a) asuminy no station jamming at al tim ava2 b) No of tailure in (oooo cycl 5 in ieldに-So z lo fasidiez ニチ200 sec Readluution cueution time 72oo sec = 2し600 sec 2 Ii) D

Add a comment
Know the answer?
Add Answer to:
Suppose a 20-station automatic assembly line with no storage or slack between stations is being planned...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 9. A new product is to be assembled on a 100% manual assembly line. The line is designed to produce 120,000 units/yr. Work content time for the product is 39.5 min. The assembly line will operate...

    9. A new product is to be assembled on a 100% manual assembly line. The line is designed to produce 120,000 units/yr. Work content time for the product is 39.5 min. The assembly line will operate 50 wklyr, 5 shifts/wk, 8 hr/shift. Expected line efficiency is 96%. There will be one worker per station. Determine (a) average hourly production rate, (b) cycle time, and (c) ideal minimum number of workstations.(6 pts) 9. A new product is to be assembled on...

  • t nc automated stations, and (e) labor efficiency on the line. 4.6 A manual assembly line...

    t nc automated stations, and (e) labor efficiency on the line. 4.6 A manual assembly line is being designed for a product whose annual demand is 100,000 units The line will operate 50 wk/yr, 5 shifts/wk, and 8 hr/shift. Work units will be attached to a con- moving conveyor. Work content time is 42.0 min.Assume line efficiency is 0.95, bal- is 0.93 or slightly less, repositioning time is 6 sec, and manning level is 1.4 Determine (a) average hourly production...

  • 4.22 The table below lists the work elements in minutes to be performed on assembly line...

    4.22 The table below lists the work elements in minutes to be performed on assembly line with precedence requirements. Annual demand is 60000 units. The line will operate on shift (2000 hr/yr). Line efficiency is expected 95% and repositioning time is 6 sec. The table below defines the precedence relationships and element times for a new model toy. (a) Construct the precedence diagram for this job. (b) If the ideal cycle time = 1.1 min. repositioning time = 0.1 min,...

  • An assembly line is to operate eight hours per day with a desired output of 160...

    An assembly line is to operate eight hours per day with a desired output of 160 units per day. The following table contains information on this product's task times and precedence relationships: IMMEDIATE PREDECESSOR TASK TIME (SECONDS) 100 TASK A 70 D 50 40 C C. D 70 140 G H b. What is the required workstation cycle time meet the desired output rate? (Round your answer to the nearest whole number.) Workstation cycle time seconds per unit c. Balance...

  • The Walton Toy Company manufactures a line of dolls and a sewing kit. Demand for the...

    The Walton Toy Company manufactures a line of dolls and a sewing kit. Demand for the company’s products is increasing, and management requests assistance from you in determining an economical sales and production mix for the coming year. The company has provided the following data: Product Demand Next year (units) Selling Price per Unit Direct Materials Direct Labor Debbie 66,000 $ 37.00 $ 4.30 $ 3.50 Trish 58,000 $ 5.00 $ 1.20 $ 0.84 Sarah 51,000 $ 35.50 $ 8.84...

  • The Walton Toy Company manufactures a line of dolls and a sewing kit. Demand for the...

    The Walton Toy Company manufactures a line of dolls and a sewing kit. Demand for the company’s products is increasing, and management requests assistance from you in determining an economical sales and production mix for the coming year. The company has provided the following data: Product Demand Next year (units) Selling Price per Unit Direct Materials Direct Labor Debbie 75,000 $ 28.00 $ 5.20 $ 4.80 Trish 67,000 $ 5.70 $ 2.10 $ 1.36 Sarah 60,000 $ 33.50 $ 10.19...

  • The Walton Toy Company manufactures a line of dolls and a sewing kit. Demand for the...

    The Walton Toy Company manufactures a line of dolls and a sewing kit. Demand for the company’s products is increasing, and management requests assistance from you in determining an economical sales and production mix for the coming year. The company has provided the following data: Product Demand Next year (units) Selling Price per Unit Direct Materials Direct Labor Debbie 72,000 $ 18.00 $ 4.90 $ 4.05 Trish 64,000 $ 6.50 $ 1.80 $ 1.89 Sarah 57,000 $ 30.00 $ 9.74...

  • The Walton Toy Company manufactures a line of dolls and a sewing kit. Demand for the...

    The Walton Toy Company manufactures a line of dolls and a sewing kit. Demand for the company’s products is increasing, and management requests assistance from you in determining an economical sales and production mix for the coming year. The company has provided the following data: Product Demand Next year (units) Selling Price per Unit Direct Materials Direct Labor Debbie 54,000 $ 23.00 $ 4.70 $ 5.40 Trish 46,000 $ 5.00 $ 1.50 $ 1.80 Sarah 39,000 $ 30.00 $ 7.04...

  • The Walton Toy Company manufactures a line of dolls and a sewing kit. Demand for the...

    The Walton Toy Company manufactures a line of dolls and a sewing kit. Demand for the company’s products is increasing, and management requests assistance from you in determining an economical sales and production mix for the coming year. The company has provided the following data: Product Demand Next year (units) Selling Price per Unit Direct Materials Direct Labor Debbie 63,000 $ 21.00 $ 5.60 $ 4.20 Trish 55,000 $ 7.50 $ 2.40 $ 1.44 Sarah 48,000 $ 36.50 $ 8.39...

  • The Walton Toy Company manufactures a line of dolls and a sewing kit. Demand for the...

    The Walton Toy Company manufactures a line of dolls and a sewing kit. Demand for the company's products is increasing, and management requests assistance from you in determining an economical sales and production mix for the coming year. The company has provided the following data: Product Debbie Trish Sarah Mike Sewing kit Demand Next Selling year Price (units) per Unit 71,000 $17.50 63,000 $ 6.00 56,000 $31.50 47,600 $13.00 346,000 $10.10 Direct Materials $4.80 $1.70 $9.59 $4.10 $5.30 Direct Labor...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT