Chris Sandvig Irrigation, Inc., has summarized the price list from four potential suppliers of an underground control valve. See the table below. Annual usage is 1,100 valves; order cost is $14 per order; and annual inventory holding costs are $7.55 per unit. Vendor A Vendor B Vendor C Vendor D Quantity 1-14 15-24 25-99 100-199 200-399 400+ Price $35.00 34.75 33.55 32.35 31.15 30.75 Quantity 1-24 25-99 100-199 200-399 400+ Price $34.75 34.00 32.80 31.60 30.50 Quantity 1-49 50-149 150-299 300+ Price $34.50 33.75 32.50 31.10 Quantity 1-149 150-299 300+ Price $34.25 33.00 31.00 Which vendor should be selected and what order quantity is best if Sandvig Irrigation wants to minimize total cost? Chris Sandvig Irrigation should order units at a time from V (enter your response as a whole number)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

EOQ = sqrt(2*Annual demand*Order cost/Holding cost) = sqrt(2*1100*14/7.55) = 64 (Round off)

Total cost = Annual Demand/EOQ*Order cost + EOQ/2*Holding cost + Price*Annual demand

1) Vendor A: EOQ = 64, Price = 33.55

Total cost = 1100/64*14 + 64/2*7.55 + 1100*33.55 = 37387

2) Vendor A: EOQ = 100, Price = 32.35

Total cost = 1100/100*14 + 100/2*7.55 + 1100*32.35 = 36117

3) Vendor A: EOQ = 200, Price = 31.15

Total cost = 1100/200*14 + 200/2*7.55 + 1100*31.15 = 35097

4) Vendor A: EOQ = 400, Price = 30.75

Total cost = 1100/400*14 + 400/2*7.55 + 1100*30.75 = 35374

5) Vendor B: EOQ = 64, Price = 34

Total cost = 1100/64*14 + 64/2*7.55 + 1100*34 = 37882

6) Vendor B: EOQ = 100, Price = 32.8

Total cost = 1100/100*14 + 100/2*7.55 + 1100*32.8 = 36612

7) Vendor B: EOQ = 200, Price = 31.6

Total cost = 1100/200*14 + 200/2*7.55 + 1100*31.6 = 35592

8) Vendor B: EOQ = 400, Price = 30.5

Total cost = 1100/400*14 + 400/2*7.55 + 1100*30.5 = 35099

9) Vendor C: EOQ = 64, Price = 33.75

Total cost = 1100/64*14 + 64/2*7.55 + 1100*33.75 = 37607

10) Vendor C: EOQ = 150, Price = 32.5

Total cost = 1100/150*14 + 150/2*7.55 + 1100*32.5 = 36419

11) Vendor C: EOQ = 300, Price = 31.1

Total cost = 1100/300*14 + 300/2*7.55 + 1100*31.1 = 35394

12) Vendor C: EOQ = 64, Price = 34.25

Total cost = 1100/64*14 + 64/2*7.55 + 1100*34.25 = 38157

13) Vendor C: EOQ = 150, Price = 33

Total cost = 1100/150*14 + 150/2*7.55 + 1100*33 = 36969

14) Vendor C: EOQ = 300, Price = 31

Total cost = 1100/300*14 + 300/2*7.55 + 1100*31 = 35284

Lowest cost scenario is Case 3:

Vendor A

Order quantity = 200

Add a comment
Know the answer?
Add Answer to:
Chris Sandvig Irrigation, Inc., has summarized the price list from four potential suppliers of an underground...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Chris Sandvig Irrigation, Inc., has summarized the price list from four potential suppliers of an underground...

    Chris Sandvig Irrigation, Inc., has summarized the price list from four potential suppliers of an underground control valve. See the table below. Annual usage is 800 valves; order cost is $12 per order; and annual inventory holding costs are $5.25 per unit. Vendor A Quantity Price 1-14 $35.00 15-24 34.75 25-99 33.55 100-199 32.35 200-399 31.15 400+ 30.75 Vendor B Quantity Price 1-24 $34.75 25-99 34.00 100-199 32.80 200-399 31.60 400+ 30.50 Vendor C Quantity Price 1-49 $34.50 50-149 33.75...

  • Chris Sandvig Irrigation, Inc., has summarized the price list from four potential suppliers of an underground...

    Chris Sandvig Irrigation, Inc., has summarized the price list from four potential suppliers of an underground control valve. See the table below. Annual usage is 1,100 valves; order cost is $13 per order; and annual inventory holding costs are $7.55 per unit. Vendor A Quantity Price 1-14 $35.00 15-24 34.75 25-99 33.55 100-199 32.35 200-399 31.15 400+ 30.75 Vendor B Quantity Price 1-24 $34.75 25-99 34.00 100-199 32.80 200-399 31.60 400+ 30.50 Vendor C Quantity Price 1-49 $34.50 50-149 33.75...

  • Chris Sandviq Irrigation, Inc., has summarized the price list from 3 potential suppliers of an underground...

    Chris Sandviq Irrigation, Inc., has summarized the price list from 3 potential suppliers of an underground control valve as shown in Table 6. Annual usage is 2,400 valves, order cost is $10 per order, and annual inventory holding costs are $%3.33 per unit. Determine which vendor should be selected. Justify your selection. Table 6 VENDORA VENDOR B VENDOR C QUANTITYPRICE() QUANTITY PRICE ($) 34.75 34.00 32.80 31.60 30.50 QUANTITY 1-99 100-199 200-399 400+ PRICE ($) 34.50 33.75 32.50 31.10 1-49...

  • Chris Sandvig Irrigation, Inc., has summarized the price list from four potential suppliers of an underground...

    Chris Sandvig Irrigation, Inc., has summarized the price list from four potential suppliers of an underground control valve. See the table below. Annual usage is 700 valves; order cost is $7 per order; and annual inventory holding costs are $7.55 per unit. Vendor A Quantity Price 1-9 $35.00 10-14 34.75 15-49 33.55 50-99 32.35 100-299 31.15 300+ 30.75 Vendor B Quantity Price 1-14 $34.75 15-49 34.00 50-99 32.80 100-299 31.60 300+ 30.50 Vendor C Quantity Price 1-24 $34.50 25-74 33.75...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT