In the basic EOQ model, which of the following could lead to stock-outs?
smaller than average lead time |
||
higher consumption during the lead time |
||
higher reorder points |
||
lower consumption during the lead time |
Answer: Option B
Explanation: Higher consumption during lead time can lead to stock out.
In the basic EOQ model, which of the following could lead to stock-outs? smaller than average...
1. What are the six assumptions of the EOQ model? 2. Average daily demand for a product is normally distributed with a mean of 25 units and a standard deviation of 4 units. Lead time is fixed at 20 days. What reorder point provides for a service level of 95 percent (z=1.65)?
Which of the following is NOT an assumption of the EOQ model? a. Continuous review b. Demand is known and constant c. Lead time is known and constant d. All demand is satisfied e. All of the above are assumptions of the EOQ model
1. Basic EOQ Question: The inventory manager of ABC, Ltd., wants to order flour for its bakery in a cost effective manner. The bakery uses an average of 12,000 bags a year. Preparing an order and receiving a shipment of flour involves a cost of $40 per order. Annual carrying costs are $37.50 per bag. REQUIRED: A. Determine the economic order quanity. B. What is the average number of bags on hand? C How many orders will there be per...
. Basic EOQ model The local Verizon dealer must decide how many Model XYZ cell phones to order for his business. Each phone wholesales for $30. Demand for the phone has been running at an average of 8 per day for the 300 days of operation each year. The cost of ordering is estimated to be $50 per order and the holding cost is estimated to be 25% of the wholesale cost. a. What quantity should he purchase? b. If...
please read before solving thanks A products with an annual demand of 1000 units has EOQ (Economic Order Quantity)- 80. The demand during the lead time follows a normal probability distribution with u- 25 and s-5 during the reorder period. a How much safety stock is required, if the firm desires at most a 2% probability of a 4. stockout on any given order cycle? b. If a manager sets the reorder point at 30, what is the probability of...
Which of the following is a difference between the EOQ and the EPQ models? a)In the EOQ model, lead time is known, but not in the EPQ model b)In the EOQ model, shortages are allowed, but not in the EPQ model. c)In the EOQ model, additional inventory is received all at once, but not in the EPQ model. d)In the EOQ model, there are quantity discounts available, but not in the EPQ model
In the Quantity Discount EOQ inventory model, which of the following items is NOT considered relevant in determining the lowest cost order quantity? A. The cost of placing an order. B. The individual purchase price of an item of inventory. C. The cost of carrying an item in inventory. D. The variability of demand during lead time. E. The annual demand for the product.
For questions 26-75, choose the most appropriate choice 26. In the A-B-C classification system, items represent 50%-60% of all items but only 10%-15% of the total value? A. A items B. B items C. C items D. A items plus B items E. B items plus C items 27. If no variations in demand during the item's lead time exist and no safety stock is needed, then the ROP will equal to: A. the EOC B. expected demand during lead...
Suppose inventory is managed using the order-up-to model. Which of the following actions will certainly lead to a higher order- up to level in all cases assume the characteristics of the demand process do not change A. Increase in the target in stock probability (for the same lead time) B. Decrease the target stock-out probability (for the same lead time) C. Increase in the lead time (for the same service level). A only Bonly Conly A and B Band A...
Using the reorder level-order quantity model, and assuming a safety stock of 800, what is the re-order point (R) given a daily demand of 300 units, a lead time of 5 days? 300 800 1500 2300 1100 Which of the following basic types of process structures needs to keep inventory of work-in-process component parts? Assemble to Order Make to Stock O None of the above Make to Order Engineer to Order Suppose a call center has one agent answering the...