Question

At the Boise Cascade Corporation, lumber mill logs arrive by truck and are scaled (measured to determine the number of board feet) before they are dumped into a log pond. The figure below shows the basic flow. Scaling Stations Trucks Enter Log Pond The mill manager must determine how many scale stations to have open during various times of the day. If too many stations are open, the scalers will have excessive idle time and the cost of scaling will be unnecessarily high. On the other hand, if too few scale stations are open, some log trucks will have to wait. The manager has studied the truck arrival patterns and has determined that throughout the day, trucks randomly arrive at 11 per hour on average. Each scale station can scale 4 trucks per hour (15 minutes each). If the manager knew how many trucks would arrive during the hour, she would know how many scale stations to have open. For example, 0-4 trucks, open 1 scale station; 5-8 trucks, open 2 scale stations, etc. However, the number of trucks is a random variable and is uncertain. Your task is to provide guidance for the decision. 1) Based on the mean rate of 11 trucks per hour, what probability distribution should be used? 2) Use the probabilities fromthe first probability distribution above to create a probability distribution for the number of scale stations to open. For example, 0-4 trucks, open 1 scale station; 5-8 trucks, open 2 scale stations, etc. What is the expected number of scale stations needed? Are there additional factors that should be considered? What are your recommendations for handling those factors? 3)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The number of trucks arriving per hour is a discrete random variable, with a given mean rate. It can be best modelled as Poisson distribution, and can be written as

P(x,\mu )=\frac{e^{-\mu }\mu ^{x}}{x!}\rightarrow \textup{ Given, }\mu =11

Now we are more interested to obtain the number of scale stations to open. Here, we note that a particular range of the parameter 'x' in above distribution corresponds to the number of stations required. Hence, we need to evaluate the sum of those probabilities, and map them to #stations (N). Let us map them as per below

P(N=1)\equiv P(0,\mu )+P(1,\mu )+P(2,\mu )+P(3,\mu )+P(4,\mu )

=e^{-11 }[\frac{11 ^{0}}{0!}+\frac{11 ^{1}}{1!}+\frac{11 ^{2}}{2!}+\frac{11 ^{3}}{3!}+\frac{11 ^{4}}{4!}]\approx 0.0151

P(N=2)\equiv P(5,\mu )+P(6,\mu )+P(7,\mu )+P(8,\mu )

  =e^{-11 }[\frac{11 ^{5}}{5!}+\frac{11 ^{6}}{6!}+\frac{11 ^{7}}{7!}+\frac{11 ^{8}}{8!}]\approx0.2169

P(N=3)\equiv P(9,\mu )+P(10,\mu )+P(11,\mu )+P(12,\mu )

  =e^{-11 }[\frac{11 ^{9}}{9!}+\frac{11 ^{10}}{10!}+\frac{11 ^{11}}{11!}+\frac{11 ^{12}}{12!}]\approx0.4567

P(N=4)\equiv P(13,\mu )+P(14,\mu )+P(15,\mu )+P(16,\mu )

  =e^{-11 }[\frac{11 ^{13}}{13!}+\frac{11 ^{14}}{14!}+\frac{11 ^{15}}{15!}+\frac{11 ^{16}}{16!}]\approx0.25538

P(N=5)\equiv P(17,\mu )+P(18,\mu )+P(19,\mu )+P(20,\mu )

=e^{-11 }[\frac{11 ^{17}}{17!}+\frac{11 ^{18}}{18!}+\frac{11 ^{19}}{19!}+\frac{11 ^{20}}{20!}]\approx0.05125

P(N=5)\equiv P(21,\mu )+P(22,\mu )+P(23,\mu )+P(24,\mu )

  =e^{-11 }[\frac{11 ^{21}}{21!}+\frac{11 ^{22}}{22!}+\frac{11 ^{23}}{23!}+\frac{11 ^{24}}{24!}]\approx0.00447

Similarly, probabilities for higher number of scaling stations required can be evaluated. But since the sum of above probabilities is 0.9998, so for practical purposes we can stop at this point. The average number of scaling stations required can now be evaluated as

E(N)=\sum n\times P(N=n)

=1\times 0.0151+2\times 0.2169+3\times 0.4567+4\times0.05125+5\times 0.00447\approx 2.04

The expected no of scale stations needed is very close to the value 2.

There could be many additional factors. Traffic conditions may sometimes create some bunch of trucks to be stranded, which will then arrive altogether, thus creating a sudden burst in demand. The scaling station is also a machine in itself, which is subject to failure. So allowance must be made for such a n eventuality. For ex, at least 6 scaling stations should be operationsla to create redundancy.

Add a comment
Know the answer?
Add Answer to:
At the Boise Cascade Corporation, lumber mill logs arrive by truck and are scaled (measured to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • QUESTION 1 Customers arrive at a hair salon according to a Poisson process with an average of 1...

    QUESTION 1 Customers arrive at a hair salon according to a Poisson process with an average of 16 customers per hour. Which of the following is most likely true, based on this information: a. The hair salon serves customers on a walk-in basis (rather than by appointment times) b. If 10 customers arrive in the first hour, it is likely that 22 customers will arrive in the next hour. c. If the salon can serve an average of 20 customers...

  • HDT Truck Company HDT Truck Company has been located in Crown Point, Indiana, since 1910. Its...

    HDT Truck Company HDT Truck Company has been located in Crown Point, Indiana, since 1910. Its only products— large trucks—are built to individual customer specifications. The firm once produced automobiles but dropped out of the auto business in 1924. The firm nearly went out of business in the late 1930s, but by 1940 its fortunes were buoyed by receipt of several military contracts for tank retrievers—large-wheeled vehicles that can pull a disabled tank onto a low trailer and haul it...

  • Three days before Hurricane Harvey hit Texas, hardware retailer Home Depotreceived an alert from a weather...

    Three days before Hurricane Harvey hit Texas, hardware retailer Home Depotreceived an alert from a weather service and activated its disaster-response plan to get supplies to those in the storm’s path, while turning a profit, too. Over the next three days—as Harvey gained power and made landfall early on Saturday—the world’s largest home improvement retailer set up a temporary hurricane command center at its Atlanta headquarters. It told managers to freeze prices and move plywood, generators, chainsaws and other storm-related...

  • As a digital retailer,how does alibaba provide value to Chinese consumers ? whit sets of values...

    As a digital retailer,how does alibaba provide value to Chinese consumers ? whit sets of values are unique to the chinese market? Given that alibaba does not own or distribute any of the merchandise exchanged on its sites, describes what factors had to develop for the company to succeed. Analyze Alibaba's business model relative to all the different forms of digital and online marketing covered in this chapter. Can alibaba succeed in countries outside of China? Why or why not?...

  • 10. Write a one-page summary of the attached paper? INTRODUCTION Many problems can develop in activated...

    10. Write a one-page summary of the attached paper? INTRODUCTION Many problems can develop in activated sludge operation that adversely affect effluent quality with origins in the engineering, hydraulic and microbiological components of the process. The real "heart" of the activated sludge system is the development and maintenance of a mixed microbial culture (activated sludge) that treats wastewater and which can be managed. One definition of a wastewater treatment plant operator is a "bug farmer", one who controls the aeration...

  • SYNOPSIS The product manager for coffee development at Kraft Canada must decide whether to introduce the...

    SYNOPSIS The product manager for coffee development at Kraft Canada must decide whether to introduce the company's new line of single-serve coffee pods or to await results from the product's launch in the United States. Key strategic decisions include choosing the target market to focus on and determining the value proposition to emphasize. Important questions are also raised in regard to how the new product should be branded, the flavors to offer, whether Kraft should use traditional distribution channels or...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT