Excavation and removal of earth has to be done in a road project. One excavator with...
Correct answer is 238 cy/hr. How do I get this? A contractor has a project involving the construction of a small manufacturing plant. The contractor has selected a borrow site and has decided to use 27-cubic yard dump trucks to haul the needed fill material. The contractor has decided to use a hydraulic excavator with a shovel attachment to load the trucks. The excavator has expected productivity as 422cy/hr at 100% efficiency, and the truck cycle time excluding loading is...
Part 2 Based upon the results to part 1, the project requires hauling materials to, or from, the site. The following equipment is available for earthwork operations: - One 5-cy heaped capacity bucket loader; a 0.5 min cycle time; 90% fill capacity. - One 7-cy heaped capacity bucket loader; a 0.6 min cycle time; 90% fill capacity. 45.9-cy heaped capacity off-road trucks; a 0.5 min dump time; 100% fill capacity. - Loaded trucks travel through the following three sections: Haul...
please help me. Problem 2: Evaluate cost and production using a 3-cy hoe to load wet gravel (2980 lb/lcy) into 14 cy trucks. Assume a bucket fill factor of 105% and that the hoe bucket swing cycle time is 24 sec. the truck empty weight is 36860 lb, and a rated payload of 40000 lb. Dump time will be 1.3 min. the haul distance is 2.5 miles from the pit to the plant up a 3% grade. The rolling resistance...
Please solve problem 1 and show formulas used Tables for reference: Homework 6- Chapter 9 Problem 1: A crawler hoe having a 2 -cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under each of the stated conditions. The maximum digging depth of the machine is 22 ft. Determine the cost per bank cubic yard for each condition. (Condition 1: 315 bey/hr, S0.346/bcy; condition 2: 289 bey/hr, S0.377/bcy;...
(50) 7. Analyze the following operation. A 385C Excavator will be used to load material into a CAT 740 (no ejector) articulated truck. The excavator is equipped with a 6 cy heaped bucket and is capable of cycling every 30 seconds. The material being loaded weighs 3,300 lbs cy. The job efficiency is 90%. The trucks will be hauling the nmaterial 4000 feet over a road with a total rolling resistance of 9% to the dumpsite and 10% total rolling...
Part 2 Based upon the results to part 1, the project requires hauling materials to, or from, the site. The following equipment is available for earthwork operations: - One 5-cy heaped capacity bucket loader; a 0.5 min cycle time; 90% fill capacity. - One 7-cy heaped capacity bucket loader; a 0.6 min cycle time; 90% fill capacity. 45.9-cy heaped capacity off-road trucks; a 0.5 min dump time; 100% fill capacity. - Loaded trucks travel through the following three sections: Haul...
Part 1 Complete the following Earthwork Sheet Material: Earth and Gravel, Swell Factor: 83 Strip fill(cy Total till och Total cut beyl Adj fill (byl Sum (beyl Mass ordinate 1.23 056 2.37 1.20 2.36 3.07 3.60 3.77 3.09 3.01 4.65 Strip cut (boyil 0.04 1.04 097 3.22 2.08 2.33 2.51 1.85 161 1.74 0.88 109 35.70 5.58 18 3.12 2.03 6.77 2.01 2.53 0.82 1.08 1.20 1.92 1.59 1.82 3.95 3.25 2.74 150 7.42 556 80 End-area End area cut...
HDT Truck Company HDT Truck Company has been located in Crown Point, Indiana, since 1910. Its only products— large trucks—are built to individual customer specifications. The firm once produced automobiles but dropped out of the auto business in 1924. The firm nearly went out of business in the late 1930s, but by 1940 its fortunes were buoyed by receipt of several military contracts for tank retrievers—large-wheeled vehicles that can pull a disabled tank onto a low trailer and haul it...