Question

Consider a project to build a bridge over a river gorge. What are some of the...

Consider a project to build a bridge over a river gorge. What are some of the resource constraints that would make this project challenging?
thank you
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer: The river gorges are a typical geographical terrain and there may be four major resource constraints that a project of building a gorge over it may face. They are

  1. People: These projects are risky in nature and hence experts that are not risk adverse are required and they are not easy to find
  2. Equipment: Building such bridges require specialty equipment and at times it is not easy to procure such equipment
  3. Money: Such a project may require huge budgets and the project may face financial constraints
  4. Supplies: Such locations are present in the difficult geographical regions and hence getting and maintaining supplies like materials , food and so on can prove to be difficult
Add a comment
Know the answer?
Add Answer to:
Consider a project to build a bridge over a river gorge. What are some of the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • [2 point) The New River Gorge Bridge in West Virginia is a steel arch bridge 518...

    [2 point) The New River Gorge Bridge in West Virginia is a steel arch bridge 518 min length. How much does the total length of the roadway decking change between temperature extremes of -20.0*C and 35.0°C? The result indicates the size of the expansion joints that must be built into the structure. 5. (2 point) Two concrete spans of a 250-m-long bridge are placed end to end so that no room is allowed for expansion. If a temperature increase of...

  • A company is considering building a bridge across a river

    A company is considering building a bridge across a river. The bridge would cost $2 million to build and nothing to maintain. The following table shows the company¡¯s anticipated demand over the lifetime of the bridge:Price per crossing ($) 8 7 6 5 4 3 2 1 0Number of crossings (in Thousands) 0 100 200 300 400 500 600 700 800a. If the company were to build the bridge, what would be its profit-maximizing price? Would that be the efficient...

  • what is build transfer operate BTO scheme and why its not viable for bridge project

    what is build transfer operate BTO scheme and why its not viable for bridge project

  • Choose one of the following projects: a project to build a hotel in Japan, a project...

    Choose one of the following projects: a project to build a hotel in Japan, a project to build a new prototype for an electric car, or an IT project to create a new internal accounting software system. As a project manager, what are some of the specific cost estimation problems you might encounter? Considering those potential problems, what could you do to help ensure accurate cost estimation? Please limit to 250 words. Thank you!

  • A town council is considering building a new bridge over a small river that runs through the town to reduce congestion on the existing bridge and reduce commuting times. Each of 1,000 commuters who mu...

    A town council is considering building a new bridge over a small river that runs through the town to reduce congestion on the existing bridge and reduce commuting times. Each of 1,000 commuters who must cross the bridge would experience a benefit of $20 per day from saving commuting time. The bridge would be financed through increased property taxes that amount to $1 per day for each of the 40,000 households in the town.  Would the bridge pass a...

  • 2 Problem 5-6 (Algo) A project to build a new bridge seems to be going very...

    2 Problem 5-6 (Algo) A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 65% complete. The planners were expecting to be only58 % through the third activity at this time. The first activity involves prepping the site for the bridge....

  • please help! Question 5 (1 point) Tallula is standing on a bridge over the Credit River....

    please help! Question 5 (1 point) Tallula is standing on a bridge over the Credit River. She throws a rock from a height of 73.1 m above the water. The rock is thrown with a velocity of 7.57 m/s at an angle of elevation of 31.0°. What is the height of the rock above the water 1.23 s after it is thrown? Give your answer in metres. Your Answer: Answer

  • Bob is standing on a bridge over the Credit River. He throws a 0.0830-kg rock straight...

    Bob is standing on a bridge over the Credit River. He throws a 0.0830-kg rock straight down with a speed of 10.51 m/s. The rock hits the water 1.47 s later. What was the height of the rock above the water in metres at the moment it was thrown? Enter the magnitude ONLY no SIGN. Enter your final answer up to 5 decimal places. Do not enter units.

  • A company has a contract to build a bridge for $100,000 with an estimated time to...

    A company has a contract to build a bridge for $100,000 with an estimated time to completion of three years. A reliable total cost estimate for the project would be $60,000. In the first year of the project, the company incurred a cost of $24,000. (a) Assume that the contractor bases the degree of completion on the percentage of total costs incurred to date. Under the percentage-of-completion method, what amount of gross profit the company will report in the first...

  • 1)How did project GLOBE build on and extend Hofstede’s analysis? What unique contributions are associated with...

    1)How did project GLOBE build on and extend Hofstede’s analysis? What unique contributions are associated with project GLOBE? 2)What are some categories of cultural differences that help make one country or region of the world different from another? In each case, describe the value or norm, and explain how it would result in different behavior in two or more countries. If you like, use the countries in this chapter as your point of reference.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT