A company has a contract to build a bridge for $100,000 with an estimated time to...
During 20x5, the Ibti Construction Company obtained a $15 million contract to build a bridge. The costs incurred, estimated costs to complete and the billings made on the contract for the period 20x5 – 20x6 are as follows: 20x5 20x6 Costs incurred during the year $3,000,000 $5,000,000 Expected costs to complete 9,000,000 6,000,000 Billings 7,500,000 - Ibti uses the percentage of completion method. Costs incurred relative to total project costs are used to measure the percentage of completion at the...
Google Fiber signed a contract and hired Patrick Wirelines to build a new data center in Aksarben. They signed a fixed price contract for 80,000. Additional information about the contract is included in the schedule with the problem worksheets. Required 1. Using the Percentage of Completion Method for each year report the amount of Revenue and Gross Profit or Loss that should be recognized 2. Using the Completed Contract Method for each year report the amount of Revenue and Gross...
74 757. 2.) Frame Construction company's contract requires the construction of a bridge in 3 years. The expected cost of the bridge is $2 million and Frame will receive $2.5 million for the project. The actual costs incurred to complete the project were $500,000, $900,000, and $600,000, respectively during each of the 3 years. Progress payments received by Frame were $600,000, $1.2 million and $700,000 in each year respectively. Assuming that the percentage-of-completion method is used, what amount of gross...
1) A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes...
The contract price for a 3-year construction contract is $100 The actual cost and estimated costs for each vear are given below: Items 2016 2017 2018 Actual cost incurred each year $10 Estimated cost to complete $40 Under Percentage of Completion method (You first prepare the table I showed you in the class to make your calculations easier) S20 $30 1. Compute Actual cost incurred to date 2. Compute total estimated cost for each year 3. Compute estimated gross profit...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,330,000. During 2021, costs of $2,110,000 were incurred with estimated costs of $4,110,000 yet to be incurred. Billings of $2,610,000 were sent, and cash collected was $2,360,000. In 2022, costs incurred were $2,610,000 with remaining costs estimated to be $3,765,000. 2022 billings were $2,860,000 and $2,585,000 cash was collected. The project was completed in 2023 after additional costs of $3,910,000...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2023 after additional costs of $3,900,000...
At the beginning of 2013, the Harding Construction Company received a contract to build an office building for $10 million. Harding will construct the building according to specifications provided by the buyer, and the project is estimated to take three years to complete. According to the contract, Harding will bill the buyer in installments over the construction period according to a prearranged schedule. Information related to the contract is as follows: 2013 2014 2015 Cost incurred during the year $2,300,000...
1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows: 2016 2017 2018 Actual Construction costs incurred...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimated costs of $4,140,000 yet to be incurred. Billings of $2,640,000 were sent, and cash collected was $2,390,000. In 2019, costs incurred were $2,640,000 with remaining costs estimated to be $3,810,000. 2019 billings were $2,890,000 and $2,615,000 cash was collected. The project was completed in 2020 after additional costs of...