Question

74 757. 2.) Frame Construction companys contract requires the construction of a bridge in 3 years. The expected cost of the
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution -

$150,000

Explanation -

The gross profit realised for the first two years must be computed first. Then, the difference between the $500,000 final total gross profit on the project ($2.5mn − $2mn).

And gross profit for the first two years is the amount of gross profit recognised in the last (third) year. The % of completion at the end of the first two years is 70% (= $500,000 + $900,000)/$2mn).

The gross profit recognised through the end of year two is $350,000 [= .70($2.5mn − $2mn)]. Thus, gross profit for year three is $150,000 ($500,000 total gross profit on the project − $350,000).

Add a comment
Know the answer?
Add Answer to:
74 757. 2.) Frame Construction company's contract requires the construction of a bridge in 3 years....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Bigelow Contractors signed a contract to construct a storage facility for RGN manufacturing, Inc. The fixed-fee...

    Bigelow Contractors signed a contract to construct a storage facility for RGN manufacturing, Inc. The fixed-fee contract specifies that the facility is to be completed in three years. Bigelow uses the percentage-of-completion method (cost-to-cost approach) to account for its construction transactions. Information related to this contract is summarized in the following table. Contract price $ 2,000,000 2018 2019 2020 Actual construction costs incurred during the year $ 900,000 $ 300,000 $ 600,000 Construction costs incurred in prior years 0 900,000...

  • During 20x5, the Ibti Construction Company obtained a $15 million contract to build a bridge. The...

    During 20x5, the Ibti Construction Company obtained a $15 million contract to build a bridge. The costs incurred, estimated costs to complete and the billings made on the contract for the period 20x5 – 20x6 are as follows: 20x5 20x6 Costs incurred during the year $3,000,000 $5,000,000 Expected costs to complete 9,000,000 6,000,000 Billings 7,500,000 - Ibti uses the percentage of completion method. Costs incurred relative to total project costs are used to measure the percentage of completion at the...

  • Question 2 Ivanhoe Construction entered into a contract to construct a bridge for a contract price...

    Question 2 Ivanhoe Construction entered into a contract to construct a bridge for a contract price of $2.80 million. Construction began in 2019 and was completed in 2021. Below are the details of the transactions related to the contract: 2019 2020 $653,000 $806,000 1,436,600 541,000 2021 $709,900 Costs incurred during the year Estimated costs to complete Calculate the revenue, expenses and gross profit to be recognized each year using the percentage-of-completion method. (Round the percentage completion to 2 decimal places,...

  • On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2016, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2017, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2017 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2018 after additional costs of...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimat...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimated costs of $4,140,000 yet to be incurred. Billings of $2,640,000 were sent, and cash collected was $2,390,000. In 2019, costs incurred were $2,640,000 with remaining costs estimated to be $3,810,000. 2019 billings were $2,890,000 and $2,615,000 cash was collected. The project was completed in 2020 after additional costs of...

  • On December 31, 2017, Tri-State Construction Inc. signs a contract with the state of West Virginia...

    On December 31, 2017, Tri-State Construction Inc. signs a contract with the state of West Virginia Department of Transportation to manufacture a bridge over the New River. State anticipates the construction will take three years. The company’s accountants provide the following contract details relating to the project: Contract price $780 million Estimated construction costs $600 million Estimated total profit $180 million During the three-year construction period, Tri-State incurred costs as follows: 2018 $ 60 million 2019 $360 million 2020 $180...

  • 1) A construction company entered into a fixed-price contract to build an office building for $20...

    1) A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes...

  • In 2015 The Big Boss Construction Company, started a 3 year project at a fixed contract...

    In 2015 The Big Boss Construction Company, started a 3 year project at a fixed contract price of $22,000,000. The estimated construction costs were $15,500,000. The project was completed on time during the 2917 year. The following information is available for the three year period of the construction project. 2015 2016 2017 Costs Incurred to Date $6,188,000 $12,360,000 $15,875,000 Estimated Costs to Complete 9,282,000 3,090,000 -- Billings to Date 6,400,000 18,890,000 22,000,000 Collections to Date 5,100,000 17,110,000 21,630,000 Required 1....

  • Coquel Company has a non-cancellable contract to construct a bridge for an estimated cost of$ 1,950,000....

    Coquel Company has a non-cancellable contract to construct a bridge for an estimated cost of$ 1,950,000. The contract is to start in July 2020, and the bridge is to be completed in September 2022. The following data pertain to the construction period. Assume that progress billings are 4. non-refundable. 2020 2021 2022 Costs to date $360,000 $900,000 $390,000 Estimated costs to complete 1,260,000 380,000 Progress billings during the 305,000 765,000 1,200,000 year Cash collected during the year 280,000 760,000 2,000,000...

  • A construction company entered into a fixed-price contract to build an office building for $20 million....

    A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT