Bigelow Contractors signed a contract to construct a storage facility for RGN manufacturing, Inc. The fixed-fee contract specifies that the facility is to be completed in three years. Bigelow uses the percentage-of-completion method (cost-to-cost approach) to account for its construction transactions. Information related to this contract is summarized in the following table.
Contract price | $ 2,000,000 | ||
2018 | 2019 | 2020 | |
Actual construction costs incurred during the year | $ 900,000 | $ 300,000 | $ 600,000 |
Construction costs incurred in prior years | 0 | 900,000 | 1,200,000 |
Cumulative construction costs incurred to date | 900,000 | 1,200,000 | 1,800,000 |
Estimated costs to complete | 600,000 | 400,000 | 0 |
Estimated total costs | 1,500,000 | 1,600,000 | 1,800,000 |
Progress billings made during the year | 700,000 | 700,000 | 600,000 |
Cash collections during the year | 400,000 | 800,000 | 800,000 |
Assume that Bigelow's total assets were $5,000,000 and its liabilities were $2,000,000 at the beginning of the year.
b. Compute the total assets, liabilities, and equity under the percentage-of-completion and completed contract methods at the end of each year.
Can someone help with Part B, the question is already answered, but does not explain how to get the total assets.
thanks in advance.
Ans :-
Under Percentage of completion method the recognition of revenue and cost taking into account the stage of completion of a contract. Under this method, revenue and cost are recognized in the statement of profit and loss in the accounting periods in which the work is performed. IV
Please find Balance sheet and P/L which will provide all requirements.
BALANCE SHEET (2018) | |||
EQUITY | 31,75,000 | ASSETS | 50,00,000 |
LIABILITY | 20,00,000 | STOCK | 3,75,000 |
CREDITORS | 5,00,000 | DEBTORS | 3,00,000 |
56,75,000 | 56,75,000 | ||
BALANCE SHEET (2019) | |||
EQUITY | 34,55,000 | ASSETS | 56,75,000 |
LIABILITY | 25,00,000 | STOCK | 80,000 |
CREDITORS | - | DEBTORS | 2,00,000 |
59,55,000 | 59,55,000 | ||
BALANCE SHEET (2020) | |||
EQUITY | 33,75,000 | ASSETS | 58,75,000 |
LIABILITY | 25,00,000 | CASH | - |
CREDITORS | - | DEBTORS | - |
58,75,000 | 58,75,000 | ||
Profit and Loss A/c (2018) | |||
Expenses (35%) | 9,00,000 | Sales (35%) | 7,00,000 |
Profit | 1,75,000 | Closing stock | 3,75,000 |
10,75,000 | 10,75,000 | ||
Note:- | |||
Estimated completion cost | 15,00,000 | ||
Cost of work done (35%) | 5,25,000 | ||
Actual cost incurred | 9,00,000 | ||
Closing stock | 3,75,000 | ||
Profit and Loss A/c (2019) | |||
Opening Stock | 3,75,000 | Sales | 7,00,000 |
Expenses | 3,00,000 | Closing stock | 80,000 |
Profit | 1,05,000 | ||
7,80,000 | 7,80,000 | ||
Note:- | |||
Estimated completion cost | 16,00,000 | ||
Cost of work done (70%) | 11,20,000 | ||
Actual cost incurred | 12,00,000 | ||
Closing stock | 80,000 | ||
Profit and Loss A/c (2020) | |||
Opening Stock | 80,000 | Sales | 6,00,000 |
Expenses | 600000 | Closing stock | |
Profit | -80,000 | ||
6,00,000 | 6,00,000 | ||
Note:- | |||
Estimated completion cost | 18,00,000 | ||
Cost of work done (100%) | 18,00,000 | ||
Actual cost incurred | 18,00,000 | ||
Closing stock | - |
Bigelow Contractors signed a contract to construct a storage facility for RGN manufacturing, Inc. The fixed-fee...
McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun in 2023 and completed in 2024. Cost and other data are presented below: 2024 $1,300 Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2023 $1,500 1,200 1,200 1,000 1,300 1,500 1. Compute the amount of revenue and gross profit recognized during 2023 and 2024. 2. Assume that McCombs recognizes revenue on this contract over...
Ex. 18-127-Percentage-of-completion and completed-contract methods. On February 1, 2012, Marsh Contractors agreed to construct a building at a contract price of $5,400,000. Marsh estimated total construction costs would be $4,000,000 and the project would be finished in 2014. Information relating to the costs and billings for this contract is as follows: 2014 2012 $1,500,000 2,500,000 2,200,000 2,000,000 2013 $4,600,000 $2,640,000 1,760,000 4,000,000 3,500,000 Total costs incurred to date Estimated costs to complete Customer billings to date Collections to date -0-...
On February 1, 2017, Marsh Contractors agreed to construct a
building at a contract price of $5,720,000. Marsh estimated total
construction costs would be $3,936,000 and the project would be
finished in 2019. Information relating to the costs and billings
for this contract is as follows:
2017
2018
2019
Total costs incurred to date
$1,476,000
$2,592,000
$4,560,000
Estimated costs to complete
2,460,000
1,728,000
-0-
Customer billings to date
2,120,000
3,936,000
5,520,000
Collections to date
1,920,000
3,420,000
5,420,000
Fill in the...
Question Three: In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara Countyfor $10,000,000. The road was completed in 201 contract is as follows: 8. Information related to the 2018 2016 2,400,000 3,600,000 2,200,00 5,600,000 2,000,000 4,000,000 4,000,000 ,800,000 3,600,000 4,600,000 2017 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2,000,000 Westgate recognizes revenue over time according to percentage of...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate recognizes revenue over time according to...
Coquel Company has a non-cancellable contract to construct a bridge for an estimated cost of$ 1,950,000. The contract is to start in July 2020, and the bridge is to be completed in September 2022. The following data pertain to the construction period. Assume that progress billings are 4. non-refundable. 2020 2021 2022 Costs to date $360,000 $900,000 $390,000 Estimated costs to complete 1,260,000 380,000 Progress billings during the 305,000 765,000 1,200,000 year Cash collected during the year 280,000 760,000 2,000,000...
* (Long-Term Contract with an Overall Loss) On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily Corp. for a total contract price of $2,600,000. On July 1, Roman estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Sicily 2020, 2021, and 2022:...
question 1
4. Coquel Company has a non-cancellable contract to construct a bridge for an estimated cost of $ 1,950,000. The contract is to start in July 2020, and the bridge is to be completed in September 2022. The following data pertain to the construction period. Assume that progress billings are non-refundable. 2022 2021 2020 $390,000 $ 900,000 $360,000 Costs to date 380,000 1,260,000 Estimated costs to complete 420 Doo -1,200,000 765,000 305,000 Progress billings during the year 2,000,000 760,000...
JJ Construction Inc. entered into a contract with a customer to build a movable storage facility on January 1, 2020, for $1,800,000. JJ Construction Inc. owns the work in process and constructs this type of storage unit for a number of customers. The customer made a down payment of 10% of the project, with an additional 10% due at the end of year one and the remaining due when it takes control of the facility. The facility is expected to...
Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, lo construct a four- story office building. At that time, Curtiss estimated that it would take belween two and three years to complete the project. The total contract price for construction of the building is $5.080,000. Curliss concludes that the contract does not qually for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract...