Question

Coquel Company has a non-cancellable contract to construct a bridge for an estimated cost of$ 1,950,000. The contract is to s

0 0
Add a comment Improve this question Transcribed image text
Answer #1

2021 $900,000 $900,000 2022 $390,000 $390,000 $765,000 $765,000 $880.000 $880,000 Zero-profit method Journal entries: Date AcBillings during the year 2022 $880,000 2020 $305,000 2020 $360,000 $360,000 $1,260,000 $1,620,000 Costs incurred during the y2022 $390,000 $390,000 $880,000 $880,000 Percentage-of-completion method Journal entries: Date Accounts title and explanation

Add a comment
Know the answer?
Add Answer to:
Coquel Company has a non-cancellable contract to construct a bridge for an estimated cost of$ 1,950,000....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • question 1 4. Coquel Company has a non-cancellable contract to construct a bridge for an estimated...

    question 1 4. Coquel Company has a non-cancellable contract to construct a bridge for an estimated cost of $ 1,950,000. The contract is to start in July 2020, and the bridge is to be completed in September 2022. The following data pertain to the construction period. Assume that progress billings are non-refundable. 2022 2021 2020 $390,000 $ 900,000 $360,000 Costs to date 380,000 1,260,000 Estimated costs to complete 420 Doo -1,200,000 765,000 305,000 Progress billings during the year 2,000,000 760,000...

  • Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price...

    Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $2.9 million beginning September 1, 2020, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2022. The following data pertain to the construction period. 2020 2021 2022 Costs to date $848,000 $1,871,250 $2,428,000 Estimated costs to complete 1,802,000 623,750 0 Progress billings to date (non-refundable) 890,000 2,378,000 2,900,000 Cash collected to...

  • Sandhill Construction Company has entered into a non-cancellable contract beginning January 1, 2020, to build a...

    Sandhill Construction Company has entered into a non-cancellable contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $650,000 and will take three years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2022 $660,000 Costs to date Estimated costs to complete Progress billings to date (non-refundable) Cash collected to date 2020 $292,500 357,500 292,500 262,500 2021 $487,500 162,500...

  • Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price...

    Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $2.9 million beginning September 1, 2020, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2022. The following data pertain to the construction period. 2020 2021 2022 Costs to date $848,000 $1,871,250 $2,428,000 Estimated costs to complete 1,802,000 623,750 0 Progress billings to date (non-refundable) 890,000 2,378,000 2,900,000 Cash collected to...

  • E6.37 (LO 12) (Recognition of Profit on Long-Term Contract) Vaughn Enterprises Ltd. has entered into a...

    E6.37 (LO 12) (Recognition of Profit on Long-Term Contract) Vaughn Enterprises Ltd. has entered into a contract beginning in February 2020 to build two warehouses for Atlantis Structures Ltd. The contract is a non-cancellable fixed price contract for $10 million. The following data pertain to the construction period (all figures in thousands). 2020 2021 2022 Costs for the year $3,825 $4,675 $1,200 Estimated costs to complete 4,675 1,270 –0– Progress billings for the year (non-refundable) 3,500 4,100 2,400 Cash collected...

  • During 2020, Sunland Company started a construction job with a contract price of $1,408,000. The job was completed in 20...

    During 2020, Sunland Company started a construction job with a contract price of $1,408,000. The job was completed in 2022. The following information is available. The contract is non-cancellable. 2020 2021 2022 Costs incurred to date $352,000 $726,000 $941,600 Estimated costs to complete 528,000 242,000 0 Billings to date (non-refundable) 264,000 792,000 1,408,000 Collections to date 237,600 712,800 1,254,000 QUESTION: A) Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. B) Prepare...

  • E6.37 (LO 12) (Recognition of Profit on Long-Term Contract) Vaughn Enterprises Ltd. has entered into a...

    E6.37 (LO 12) (Recognition of Profit on Long-Term Contract) Vaughn Enterprises Ltd. has entered into a contract beginning in February 2020 to build two warehouses for Atlantis Structures Ltd. The contract is a non-cancellable fixed price contract for $10 million. The following data pertain to the construction period (all figures in thousands). 2020 2021 2022 Costs for the year $3,825 $4,675 $1,200 Estimated costs to complete 4,675 1,270 –0– Progress billings for the year (non-refundable) 3,500 4,100 2,400 Cash collected...

  • Question No. 3 (15 marks) Napanee Construction Company (NCC) has entered into a non-cancellable contract with...

    Question No. 3 (15 marks) Napanee Construction Company (NCC) has entered into a non-cancellable contract with Raglan Company to construct a building for $2,100,000. NCC is a public company with a December 31 year-end. NCC has elected to use the Percentage-of-Completion method. The following data are available: 2018 2019 2020 Construction costs incurred to-date $ 400,000 $1,600,000 $1,900,000 Estimated costs to completion 1,400,000 450,000 0 Progress Billings to-date 320,000 1,128,000 652,000 Cash collected to date 300,000 1,050,000 750,000 Required: (Note:...

  • During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job...

    During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 $366,300 623,700 297,000 270,000 2021 $831,440 262,560 894,000 816,000 2022 $1,067,000 -0- 1,590,000 1,417,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...

  • During 2020, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job...

    During 2020, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $396,000 $806,600 $1,080,000 Estimated costs to complete 594,000 283,400 -0- Billings to date 301,000 268,000 892,000 816,000 1,590,000 1,427,000 Collections to date Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework