Crane Construction Inc., which has a calendar year end, has
entered into a non-cancellable fixed price contract for $2.9
million beginning September 1, 2020, to build a road for a
municipality. It has been estimated that the road construction will
be complete by June 2022. The following data pertain to the
construction period.
2020 | 2021 | 2022 | ||||
Costs to date | $848,000 | $1,871,250 | $2,428,000 | |||
Estimated costs to complete | 1,802,000 | 623,750 | 0 | |||
Progress billings to date (non-refundable) | 890,000 | 2,378,000 | 2,900,000 | |||
Cash collected to date | 748,000 | 2,271,000 | 2,900,000 |
Using the percentage-of-completion method, calculate the estimated gross profit that would be recognized during each year of the construction period.
2020 2021 2022
Gross profit / (loss) $ $ $
2020
Percentage of completion = Cost to date * 100
Estmated total cost
= $848,000 * 100
$848,000+$1,802,000
= 32%
Revenue to be recognised = $2,900,000 * 32%
= $928,000
2021
Cumulative Percentage of completion = Cost to date * 100
Estmated total cost
= $1,871,250 * 100
$1,871,250+$623,750
= 75 %
Revenue to be recognised = $2,900,000 * (75-32)%
= $1,247,000
Cost incurred = Cost to date - previous year cost
= $1,871,250-$848,000
= $1,023,250
2022
Cumulative Percentage of completion = 100% since project completed.
Revenue to be recognised = Total contract price - Revenue recognised till dsate
= $2,900,000- $928,000 - $1,247,000
= $725,000
Cost incurred = Cost to date - previous year cost
= $2,428,000- $1,871,250
= $556,750
CRANE CONSTRUCTION INC. | ||||
STATEMENT OF GROSS PROFIT | ||||
2020 | 2021 | 2022 | Total | |
Revenue | $928,000 | $1,247,000 | $725,000 | $2,900,000 |
Costs | ($848,000) | ($1,023,250) | ($556,750) | ($2,428,000) |
Gross profit | $80,000 | $223,750 | $168,250 | $472,000 |
Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price...
Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $2.9 million beginning September 1, 2020, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2022. The following data pertain to the construction period. 2020 2021 2022 Costs to date $848,000 $1,871,250 $2,428,000 Estimated costs to complete 1,802,000 623,750 0 Progress billings to date (non-refundable) 890,000 2,378,000 2,900,000 Cash collected to...
Sandhill Construction Company has entered into a non-cancellable contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $650,000 and will take three years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2022 $660,000 Costs to date Estimated costs to complete Progress billings to date (non-refundable) Cash collected to date 2020 $292,500 357,500 292,500 262,500 2021 $487,500 162,500...
Coquel Company has a non-cancellable contract to construct a bridge for an estimated cost of$ 1,950,000. The contract is to start in July 2020, and the bridge is to be completed in September 2022. The following data pertain to the construction period. Assume that progress billings are 4. non-refundable. 2020 2021 2022 Costs to date $360,000 $900,000 $390,000 Estimated costs to complete 1,260,000 380,000 Progress billings during the 305,000 765,000 1,200,000 year Cash collected during the year 280,000 760,000 2,000,000...
question 1
4. Coquel Company has a non-cancellable contract to construct a bridge for an estimated cost of $ 1,950,000. The contract is to start in July 2020, and the bridge is to be completed in September 2022. The following data pertain to the construction period. Assume that progress billings are non-refundable. 2022 2021 2020 $390,000 $ 900,000 $360,000 Costs to date 380,000 1,260,000 Estimated costs to complete 420 Doo -1,200,000 765,000 305,000 Progress billings during the year 2,000,000 760,000...
Bramble Construction Company has entered into a contract
beginning January 1, 2020, to build a parking complex. It has been
estimated that the complex will cost $606,000 and will take 3 years
to construct. The complex will be billed to the purchasing company
at $902,000. The following data pertain to the construction period.
2020 2021 2022 Costs to date $272,700 $466,620 $618,000 Estimated
costs to complete 333,300 139,380 –0– Progress billings to date
273,000 546,000 902,000 Cash collected to date...
E6.37 (LO 12) (Recognition of Profit on Long-Term Contract) Vaughn Enterprises Ltd. has entered into a contract beginning in February 2020 to build two warehouses for Atlantis Structures Ltd. The contract is a non-cancellable fixed price contract for $10 million. The following data pertain to the construction period (all figures in thousands). 2020 2021 2022 Costs for the year $3,825 $4,675 $1,200 Estimated costs to complete 4,675 1,270 –0– Progress billings for the year (non-refundable) 3,500 4,100 2,400 Cash collected...
During 2020, Sunland Company started a construction job with a contract price of $1,408,000. The job was completed in 2022. The following information is available. The contract is non-cancellable. 2020 2021 2022 Costs incurred to date $352,000 $726,000 $941,600 Estimated costs to complete 528,000 242,000 0 Billings to date (non-refundable) 264,000 792,000 1,408,000 Collections to date 237,600 712,800 1,254,000 QUESTION: A) Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. B) Prepare...
Pronghorn Construction Company has entered into a contract
beginning January 1, 2020, to build a parking complex. It has been
estimated that the complex will cost $596,000 and will take 3 years
to construct. The complex will be billed to the purchasing company
at $894,000. The following data pertain to the construction
period.
2020
2021
2022
Costs to date
$274,160
$417,200
$607,000
Estimated costs to complete
321,840
178,800
–0–
Progress billings to date
272,000
550,000
894,000
Cash collected to date...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period 2020 2021 2022 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $598,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $897,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $275,080 $412,620 $607,000 Estimated costs to complete 322,920 185,380 –0– Progress billings to date 272,000 545,000 897,000 Cash collected to date...