Question

Question No. 3 (15 marks) Napanee Construction Company (NCC) has entered into a non-cancellable contract with...

Question No. 3 (15 marks)

Napanee Construction Company (NCC) has entered into a non-cancellable contract with Raglan Company to construct a building for $2,100,000. NCC is a public company with a December 31 year-end. NCC has elected to use the Percentage-of-Completion method. The following data are available:

2018

2019

2020

Construction costs incurred to-date

$ 400,000

$1,600,000

$1,900,000

Estimated costs to completion

1,400,000

450,000

0

Progress Billings to-date

320,000

1,128,000

652,000

Cash collected to date

300,000

1,050,000

750,000

Required: (Note: All supporting calculations must be shown in order to get part marks)

  1. Calculate the amount of gross profit that will be reported by NCC on its Statement of Comprehensive Income in each year? (6 marks)

  1. What is the balance in the accounts receivable account on December 31, 2019? (2 marks)

  1. What is the amount of the contract net asset or contract net liability to be reported on NCC’s Statement of Financial Position at December 31, 2019? Use appropriate T-accounts to support your answer. (4 marks)

  1. If Napanee Construction Company had used the Zero Profit method instead of the Percentage-of-Completion method, how much gross profit would recorded in each year? (3 marks)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Napanee Construction Company (NCC) Percentage of completion Method Year 2018 Year 2019 Year 2020 Total Cost incurred to DateRequirement 2 *Accounts Receivables at year end 2018 Opening balance $ (+) Addtions 4,66,667 Cash collected 3,00,000 ClosingRequirement 3 A *Billings in excess of cost and loss for 2018 opening Balance (+) Billing during the year $ 3,20,000 (-) Tota

Add a comment
Know the answer?
Add Answer to:
Question No. 3 (15 marks) Napanee Construction Company (NCC) has entered into a non-cancellable contract with...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Sandhill Construction Company has entered into a non-cancellable contract beginning January 1, 2020, to build a...

    Sandhill Construction Company has entered into a non-cancellable contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $650,000 and will take three years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2022 $660,000 Costs to date Estimated costs to complete Progress billings to date (non-refundable) Cash collected to date 2020 $292,500 357,500 292,500 262,500 2021 $487,500 162,500...

  • Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price...

    Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $2.9 million beginning September 1, 2020, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2022. The following data pertain to the construction period. 2020 2021 2022 Costs to date $848,000 $1,871,250 $2,428,000 Estimated costs to complete 1,802,000 623,750 0 Progress billings to date (non-refundable) 890,000 2,378,000 2,900,000 Cash collected to...

  • Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price...

    Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $2.9 million beginning September 1, 2020, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2022. The following data pertain to the construction period. 2020 2021 2022 Costs to date $848,000 $1,871,250 $2,428,000 Estimated costs to complete 1,802,000 623,750 0 Progress billings to date (non-refundable) 890,000 2,378,000 2,900,000 Cash collected to...

  • Coquel Company has a non-cancellable contract to construct a bridge for an estimated cost of$ 1,950,000....

    Coquel Company has a non-cancellable contract to construct a bridge for an estimated cost of$ 1,950,000. The contract is to start in July 2020, and the bridge is to be completed in September 2022. The following data pertain to the construction period. Assume that progress billings are 4. non-refundable. 2020 2021 2022 Costs to date $360,000 $900,000 $390,000 Estimated costs to complete 1,260,000 380,000 Progress billings during the 305,000 765,000 1,200,000 year Cash collected during the year 280,000 760,000 2,000,000...

  • question 1 4. Coquel Company has a non-cancellable contract to construct a bridge for an estimated...

    question 1 4. Coquel Company has a non-cancellable contract to construct a bridge for an estimated cost of $ 1,950,000. The contract is to start in July 2020, and the bridge is to be completed in September 2022. The following data pertain to the construction period. Assume that progress billings are non-refundable. 2022 2021 2020 $390,000 $ 900,000 $360,000 Costs to date 380,000 1,260,000 Estimated costs to complete 420 Doo -1,200,000 765,000 305,000 Progress billings during the year 2,000,000 760,000...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,060,000. During 2018, costs of $2,020,000 were incurred with estimated costs of $4,020,000 yet to be incurred. Billings of $2,520,000 were sent, and cash collected was $2,270,000. In 2019, costs incurred were $2,520,000 with remaining costs estimated to be $3,630,000. 2019 billings were $2,770,000 and $2,495,000 cash was collected. The project was completed in 2020 after additional costs of...

  • King Corporation started the construction of a building during 2017 at a contract price of $5,000,000....

    King Corporation started the construction of a building during 2017 at a contract price of $5,000,000. The contract to build was non-cancellable and they managed to complete the project in 2019 as anticipated. Billings are nonrefundable and under the terms of the project, King sends billings to the vendor as revenues are earned. The following additional information is available: 2017 2018 2019 Costs to-date $ 800,000 $2,500,000 $4,800,000 Estimated costs to complete $2,400,000 $2,500,000 $0 Required: a. Calculate the amount...

  • 3. On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2018, costs of $2,100,000 were incurred...

    3. On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2018, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2019, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2019 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2020 after additional costs...

  • Black Sea Construction Company has a contract to construct a $6,000,000 oil rig at an estimated...

    Black Sea Construction Company has a contract to construct a $6,000,000 oil rig at an estimated cost of $5,300,000. The contract is to start in July 2017, and the oil rig is to be completed in October 2019. The following data pertain to the construction period. 2017    2018    2019 Costs to date $1,325,000 $3,720,000 $6,300,000 Estimated costs to complete 3,975,000 2,480,000 — Progress billings during the year 1,200,000 3,200,000 1,600,000 Cash collected during the year 1,000,000 2,340,000 2,660,000 What amount...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT