Question

E6.37 (LO 12) (Recognition of Profit on Long-Term Contract) Vaughn Enterprises Ltd. has entered into a...

E6.37 (LO 12) (Recognition of Profit on Long-Term Contract) Vaughn Enterprises Ltd. has entered into a contract beginning in February 2020 to build two warehouses for Atlantis Structures Ltd. The contract is a non-cancellable fixed price contract for $10 million. The following data pertain to the construction period (all figures in thousands).

2020 2021 2022
Costs for the year $3,825 $4,675 $1,200
Estimated costs to complete 4,675 1,270 –0–
Progress billings for the year (non-refundable) 3,500 4,100 2,400
Cash collected for the year 3,100 4,150 2,750

E6.39 (LO 15 ) (Recognition of Profit on Long-Term Contract—Overall Loss) Assume the facts given in E6.37 except that Vaughn's non-cancellable fixed-price contract with Atlantis is for $9.5 million. Billings and collections are lower in 2022 by $500,000 each.

2020 2021 2022
Costs for the year $3,825 $4,675 $1,200
Estimated costs to complete 4,675 1,270 –0–
Progress billings for the year (non-refundable) 3,500 4,100 1,900
Cash collected for the year 3,100 4,150 2,250

Instructions

a. Using the percentage-of-completion method, calculate the percent complete for 2020 and 2021. Round the percent complete to the nearest whole percentage point.

b. Calculate the amount of revenue to be recognized in 2020 and 2021.

c. Calculate the construction costs to be expensed in 2021.

d. Prepare the journal entry at December 31, 2021, to record long-term contract revenues, expenses, and losses for 2021.

e. What is the balance in the Contract Asset/Liability account at December 31, 2020 and 2021?

f. Show how the construction contract would be reported on the SFP and the income statement for the year ended December 31, 2021.

g. Assume that Vaughn uses the zero-profit or completed-contract method. What would be the journal entry recorded on December 31, 2021?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer to first 4 parts of Q# E6.39 (Requested question in the list): a) 2020 $3,500,000 2021 $4,100,000 2022 $1,900,000 Billc) Construction costs to be expensed in 2021 $4,675,000 (= Construction costs for the year given] d) Account Titles 2021 Debi

Add a comment
Know the answer?
Add Answer to:
E6.37 (LO 12) (Recognition of Profit on Long-Term Contract) Vaughn Enterprises Ltd. has entered into a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • E6.37 (LO 12) (Recognition of Profit on Long-Term Contract) Vaughn Enterprises Ltd. has entered into a...

    E6.37 (LO 12) (Recognition of Profit on Long-Term Contract) Vaughn Enterprises Ltd. has entered into a contract beginning in February 2020 to build two warehouses for Atlantis Structures Ltd. The contract is a non-cancellable fixed price contract for $10 million. The following data pertain to the construction period (all figures in thousands). 2020 2021 2022 Costs for the year $3,825 $4,675 $1,200 Estimated costs to complete 4,675 1,270 –0– Progress billings for the year (non-refundable) 3,500 4,100 2,400 Cash collected...

  • *E6.37 (LO 12) (Recognition of Profit on Long-Term Contract) Vaughn Enterprises Ltd. has entered into a...

    *E6.37 (LO 12) (Recognition of Profit on Long-Term Contract) Vaughn Enterprises Ltd. has entered into a contract beginning in February 2020 to build two warehouses for Atlantis Structures Ltd. The contract is a non-cancellable fixed price contract for $10 million. The following data pertain to the construction period (all figures in thousands). Instructions a. Using the percentage-of-completion method, calculate the percent complete for each year of the contract. Round the percentage completion to the nearest whole percentage point.

  • Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price...

    Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $2.9 million beginning September 1, 2020, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2022. The following data pertain to the construction period. 2020 2021 2022 Costs to date $848,000 $1,871,250 $2,428,000 Estimated costs to complete 1,802,000 623,750 0 Progress billings to date (non-refundable) 890,000 2,378,000 2,900,000 Cash collected to...

  • Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price...

    Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $2.9 million beginning September 1, 2020, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2022. The following data pertain to the construction period. 2020 2021 2022 Costs to date $848,000 $1,871,250 $2,428,000 Estimated costs to complete 1,802,000 623,750 0 Progress billings to date (non-refundable) 890,000 2,378,000 2,900,000 Cash collected to...

  • (Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a...

    (Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below. 2020 2021 2022 Contract costs incurred during the year $3,400,000 $2,400,000 $2,900,000 Estimated costs to complete the contract at 12/31 4,600,000 3,100,000 -0-...

  • *P18.11 (LO 5, 6, 7) Excel (Long-Term Contract with an Overall Loss) On July 1, 2020,...

    *P18.11 (LO 5, 6, 7) Excel (Long-Term Contract with an Overall Loss) On July 1, 2020, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to...

  • Sandhill Construction Company has entered into a non-cancellable contract beginning January 1, 2020, to build a...

    Sandhill Construction Company has entered into a non-cancellable contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $650,000 and will take three years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2022 $660,000 Costs to date Estimated costs to complete Progress billings to date (non-refundable) Cash collected to date 2020 $292,500 357,500 292,500 262,500 2021 $487,500 162,500...

  • Coquel Company has a non-cancellable contract to construct a bridge for an estimated cost of$ 1,950,000....

    Coquel Company has a non-cancellable contract to construct a bridge for an estimated cost of$ 1,950,000. The contract is to start in July 2020, and the bridge is to be completed in September 2022. The following data pertain to the construction period. Assume that progress billings are 4. non-refundable. 2020 2021 2022 Costs to date $360,000 $900,000 $390,000 Estimated costs to complete 1,260,000 380,000 Progress billings during the 305,000 765,000 1,200,000 year Cash collected during the year 280,000 760,000 2,000,000...

  • During 2020, Sunland Company started a construction job with a contract price of $1,408,000. The job was completed in 20...

    During 2020, Sunland Company started a construction job with a contract price of $1,408,000. The job was completed in 2022. The following information is available. The contract is non-cancellable. 2020 2021 2022 Costs incurred to date $352,000 $726,000 $941,600 Estimated costs to complete 528,000 242,000 0 Billings to date (non-refundable) 264,000 792,000 1,408,000 Collections to date 237,600 712,800 1,254,000 QUESTION: A) Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. B) Prepare...

  • * (Long-Term Contract with an Overall Loss) On June 1, 2020, Roman Construction Company Inc. contracted...

    * (Long-Term Contract with an Overall Loss) On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily Corp. for a total contract price of $2,600,000. On July 1, Roman estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Sicily 2020, 2021, and 2022:...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT