During 20x5, the Ibti Construction Company obtained a $15 million contract to build a bridge. The costs incurred, estimated costs to complete and the billings made on the contract for the period 20x5 – 20x6 are as follows: |
||||||||||||
|
||||||||||||
Ibti uses the percentage of completion method. Costs incurred relative to total project costs are used to measure the percentage of completion at the end of the year. |
||||||||||||
Required – |
||||||||||||
For each of the years 20x5 and 20x6, calculate the following: |
||||||||||||
• revenues realized, |
||||||||||||
• costs realized, |
||||||||||||
• profit or loss realized, and |
||||||||||||
• the amount recognized for the project on Ibti’s Statement of Financial Position at the end of each year. |
2005 | 2006 | |
Cost incurred during the year | 3,000,000 | 5,000,000 |
Expected Cost to complete | 9,000,000 | 6,000,000 |
Billings | 7,500,000 | |
Contract Value | 15,000,000 | 15,000,000 |
Total Cost Incurred | 3,000,000 | 8,000,000 |
Total Project Cost | 12,000,000 | 14,000,000 |
Percentage Completed | 25.00% | 57.14% |
Balance to be recognised | 32.14% | |
Revenue Realised | 3,750,000 | 4,821,429 |
Cost Realised | 3,000,000 | 5,000,000 |
Profit or Loss Realised | 750,000 | -178,571 |
Amount recognised for the project on Ibti’s Statement of Financial Position at the end of each year. | ||
Current Liabilities | ||
Progress Billings - Excess Billings over Cost | 4,500,000 | |
Current Assets | ||
Construction in Progress - Excess Cost over Billings | 500,000 | |
During 20x5, the Ibti Construction Company obtained a $15 million contract to build a bridge. The...
CORRECT ANSWER NEEDED ASAP! THANK YOU During 20x5, the Ibti Construction Company obtained a $15 million contract to build a bridge. The costs incurred, estimated costs to complete and the billings made on the contract for the period 20x5 – 20x6 are as follows: 20x5 20x6 $3,000,000 $5,000,000 Costs incurred during the year Expected costs to complete Billings 9,000,000 6,000,000 7,500,000 Ibti uses the percentage of completion method. Costs incurred relative to total project costs are used to measure the...
King Corporation started the construction of a building during 2017 at a contract price of $5,000,000. The contract to build was non-cancellable and they managed to complete the project in 2019 as anticipated. Billings are nonrefundable and under the terms of the project, King sends billings to the vendor as revenues are earned. The following additional information is available: 2017 2018 2019 Costs to-date $ 800,000 $2,500,000 $4,800,000 Estimated costs to complete $2,400,000 $2,500,000 $0 Required: a. Calculate the amount...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimated costs of $4,140,000 yet to be incurred. Billings of $2,640,000 were sent, and cash collected was $2,390,000. In 2019, costs incurred were $2,640,000 with remaining costs estimated to be $3,810,000. 2019 billings were $2,890,000 and $2,615,000 cash was collected. The project was completed in 2020 after additional costs of...
Fender period. Construction Company receives a contract to construct a building over a 3 year Information relating to the performance of the contract is summarized as follows: 2015 2016 2017 S 16,000,000 Cumulative construction costs incurred to date Estimated costs to complete Billings during the year Cash collected during the year 6,000,000 8,000,000 6,000,000 3,000,000 8,000,000 7,000,000 4,000,000 5,000,000 Required: 1. How much is Fender Construction charging to build this athletic stadium? In other words, what is the contract price...
On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2016, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2017, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2017 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2018 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,330,000. During 2021, costs of $2,110,000 were incurred with estimated costs of $4,110,000 yet to be incurred. Billings of $2,610,000 were sent, and cash collected was $2,360,000. In 2022, costs incurred were $2,610,000 with remaining costs estimated to be $3,765,000. 2022 billings were $2,860,000 and $2,585,000 cash was collected. The project was completed in 2023 after additional costs of $3,910,000...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2023 after additional costs of $3,900,000...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2,830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,030,000. During 2021, costs of $2,010,000 were incurred with estimated costs of $4,010,000 yet to be incurred. Billings of $2,510,000 were sent, and cash collected was $2,260,000. In 2022, costs incurred were $2,510,000 with remaining costs estimated to be $3,615,000. 2022 billings were $2,760,000 and $2,485,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2021, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2022, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2022 billings were $2,790,000 and $2,515,000 cash was collected. The project was completed in 2023 after additional costs of...