During 20x5, the Ibti Construction Company obtained a $15 million contract to build a bridge. The costs incurred, estimated c

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Particulars 2015 2016
a) Revenue to be recorded in Statement of Profit and Loss (WN-3)     3,750,000     4,821,429
b) Cost to be recorded in Statement of Profit and Loss (WN-2 and 2.1)     3,000,000     5,000,000
c) Profit/(Loss) to be recorded in Statement of Profit and Loss (WN-4)        750,000       -178,571
d) Amount Recognised for the project on Financial Statement Position
    Unearned Revenue (shown under Liability side of Balance Sheet)     3,750,000
    Unbilled Revenue (shown under asset side of Balance Sheet)     1,071,429
WN-1
Particulars 2015 2016
Contract Revenue 15,000,000 15,000,000
Total Contract Cost (WN-2 and 2.1) 12,000,000 14,000,000
Estimated Profit     3,000,000     1,000,000
WN-2
Calculation of Percentage of Completion for 2015
Particulars 2015
Costs Incurred (A)     3,000,000
Expected cost to complete (B)     9,000,000
Total Contract Cost (C = A+B) 12,000,000
Percentage of Completion 25%
Percentage of Completion = Costs Incurred / Total Contract Cost *100
WN-2.1
Calculation of Percentage of Completion for 2016
Particulars 2016
Costs Incurred (A) ( 2015+2016)     8,000,000
Expected cost to complete (B)     6,000,000
Total Contract Cost (C = A+B) 14,000,000
Percentage of Completion 57%
WN-3
Calculation of Revenue to be recored in Statement of Profit & Loss
Particulars 2015 2016
Contract Revenue 15,000,000 15,000,000
% of Completion 25% 57%
Cumulative Revenue to be recored in Statement of Profit & Loss (Contract Revenue* % of Completion)     3,750,000     8,571,429
Revenue Recorded in Previous Year                      -     3,750,000
Revenue to be Recorded in current Year     3,750,000     4,821,429
WN-4
Calculation of Profit/Loss to be recored in Statement of Profit & Loss A B C =B-A
Cumulative Cumulative For the year
Particulars 2015 2016 2016
Revenue to be recored in Statement of Profit & Loss     3,750,000     8,571,429      4,821,429
Less : Costs Incurred -3,000,000 -8,000,000    -5,000,000
Profit/Loss to be recored in Statement of Profit & Loss        750,000        571,429        -178,571
WN-5
Calculation of Unearned Revenue or Unbilled Revenue
Particulars 2015 2016
Opening (Unearned Revenue)/ Unbilled Revenue -3,750,000
Revenue to be recorded from % of completion     3,750,000     4,821,429
Less : Billings -7,500,000 0
Closing (Unearned Revenue)/ Unbilled Revenue -3,750,000     1,071,429
Add a comment
Know the answer?
Add Answer to:
CORRECT ANSWER NEEDED ASAP! THANK YOU During 20x5, the Ibti Construction Company obtained a $15 million...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • During 20x5, the Ibti Construction Company obtained a $15 million contract to build a bridge. The...

    During 20x5, the Ibti Construction Company obtained a $15 million contract to build a bridge. The costs incurred, estimated costs to complete and the billings made on the contract for the period 20x5 – 20x6 are as follows: 20x5 20x6 Costs incurred during the year $3,000,000 $5,000,000 Expected costs to complete 9,000,000 6,000,000 Billings 7,500,000 - Ibti uses the percentage of completion method. Costs incurred relative to total project costs are used to measure the percentage of completion at the...

  • Fender period. Construction Company receives a contract to construct a building over a 3 year Information...

    Fender period. Construction Company receives a contract to construct a building over a 3 year Information relating to the performance of the contract is summarized as follows: 2015 2016 2017 S 16,000,000 Cumulative construction costs incurred to date Estimated costs to complete Billings during the year Cash collected during the year 6,000,000 8,000,000 6,000,000 3,000,000 8,000,000 7,000,000 4,000,000 5,000,000 Required: 1. How much is Fender Construction charging to build this athletic stadium? In other words, what is the contract price...

  • Beavis Construction Company was the low bidder on a construction project to build an earthen dam...

    Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,890,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below: 2017 2018 Costs incurred during the year $ 423,000 $ 1,190,000 Estimated costs to complete 987,000 0 Billings during the year 445,000 1,445,000 Cash collections during the year 345,000 1,545,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....

  • Exercise 18-37 Your answer is partially correct. Try again. Yanmei Construction Company began operations on January...

    Exercise 18-37 Your answer is partially correct. Try again. Yanmei Construction Company began operations on January 1, 2017. During the year, Yanmei Construction entered into a contract with Lundquist Corp. to construct a manufacturing facility. At that time, Yanmei estimated that it would take 5 years to complete the facility at a total cost of $4,500,000. The total contract price for construction of the facility is $6,000,000. During the year, Yanmei incurred $1,185,800 in construction costs related to the construction...

  • King Corporation started the construction of a building during 2017 at a contract price of $5,000,000....

    King Corporation started the construction of a building during 2017 at a contract price of $5,000,000. The contract to build was non-cancellable and they managed to complete the project in 2019 as anticipated. Billings are nonrefundable and under the terms of the project, King sends billings to the vendor as revenues are earned. The following additional information is available: 2017 2018 2019 Costs to-date $ 800,000 $2,500,000 $4,800,000 Estimated costs to complete $2,400,000 $2,500,000 $0 Required: a. Calculate the amount...

  • On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2016, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2017, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2017 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2018 after additional costs of...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimat...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimated costs of $4,140,000 yet to be incurred. Billings of $2,640,000 were sent, and cash collected was $2,390,000. In 2019, costs incurred were $2,640,000 with remaining costs estimated to be $3,810,000. 2019 billings were $2,890,000 and $2,615,000 cash was collected. The project was completed in 2020 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2,830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,030,000. During 2021, costs of $2,010,000 were incurred with estimated costs of $4,010,000 yet to be incurred. Billings of $2,510,000 were sent, and cash collected was $2,260,000. In 2022, costs incurred were $2,510,000 with remaining costs estimated to be $3,615,000. 2022 billings were $2,760,000 and $2,485,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2021, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2022, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2022 billings were $2,790,000 and $2,515,000 cash was collected. The project was completed in 2023 after additional costs of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT