CORRECT ANSWER NEEDED ASAP! THANK YOU
Particulars | 2015 | 2016 | |
a) Revenue to be recorded in Statement of Profit and Loss (WN-3) | 3,750,000 | 4,821,429 | |
b) Cost to be recorded in Statement of Profit and Loss (WN-2 and 2.1) | 3,000,000 | 5,000,000 | |
c) Profit/(Loss) to be recorded in Statement of Profit and Loss (WN-4) | 750,000 | -178,571 | |
d) Amount Recognised for the project on Financial Statement Position | |||
Unearned Revenue (shown under Liability side of Balance Sheet) | 3,750,000 | ||
Unbilled Revenue (shown under asset side of Balance Sheet) | 1,071,429 | ||
WN-1 | |||
Particulars | 2015 | 2016 | |
Contract Revenue | 15,000,000 | 15,000,000 | |
Total Contract Cost (WN-2 and 2.1) | 12,000,000 | 14,000,000 | |
Estimated Profit | 3,000,000 | 1,000,000 | |
WN-2 | |||
Calculation of Percentage of Completion for 2015 | |||
Particulars | 2015 | ||
Costs Incurred (A) | 3,000,000 | ||
Expected cost to complete (B) | 9,000,000 | ||
Total Contract Cost (C = A+B) | 12,000,000 | ||
Percentage of Completion | 25% | ||
Percentage of Completion = Costs Incurred / Total Contract Cost *100 | |||
WN-2.1 | |||
Calculation of Percentage of Completion for 2016 | |||
Particulars | 2016 | ||
Costs Incurred (A) ( 2015+2016) | 8,000,000 | ||
Expected cost to complete (B) | 6,000,000 | ||
Total Contract Cost (C = A+B) | 14,000,000 | ||
Percentage of Completion | 57% | ||
WN-3 | |||
Calculation of Revenue to be recored in Statement of Profit & Loss | |||
Particulars | 2015 | 2016 | |
Contract Revenue | 15,000,000 | 15,000,000 | |
% of Completion | 25% | 57% | |
Cumulative Revenue to be recored in Statement of Profit & Loss (Contract Revenue* % of Completion) | 3,750,000 | 8,571,429 | |
Revenue Recorded in Previous Year | - | 3,750,000 | |
Revenue to be Recorded in current Year | 3,750,000 | 4,821,429 | |
WN-4 | |||
Calculation of Profit/Loss to be recored in Statement of Profit & Loss | A | B | C =B-A |
Cumulative | Cumulative | For the year | |
Particulars | 2015 | 2016 | 2016 |
Revenue to be recored in Statement of Profit & Loss | 3,750,000 | 8,571,429 | 4,821,429 |
Less : Costs Incurred | -3,000,000 | -8,000,000 | -5,000,000 |
Profit/Loss to be recored in Statement of Profit & Loss | 750,000 | 571,429 | -178,571 |
WN-5 | |||
Calculation of Unearned Revenue or Unbilled Revenue | |||
Particulars | 2015 | 2016 | |
Opening (Unearned Revenue)/ Unbilled Revenue | -3,750,000 | ||
Revenue to be recorded from % of completion | 3,750,000 | 4,821,429 | |
Less : Billings | -7,500,000 | 0 | |
Closing (Unearned Revenue)/ Unbilled Revenue | -3,750,000 | 1,071,429 |
CORRECT ANSWER NEEDED ASAP! THANK YOU During 20x5, the Ibti Construction Company obtained a $15 million...
During 20x5, the Ibti Construction Company obtained a $15 million contract to build a bridge. The costs incurred, estimated costs to complete and the billings made on the contract for the period 20x5 – 20x6 are as follows: 20x5 20x6 Costs incurred during the year $3,000,000 $5,000,000 Expected costs to complete 9,000,000 6,000,000 Billings 7,500,000 - Ibti uses the percentage of completion method. Costs incurred relative to total project costs are used to measure the percentage of completion at the...
Fender period. Construction Company receives a contract to construct a building over a 3 year Information relating to the performance of the contract is summarized as follows: 2015 2016 2017 S 16,000,000 Cumulative construction costs incurred to date Estimated costs to complete Billings during the year Cash collected during the year 6,000,000 8,000,000 6,000,000 3,000,000 8,000,000 7,000,000 4,000,000 5,000,000 Required: 1. How much is Fender Construction charging to build this athletic stadium? In other words, what is the contract price...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,890,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below: 2017 2018 Costs incurred during the year $ 423,000 $ 1,190,000 Estimated costs to complete 987,000 0 Billings during the year 445,000 1,445,000 Cash collections during the year 345,000 1,545,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Exercise 18-37 Your answer is partially correct. Try again. Yanmei Construction Company began operations on January 1, 2017. During the year, Yanmei Construction entered into a contract with Lundquist Corp. to construct a manufacturing facility. At that time, Yanmei estimated that it would take 5 years to complete the facility at a total cost of $4,500,000. The total contract price for construction of the facility is $6,000,000. During the year, Yanmei incurred $1,185,800 in construction costs related to the construction...
King Corporation started the construction of a building during 2017 at a contract price of $5,000,000. The contract to build was non-cancellable and they managed to complete the project in 2019 as anticipated. Billings are nonrefundable and under the terms of the project, King sends billings to the vendor as revenues are earned. The following additional information is available: 2017 2018 2019 Costs to-date $ 800,000 $2,500,000 $4,800,000 Estimated costs to complete $2,400,000 $2,500,000 $0 Required: a. Calculate the amount...
On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2016, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2017, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2017 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2018 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimated costs of $4,140,000 yet to be incurred. Billings of $2,640,000 were sent, and cash collected was $2,390,000. In 2019, costs incurred were $2,640,000 with remaining costs estimated to be $3,810,000. 2019 billings were $2,890,000 and $2,615,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2,830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,030,000. During 2021, costs of $2,010,000 were incurred with estimated costs of $4,010,000 yet to be incurred. Billings of $2,510,000 were sent, and cash collected was $2,260,000. In 2022, costs incurred were $2,510,000 with remaining costs estimated to be $3,615,000. 2022 billings were $2,760,000 and $2,485,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2021, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2022, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2022 billings were $2,790,000 and $2,515,000 cash was collected. The project was completed in 2023 after additional costs of...