Question

A job has 10 days of processing time left to do before completion, and today is...

A job has 10 days of processing time left to do before completion, and today is the 5th day of the month. If the job is due on the 15th day of the month, what is its critical ratio?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Cliven, Remaining Processing time (PT) = 10 days Today is 5th day job is due 15th day Remaining due days (0) due days (1) = 1

Add a comment
Know the answer?
Add Answer to:
A job has 10 days of processing time left to do before completion, and today is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Five jobs are ready for processing at time zero through a workstation. The details regarding the...

    Five jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion are provided in the following table. Job Processing Time (days) Days Due from Today A6 C 5 Using the shortest processing time (SPT) rule, it can be concluded that the average lateness for the five jobs is: O a. more than -6 but less than or equal to -2 days. O b. more than -2 but...

  • decimal places). An Alabama lumberyard has four jobs on order, as shown in the following table....

    decimal places). An Alabama lumberyard has four jobs on order, as shown in the following table. Jobs are logged as they arrive. Today is day 1 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: % (enter your response as a percentage The percentage utilization for the sequence developed using the EDD rule = rounded to two decimal places). Job Work (Processing) Time (Days) Job Due Date (Days) d)...

  • QUESTION 1 Part1. The total expected project completion time is: A. 10 days B. 11 days...

    QUESTION 1 Part1. The total expected project completion time is: A. 10 days B. 11 days C. 15 days D. none of the above Part 2. What is the effect of a delay of 1 day in distributing tickets? A. no impact B. the project will delay by one day C. the project will delay by more than one day D. same as the effect of a delay of 1 day in setting up radio ads Part 3. What is...

  • Five jobs are ready for processing at time zero through a workstation. The details of the...

    Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 6 18 B 3 14 C 4 9 D 5 19 E 2 11 Using the earliest due date (EDD) rule, the average flow time for the five jobs is _____. a. more than 10 but less than or equal to 12 days....

  • Five jobs are ready for processing at time zero through a workstation. The details of the...

    Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 8 12 B 4 9 C 3 6 D 7 7 E 5 20 Using the shortest processing time (SPT) rule, it can be concluded that the average flow time for these five jobs is _____. a. more than 14 but less than...

  • Five jobs are ready for processing at time zero through a workstation. The details of the...

    Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date (days) A 5 11 B 6 16 C 3 19 D 4 10 E 2 9 Using the earliest due date (EDD) rule, the average lateness for the five jobs is: a. more than -6 but less than or equal to -2 days. b....

  • ABC Enterprises has five jobs that must be scheduled for production at a work center. Below...

    ABC Enterprises has five jobs that must be scheduled for production at a work center. Below are the processing times and due dates for each job.                                     Job Processing Time (in days) Due Date (days from today) 1 7 14 2 5 21 3 3 10 4 2 7 5 6 9                                                                                                                            Schedule the jobs by sequencing them using the Earliest Due Date (EDD) priority rule. What is the average flow time? Show your Work and round your...

  • 4. [10 points] Today is Nov 15. The following jobs need to be scheduled on the...

    4. [10 points] Today is Nov 15. The following jobs need to be scheduled on the same machine. Job Processing Time (Davs) Due Date Nov 30 Dec 22 Nov 18 Dec 3 Nov 29 12 a. Schedule the jobs according to i. Shortest processing time ii. Earliest due date. iii. Longest processing time. b. For the SPT& EED schedules from part a, calculate the average completion time.

  • The following table represents a plan for a project: PREDECESSOR JOB(S) TIMES (DAYS) JOB NO. a...

    The following table represents a plan for a project: PREDECESSOR JOB(S) TIMES (DAYS) JOB NO. a m b 1 – 2 4 9 2 1 2 2 11 3 1 2 4 6 4 1 3 7 8 5 2 2 3 4 6 3 1 2 6 7 4 3 5 10 8 5,6 1 3 5 9 8 1 2 12 10 7 3 4 5 11 9,10 1 5 6    b. Indicate the critical path. 1-2-5-8-9-11...

  • 5. A work center has five jobs assigned to it. They are labeled, in the order...

    5. A work center has five jobs assigned to it. They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D, and E. The work center may work on only one job at a time and must complete any job it starts before starting another job. Job A has a processing time of 6 days and is due to the customer in 9 days. Job B has a processing time of 2 days...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT