11.10
Constraints on borrowing.
Country Farmlands, Inc. is considering the following potential projects for this coming year, but has only$200,000 for these projects:
Project A: Cost $60,000, NPV $4,000, and IRR 11%
Project B: Cost $78,000, NPV $6,000, and IRR 12%
Project C: Cost $38,000, NPV $3,000, and IRR 10%
Project D: Cost $41,000, NPV $4,000, and IRR 9%
Project E: Cost $56,000, NPV $6,000, and IRR 13%
Project F: Cost $29,000, NPV $2,000, and IRR 7%
What projects should Farmlands pick?
What projects should Farmlands pick?
(Select the best responses.)
A. - A, C, D, and E.
B. - B, C, D, and F.
C. - A, B, D, and E.
D. - B, C, D, and E.
E. - C, D, E, and F.
Option 1 will be selected. Because with that option NPV of the all the project is highest of $17,000 and all investments are within $200,000.00
Therefore, Project A,C,D and E will be selected.
11.10 Constraints on borrowing. Country Farmlands, Inc. is considering the following potential projects for this coming...
Constraints on borrowing Country Farmlands, Inc. is considering the following potential projects for this coming year, but has only $200,000 for these projects: Cost $60,000, NPV S4.000, and IRR 11% Project A: Project B: Cost $78,000, NPV S6,000, and IRR 12% Project C: Cost S38 000, NPV $3.000, and IRR 10% Project D: Project E: Cost S56.000, NPV S6,000, and IRR 13% Project F: Cost S29.000. NPV $2.000, and IRR 7% Cost S4 1,000, NPV $4,000, and IRR 9% What...
9. The Ott Group, Inc., has identified the following two mutually exclusive projects: Year 0 Cash Flow (S) - $12,500 4,000 5,000 6,000 1,000 Cash Flow (L) - $12,500 1,000 6,000 5,000 4,000 a. What is the IRR for each of these projects? If you apply the IRR decision rule, which project should the company accept? b. If the required return is 11 percent, what is the NPV for each of these projects? Which project will you choose if you...
Suppose you are the financial manager of a firm considering the following five projects. Project A Project B Project C Project D Project E Initial Investment -$10,000 -$15,000 -$14,000 -$6,000 -$1,500 Year 1 $5,000 $5,000 $6,000 $4,000 $1,000 Year 2 $4,000 $5,000 $4,000 $2,000 $250 Year 3 $2,000 $5,000 $3,500 $2,000 $100 Year 4 $1,000 $5,000 $2,500 $2,000 $100 Year 5 $5,000 $2,000 $100 Year 6 $2,000 $100 Calculate the Payback Period for each project. Calculate the NPV for each...
NPV versus IRR Piercy, LLC, has identified the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) -$77,500 -$77,500 43,000 21,500 29,000 28,000 23,000 34,000 21,000 41,000 a. What is the IRR for each of these projects? If you apply the IRR decision rule, which project should the company accept? Is this decision necessarily correct? b. If the required return is 11 percent, what is the NPV for each of these projects? Which project will you choose...
You are considering the following two projects and can take only one. Your cost of capital is 11.4%. The cash flows for the two projects are as follows ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$98 $27 $29 $38 $51 B −$98 $51 $38 $29 $18 a. What is the IRR of each project? b. What is the NPV of each project at your cost of capital? c. At what cost of capital...
Weston Industries is considering the following independent projects for the coming year: Project Required Investment Expected Rate of Return Risk X $3 million 10.5% High Y 3 million 9.5% Average Z 7 million 6.5% Low Weston’s WACC is 9 percent, but it adjusts for risk by adding 2 percent to the WACC for high-risk projects and subtracting 2 percent for low-risk projects. Which project(s) should Weston accept assuming it faces no capital constraints? a. Project Z only b. Projects Y...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 12.25% High B 5 million 14.75 High C 3 million 10.25 Low D 2 million 10.25 Average E 6 million 13.25 High F 5 million 13.25 Average G 6 million 8.25 Low H 3 million 12.75 Low Ziege's WACC is 10.75%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
You are considering the following two projects and can take only one. Your cost of capital is 11.2%. The cash flows for the two projects are as follows ($ million): Project Year 0 - $101 - $101 Year 1 $22 $52 Year 2 $29 $40 Year 3 $40 $29 Year 4 $52 $18 a. What is the IRR of each project? b. What is the NPV of each project at your cost of capital? c. At what cost of capital...
You are considering the following two projects and can only take one. Your cost of capital is 11.4 %. The cash flows for the two projects are as follows ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$102 $27 $31 $39 $49 B −$102 $49 $39 $31 $20 a. What is the IRR of each project? b. What is the NPV of each project at your cost of capital? c. At what cost of...
Please show steps. Ziege Systems is considering the following independent projects for the coming year: Required Investment Rate of Return Project Risk $4 million 15.00% > High 5 million 12.50 0 High 0 3 million 10.50 Low 2 million 9.50 0 Average 6 million 13.50 m High 5 million 13.50 Average I Low 6 million 7.50 Low 3 million 12.25 Ziege's WACC is 11.00%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting...