Question

If the cost of installing a monitoring system to check product quality is $200,000, what is the capitalized cost at interest

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer :-

Capitalized cost the present worth of a constant annual cost over an infinite period of analysis.

Let the capitalized cost be P. Then,

P = $200,000+$40,000(P/A,15%,n=infinity)

P = $200,000+$40,000(1/0.15)

P = $200,000+$266,667 = $466,667

Thus, the capitalized cost will be $466,667

(please thumbs up if this helps you)

Add a comment
Know the answer?
Add Answer to:
If the cost of installing a monitoring system to check product quality is $200,000, what is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • : What are the advantages and disadvantages of installing the computerized reception system at Quality Care...

    : What are the advantages and disadvantages of installing the computerized reception system at Quality Care ?

  • A company is thinking of installing a computer-process control system in one of its plants. The...

    A company is thinking of installing a computer-process control system in one of its plants. The plant is used about 40%of the time (or 3,500 operating hours per year) to produce a proprietary product. During the remaining 60% of the time, it is used to produce other specialty products. Annual production of the proprietary product amounts to 30,000 units and sell for $15 per unit. The proposed computer-process control system will cost $650,000 and is expected to provide the following...

  • JIT Features and Product Costing Accuracy Prior to installing a IT system, Barker Company, a producer...

    JIT Features and Product Costing Accuracy Prior to installing a IT system, Barker Company, a producer of automobile parts, used maintenance hours to assign maintenance costs to its three products (wheels, brake pads, and ball bearings). The maintenance costs totaled 65,000,000 per year. The maintenance hours used by each product and the quantity of each product produced are as follows: Maintenance Hours 180,000 Wheels Quantity Produced 157.500 157,500 Pads 180,000 Bearings 240,000 210,000 After installing IT, three manufacturing cells were...

  • JIT Features and Product Costing Accuracy Prior to installing a JIT system, Barker Company, a producer...

    JIT Features and Product Costing Accuracy Prior to installing a JIT system, Barker Company, a producer of automobile parts, used maintenance hours to assign maintenance costs to its three products (wheels, brake pads, and ball bearings). The maintenance costs totaled $7,473,480 per year. The maintenance hours used by each product and the quantity of each product produced are as follows: Maintenance Hours Quantity Produced Wheels 199,000 174,125 Pads 199,000 174,125 Bearings 253,000 221,375 After installing IT, three manufacturing cells were...

  • JIT Features and Product Costing Accuracy Prior to installing a JIT system, Barker Company, a producer of automobile pa...

    JIT Features and Product Costing Accuracy Prior to installing a JIT system, Barker Company, a producer of automobile parts, used maintenance hours to assign maintenance costs to its three products (wheels, brake pads, and ball bearings). The maintenance costs totaled $7,263,620 per year. The maintenance hours used by each product and the quantity of each product produced are as follows: Maintenance Hours Quantity Produced Wheels 197,000 172,375 Pads 197,000 172,375 Bearings 220,000 192,500 After installing IT, three manufacturing cells were...

  • 5. Your client is considering two alternatives for a bioremediation system for treating groundwater, a water...

    5. Your client is considering two alternatives for a bioremediation system for treating groundwater, a water circulation system and an air injection system. The water circulation system has a construction cost of $1.3 million, annual O&M costs of $75,000, and refurbishment/upgrade costs of $220,00 every 15 years. The air circulation system has a construction cost of 1.7 million, annual operating costs of $57,000, and refurbishment/upgrade costs of $300,000 every 20 years. Assume the system will operate indefinitely for a number...

  • 10.24 An automaker is considering installing a three-dimensional (3-D) computerized car-styling system at a cost of...

    10.24 An automaker is considering installing a three-dimensional (3-D) computerized car-styling system at a cost of $230,000 (including hardware and software). With the 3-D computer modeling system, designers will have the ability to view their design from many angles and to fully account for the space required for the engine and passengers. The digital information used to create the computer model can be revised in consultation with engineers, and the data can be used to run milling machines that make...

  • Check my work Determine the capitalized cost of a permanent roadside historical marker that has a...

    Check my work Determine the capitalized cost of a permanent roadside historical marker that has a first cost of $85,000 and a maintenance cost of $2,900 once every 5 years. Use an interest rate of 14% per year. The capitalized cost is $

  • 8) Determine the capitalized cost of an alternative that has a first cost of $155,000, an...

    8) Determine the capitalized cost of an alternative that has a first cost of $155,000, an annual maintenance cost of $72,000, and a salvage value of $78,000 after its 10-year life. Use an interest rate of 6%. a. a) $187,142 b.c) $1,256,890 c. d) $1,452,367 d. b) 5871,000 QUESTIONS 9) The construction cost of a park is $600,000. Annual maintenance and operating costs are $120,000 per year. At an interest rate of 10% per year, the capitatlized cost of the...

  • Set-up The cost of installing a new piece of pollution control equipment at a cement factory...

    Set-up The cost of installing a new piece of pollution control equipment at a cement factory is $60,000. Engineers and public health officials estimate that if the equipment is installed now (at year o), in every year afterwards (for years 1, 2, 3, ...) it will produce a health benefit of $7,000. There will also be an annual cost of maintenance of $1,000 per year. Questions i. What is the present value of the net benefit of the pollution control...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT