Question

3- Tables below show activities of a small project, predecessors, duration time, and resources that are...

3- Tables below show activities of a small project, predecessors, duration time, and resources that are required (machines and workers). There are 3 machines and 4 workers available each day. Please use resource allocation algorithm to optimally allocate the recourses to the activities. Please specifies the project completion time.

Table 1: Activities, predecessors and duration time.

Activity

Predecessor

Duration

A

-

2

B

B

2

C

A,B

1

D

C,D

2

E

D

3

Table 2: Activities and their required number of workers and machines.  

A

B

C

D

E

# required of workers

3

3

4

1

2

# of required machines

0

3

3

2

3

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans. Given that From the given data is There are 3 machines and u workers availblo } each day. now o find the Earlier ces), o

Add a comment
Know the answer?
Add Answer to:
3- Tables below show activities of a small project, predecessors, duration time, and resources that are...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 3- Tables below show activities of a small project, predecessors, duration time, and resources that are...

    3- Tables below show activities of a small project, predecessors, duration time, and resources that are required (machines and workers). There are 3 machines and 4 workers available each day. Please use resource allocation algorithm to optimally allocate the recourses to the activities. Please specifies the project completion time. Table 1: Activities, predecessors and duration time. Predecessor Duration 2 Activity A B с D 2 1 B AB C.D D 2 E 3 Table 2: Activities and their required number...

  • Q5: A construction project consists of activities, immediate predecessors (IPA) and duration in weeks are as...

    Q5: A construction project consists of activities, immediate predecessors (IPA) and duration in weeks are as shown in the following table. Draw the project network diagram, find the critical path and calculate the corresponding project completion time. Also, find the total float as well as the free float for each activity and the non- critical activities. (10 Marks) ТРА Duration (Weeks) Activity A B نما 4 с 14 D A 10 E F A BD BD с F.H 5 4...

  • The table below defines the activities and the normal time duration for each activities within a...

    The table below defines the activities and the normal time duration for each activities within a small project. You can decrease (crash) the durations at an additional expense. Table 1 summarizes the time-cost information for the activities to complete the project. Table 1: The time-cost information for the activities Activity Normal Completion Time (weeks) Immediate Predecessor Crash Time (weeks) Normal cost for activities Crash cost for activities/week A 2 - 1 1200 400 B 3 - 1 1400 500 C...

  • Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A...

    Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...

  • The following data were obtained from a project to expand a warehouse: Activity Duration Predecessors Resources/cost...

    The following data were obtained from a project to expand a warehouse: Activity Duration Predecessors Resources/cost A 2 weeks -- 1 Excavator/$800 day B 3 weeks -- 1 Excavator/$800 day C 2 weeks -- 1 Concrete Mixer/$250 day D 3 weeks A 1 Crane/$1,000 day E 2 weeks C 1 High-lift/$500 day F 1 week B,D 1 Crane/$1,000 day The contractor has only one machine of each type available at the above costs, and operations cannot be split. Additional equipment...

  • Consider a project with the following information: Activity Duration Predecessors A 5 -- B 7 A...

    Consider a project with the following information: Activity Duration Predecessors A 5 -- B 7 A C 9 B D 5 B E 7 C, D F 6 D G 4 C H 7 E, F, G Activity Duration ES EF LS LF Float A 5 0 5 0 5 B 7 5 12 5 12 C 9 12 21 12 21 D 5 12 17 16 21 E 7 21 28 21 28 F 6 17 23 22 28...

  • Q4. CPM Consider the following list of activities and predecessors. Activity ProcessorsDuration (...

    Q4. CPM Consider the following list of activities and predecessors. Activity ProcessorsDuration (days) Build foundation Build walls&ceilin Build roof Complete electrical wirin Put in windows Put on sidin Paint house C,F a)Draw the network diagram. Write down the LP to determine the completion time. b)Suppose that by hiring additional workers, the duration of each activity can be reduced. The costs per day of reducing the duration of the activities are given in the following table. Write down the LP to...

  • The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning...

    The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning Company are given in the following table. Assume that the activity times are independent. Activity Immediate Predecessor a (time weeks) m (time weeks) b (time weeks) A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 Calculate the expected time (mean) and variance for each activity, then answer the following: a. What is the...

  • The estimated times and immediate predecessors for the activities in a project

    The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assume that the activity times are independent This exercise contains only parts a, b, c, d, and e. a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places): ExpectedActivityTimeWarlanceA9.830.26010.336.44C10.001.00010.001.78b) The expected completion time of the critical path weeks fround your response to two decimal...

  • o. 4 below are the resources and duration for a project Resources Activity Predecessor Duration Plumbers...

    o. 4 below are the resources and duration for a project Resources Activity Predecessor Duration Plumbers Laborers A,D 9 4 F,I Eleven plumbers and 9 laborers are available for this project. Both resources must work at the same time when assigned to the same activity. Prepare an activity schedule that satisfies the resource constraints. Part B Solve the problem using MS Project and show the total project duration. You should include Gantt and CPM Answer: Duration:

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT