Question

A firm with a 14% WACC is evaluating two projects for this years capital budget. After-tax cash flows, including depreciatio

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Pls find below the steps, working and answers:

a) NPV, IRR, MIRR, Payback Period and Discounted Payback period are highlighted in yellow in the below workings;

b) If the projects are independent, both these projects are recommended as the NPV of both is positive, IRR is higher than the discounting factor and Payback is lower than the life of the projects;

c) If the projects are mutually exclusive, then N is recommended as the NPV of the same is higher than that of the Project M;

d) Conflict between the IRR and NPV is due to two factors - the initial investment is different for both these projects and also, the timing of the cash flows and value of the cashflows also different.

YEAR 1 2 3 5 Project M Project N 0 -24,000 -72,000 8,000 22,400 8,000 22,400 8,000 22,400 4 8,000 22,400 8,000 22,400 Discoun

Computation of IRR: This can be computed using formula in Excel = IRR("range of cashflows", discounting factor%);

Computation of MIRR: This can be computed using formula in Excel = MIRR("range of cashflows", discounting factor%, reinvestment factor%); Here, both discounting factor % and reinvestment factor% are considered same.

Computation of Net Present Value (NPV) based on the Discounted Cash flows; The Discounting factor is computed based on the formula: For year 0, the discounting factor is 1; For Year 1, it is computed as = Year 0 factor /(1+discounting factor%) ; Year 2 = Year 1 factor/(1+discounting factor %) and so on;

Next, the cashflows need to be multiplied with the respective years' discounting factor, to arrive at the discounting cash flows;

The total of all the discounted cash flows is equal to its respective Project NPV of the Cash Flows;

Computation of Normal / Discounted Pay Back Period: Here, the period is computed for each project, based on cumulative normal /discounted cash flows: If the cumulative value is less than or equal to zero, the period is considered as 12 months (it means that the net cumulative cash flow has not yet paid back the initial investment); Once the value turns positive in a particular year, the period for such year is observed at a proportion of actual discounted cash flow to the cumulative CF; This gives the period less than 12 months in such year; Once this is computed, total of all the years is taken and divided by 12, to arrive at the Payback period in no.of years

Add a comment
Know the answer?
Add Answer to:
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two decimal places. Do...

  • A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: Project M -$24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M:    $   Project N:    $   Calculate IRR for each project. Do not round intermediate calculations. Round your answers to two decimal places. Project M:       % Project...

  • A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: Project M Project N -$18,000 $6,000 $6,000 $6,000 $6,000 $6,000 -$54,000 $16,800 $16,800 $16,800 $16,800 $16,800 a. Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M: $ Project N: $ Calculate IRR for each project. Do not round Intermediate calculations. Round your answers to two decimal places....

  • A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M Project N - $12,000 $4,000 $4,000 $4,000 $4,000 $4,000 -$36,000 $11,200 $11,200 $11,200 $11,200 $11,200 a. Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M: $ Project N: $ Calculate IRR for each project. Do not round intermediate calculations....

  • A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$21,000 $7,000 $7,000 $7,000 $7,000 $7,000 Project N -$63,000 $19,600 $19,600 $19,600 $19,600 $19,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two decimal places. Do...

  • A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M $(21,000) $7,000 $7,000 $7,000 $7,000 $7,000 Project N $(63,000) $19,600 $19,600 $19,600 $19,600 $19,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two decimal places. Do...

  • A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 1 2 Project M Project N - $3,000 -$9,000 $1,000 $2,800 $1,000 $2,800 $1,000 $2,800 $1,000 $2,800 $1,000 $2,800 a. Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M: $ Project N: $ Calculate IRR for each project. Do not round intermediate calculations. Round your answers to...

  • A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 1 2 34 5 Project M Project N -$18,000 $6,000 $6,000 $6,000 $6,000 $6,000 -$54,000 $16,800 $16,800 $16,800 $16,800 $16,800 a. Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M: $ Project N: $ Calculate IRR for each project. Do not round intermediate calculations. Round your answers...

  • A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M:    $   Project N:    $   Calculate IRR for each project. Do not round intermediate calculations. Round your answers to...

  • A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 23 5 Project M Project N - $30,000 $10,000 $10,000 $10,000 $10,000 $10,000 - $90,000 $28,000 $28,000 $28,000 $28,000 $28,000 a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to two...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT