Question

A firm with a 14% WACC is evaluating two projects for this years capital budget. After-tax cash flows, including depreciatio

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Project M:

year 2 3 cash flow Discount factor @14% Present value 4000 0.877192982456 3508.77193 4000 0.769467528470 3077.870114 4000 0.6

NPV = -initial cash outflow + present value of cash inflows

NPV of project M = -12000+13732.32388 = 1732.32(rounded to two decimals)

Project N:

year 1 ما می cash flow Discount factor @14% Present value 11200 0.877192982456 9824.561404 11200 0.769467528470 8618.036319 1

NPV = -36000+38450.50685 = 2450.51(rounded to two decimal places)

IRR:

Project M:

f =IRR(B2:B7) B8 A Year C 1 - B cash flow -12000 4000 4000 4000 4000 4000 19.86% IRR

IRR = 19.86% using spread sheet. formula can be seen as above

Project N:

B8 A Year fx =IRR(B2:37) D E C 1 B cash flow -36000 11200 11200 11200 11200 11200 16.80% 8 IRR

IRR = 16.80%

MIRR:

Project M:

f =MIRR(B2:07,14%,14%) с 1 о. B8 • o А в Year cash flow -12000 4000 2 4000 з 4000 4 4000 5 4000 MIRR | 17.12% 7 8

MIRR = 17.12%

Project N:

B9 f c =MIRR(B3:38,14% 14%) D E F A B C 2 Year 3 0 cash flow -36000 11200 11200 11200 11200 11200 15.51% 1 2 3 4 5 MIRR 6 8 9

MIRR = 15.51%

NOTE:Reinvestment rate in MIRR is also taken as 14%

Payback period:

Payback Period = initial cash outflow / cash inflow

Project M:

Payback period = 12000 / 4000 = 3 Years

Project N:

Payback Period = 36000 / 11200 = 3.21 years

Discounted payback Period:

Discounted pay back = time required for Present value of discounted cash flows to recover initial cash outflow

Project M:

Total of first 4 years present value of cash flows = 11654.85

remaining amount required = 12000 - 11654.85 = 345.15

Discounted Pay Back = 4 + 345.15 / 2077.47

= 4.17 Years

Project N :

Total of first 4 years present value of cash flows = 32633.58

remaining amount required = 36000 - 32633.58 = 3366.42

Discounted Pay Back = 4 + 3366.42 / 5816.93

= 4.58 Years

B)

Both projects have positive Net present values.both can be selected

C)

it is given both projects are mutually exclusive so only one can be selected.it can be seen that Project B has highest NPV so project B should be selected.

D)

the conflict is Because both Projects are different in Size.Project B is larger than Project A.

  

Add a comment
Know the answer?
Add Answer to:
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: Project M Project N -$18,000 $6,000 $6,000 $6,000 $6,000 $6,000 -$54,000 $16,800 $16,800 $16,800 $16,800 $16,800 a. Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M: $ Project N: $ Calculate IRR for each project. Do not round Intermediate calculations. Round your answers to two decimal places....

  • A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: Project M -$24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M:    $   Project N:    $   Calculate IRR for each project. Do not round intermediate calculations. Round your answers to two decimal places. Project M:       % Project...

  • A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 1 2 Project M Project N - $3,000 -$9,000 $1,000 $2,800 $1,000 $2,800 $1,000 $2,800 $1,000 $2,800 $1,000 $2,800 a. Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M: $ Project N: $ Calculate IRR for each project. Do not round intermediate calculations. Round your answers to...

  • A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 1 2 34 5 Project M Project N -$18,000 $6,000 $6,000 $6,000 $6,000 $6,000 -$54,000 $16,800 $16,800 $16,800 $16,800 $16,800 a. Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M: $ Project N: $ Calculate IRR for each project. Do not round intermediate calculations. Round your answers...

  • A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M - $24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to...

  • A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two decimal places. Do...

  • A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 23 5 Project M Project N - $30,000 $10,000 $10,000 $10,000 $10,000 $10,000 - $90,000 $28,000 $28,000 $28,000 $28,000 $28,000 a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to two...

  • A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$21,000 $7,000 $7,000 $7,000 $7,000 $7,000 Project N -$63,000 $19,600 $19,600 $19,600 $19,600 $19,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two decimal places. Do...

  • A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M $(21,000) $7,000 $7,000 $7,000 $7,000 $7,000 Project N $(63,000) $19,600 $19,600 $19,600 $19,600 $19,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two decimal places. Do...

  • CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's...

    CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 5 Project M Project N - $30,000 $10,000 $10,000 $10,000 $10,000 $10,000 $90,000 $28,000 $28,000 $28,000 $28,000 $28,000 a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT