a | ||||||
Project M | ||||||
Discount rate | 0.14 | |||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow stream | -18000 | 6000 | 6000 | 6000 | 6000 | 6000 |
Discounting factor | 1 | 1.14 | 1.2996 | 1.481544 | 1.6889602 | 1.925415 |
Discounted cash flows project | -18000 | 5263.158 | 4616.805 | 4049.829 | 3552.4817 | 3116.212 |
NPV = Sum of discounted cash flows | ||||||
NPV Project M = | 2598.49 | |||||
Where | ||||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||||
Discounted Cashflow= | Cash flow stream/discounting factor | |||||
Project N | ||||||
Discount rate | 0.14 | |||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow stream | -54000 | 16800 | 16800 | 16800 | 16800 | 16800 |
Discounting factor | 1 | 1.14 | 1.2996 | 1.481544 | 1.6889602 | 1.925415 |
Discounted cash flows project | -54000 | 14736.84 | 12927.05 | 11339.52 | 9946.9487 | 8725.394 |
NPV = Sum of discounted cash flows | ||||||
NPV Project N = | 3675.76 | |||||
Where | ||||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||||
Discounted Cashflow= | Cash flow stream/discounting factor | |||||
b | ||||||
Project M | ||||||
IRR is the rate at which NPV =0 | ||||||
IRR | 0.198577097 | |||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow stream | -18000 | 6000 | 6000 | 6000 | 6000 | 6000 |
Discounting factor | 1 | 1.198577 | 1.436587 | 1.72186 | 2.0637824 | 2.473602 |
Discounted cash flows project | -18000 | 5005.936 | 4176.566 | 3484.603 | 2907.2833 | 2425.612 |
NPV = Sum of discounted cash flows | ||||||
NPV Project M = | 3.1177E-05 | |||||
Where | ||||||
Discounting factor = | (1 + IRR)^(Corresponding period in years) | |||||
Discounted Cashflow= | Cash flow stream/discounting factor | |||||
IRR= | 20% | |||||
Project N | ||||||
IRR is the rate at which NPV =0 | ||||||
IRR | 0.167976214 | |||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow stream | -54000 | 16800 | 16800 | 16800 | 16800 | 16800 |
Discounting factor | 1 | 1.167976 | 1.364168 | 1.593316 | 1.8609555 | 2.173552 |
Discounted cash flows project | -54000 | 14383.85 | 12315.19 | 10544.05 | 9027.6204 | 7729.284 |
NPV = Sum of discounted cash flows | ||||||
NPV Project N = | 2.29795E-06 | |||||
Where | ||||||
Discounting factor = | (1 + IRR)^(Corresponding period in years) | |||||
Discounted Cashflow= | Cash flow stream/discounting factor | |||||
IRR= | 17% | |||||
c | ||||||
Project M | ||||||
Combination approach | ||||||
All negative cash flows are discounted back to the present and all positive cash flows are compounded out to the end of the project’s life | ||||||
Thus year 5 modified cash flow=(10133.76)+(8889.26)+(7797.6)+(6840)+(6000) | ||||||
=39660.62 | ||||||
Thus year 0 modified cash flow=-18000 | ||||||
=-18000 | ||||||
Discount rate | 0.14 | |||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow stream | -18000 | 6000 | 6000 | 6000 | 6000 | 6000 |
Discount factor | 1 | 1.14 | 1.2996 | 1.481544 | 1.6889602 | 1.925415 |
Compound factor | 1 | 1.68896 | 1.481544 | 1.2996 | 1.14 | 1 |
Discounted cash flows | -18000 | 0 | 0 | 0 | 0 | 0 |
Compounded cash flows | 0 | 10133.76 | 8889.26 | 7797.6 | 6840 | 6000 |
Modified cash flow | -18000 | 0 | 0 | 0 | 0 | 39660.62 |
Discounting factor (using MIRR) | 1 | 1.171163 | 1.371623 | 1.606394 | 1.88135 | 2.203368 |
Discounted cash flows | -18000 | 0 | 0 | 0 | 0 | 18000 |
NPV = Sum of discounted cash flows | ||||||
NPV= | 5.71936E-05 | |||||
MIRR is the rate at which NPV = 0 | ||||||
MIRR= | 17.12% | |||||
Where | ||||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||||
Discounted Cashflow= | Cash flow stream/discounting factor | |||||
Compounding factor = | (1 + reinvestment rate)^(time of last CF-Corresponding period in years) | |||||
Compounded Cashflow= | Cash flow stream*compounding factor |
Please ask remaining parts seperately, questions are unrelated |
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...
A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 1 2 34 5 Project M Project N -$18,000 $6,000 $6,000 $6,000 $6,000 $6,000 -$54,000 $16,800 $16,800 $16,800 $16,800 $16,800 a. Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M: $ Project N: $ Calculate IRR for each project. Do not round intermediate calculations. Round your answers...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 1 1 2 3 4 5 Project M Project N -$18,000 $6,000 $6,000 $6,000 $6,000 $6,000 -$54,000 $16,800 $16,800 $16,800 $16,800 $16,800 Calculate discounted payback for each project. Do not round intermediate calculations. Round your answers to two decimal places. Project M: years Project N: years b. Assuming the projects are independent, which one(s) would you recommend?...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M Project N - $12,000 $4,000 $4,000 $4,000 $4,000 $4,000 -$36,000 $11,200 $11,200 $11,200 $11,200 $11,200 a. Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M: $ Project N: $ Calculate IRR for each project. Do not round intermediate calculations....
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: Project M -$24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M: $ Project N: $ Calculate IRR for each project. Do not round intermediate calculations. Round your answers to two decimal places. Project M: % Project...
A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 1 2 Project M Project N - $3,000 -$9,000 $1,000 $2,800 $1,000 $2,800 $1,000 $2,800 $1,000 $2,800 $1,000 $2,800 a. Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M: $ Project N: $ Calculate IRR for each project. Do not round intermediate calculations. Round your answers to...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M - $24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to two decimal places. Do...
A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 23 5 Project M Project N - $30,000 $10,000 $10,000 $10,000 $10,000 $10,000 - $90,000 $28,000 $28,000 $28,000 $28,000 $28,000 a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to two...
A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$21,000 $7,000 $7,000 $7,000 $7,000 $7,000 Project N -$63,000 $19,600 $19,600 $19,600 $19,600 $19,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to two decimal places. Do...
A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M $(21,000) $7,000 $7,000 $7,000 $7,000 $7,000 Project N $(63,000) $19,600 $19,600 $19,600 $19,600 $19,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to two decimal places. Do...