Question

Q5 Part I -What is the most cost impact in building a formwork? a. Rent the...

Q5

Part I -What is the most cost impact in building a formwork?

a. Rent the formwork

b. Labor

c. Wood material

d. Availability of the material

Part II - An estimate on doing the structural metal work (columns, beams, joists, etc) will determine the cost per

a. metal item

b. ton

c. hours plus delivery costs.

d. calculated costs from RS Means

Part III- When wood framing is used on a project, the estimator must calculate the required ________ on the project.

a. square footage of lumber

b. number of 2X4's and 2X6's

c. number of board feet

d. cost of wood versus metal

0 0
Add a comment Improve this question Transcribed image text
Answer #1

5) part I:Rent of formwork (a)

part II : ton(b)

part III : number of 2×4 's and 2×6's ( b)

Add a comment
Know the answer?
Add Answer to:
Q5 Part I -What is the most cost impact in building a formwork? a. Rent the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 12. A slab on grade measures 120 long x 60" wide x 2' 6" thick. What is the cost to form the slab...

    12. A slab on grade measures 120 long x 60" wide x 2' 6" thick. What is the cost to form the slab if formwork costs S1 per square foot of contact area? A. $72 B.S90 C.S162 D.S180 13. A place concrete' activity requires the placement of 2,080 cubic yards. If the individual production rate is 2 cubic yards per workhour per person, with a 10-person crew and 8-hour workday, how many days are needed to complete this activity? A....

  • Q-4 Part I - What is the number of board feet for the following: 100 each...

    Q-4 Part I - What is the number of board feet for the following: 100 each 2”x 4 “x 10’-0” a) 780 b) 667 c) 600 d) 1000 Part II - The raise and the span of a roof is 10’ and 60’ respectively, the run and the length of rafter are: a) 5’ and 36’ b) 30’ and 31.65’ c) 6’ and 33.6’ d) 10’ and 31.65’ Part III - Which of the following is another name for metal...

  • Auge Steel Framing Details 1. Complete all light g auge steel componente ir the following wall se...

    auge Steel Framing Details 1. Complete all light g auge steel componente ir the following wall section, including floor joists, wall studs, roof rafters, and required clips angles, stiffeners, and fasteners. Label all components. Roof sheathing Wall sheathing 。 Interior wallboard Subflooring Foundation 103 Scale: l square =2" (50 mm) Name: necessity of cutting holes in m on the construction ste 12.11. 12.15). Thack etions a sed for top and bottom plates, e construction, shemperature that col tural shapes. Prers...

  • just part E please Norwegian Satellite Development Company (NSDC) Cost Estimates for World Satellite Telephone Exchange...

    just part E please Norwegian Satellite Development Company (NSDC) Cost Estimates for World Satellite Telephone Exchange Project NSDC has a contract to produce 7 satellites to support a worldwide telephone system (for Alaska Telecom, Inc.) that allows individuals to use a single, portable telephone in any location on earth to call in and out. NSDC will develop and produce the 7 units. NSDC has estimated that the R&D costs will be NOK (Norwegian Krone) 15,000,000. Material costs are expected to...

  • answer the questions based on the informations on the 3 pictures please: What are the essential...

    answer the questions based on the informations on the 3 pictures please: What are the essential responsibilities of a structural designer or engineer in designing a structure? What factors would you consider and why when planning the design of a building structure? You are the project team leader for the design of a single family house in southwest Houston area. Discuss the types of structural loads you think are important and explain why.​​​​​​​ d) Thermal load changes in perature cause...

  • Please help with part 4-9. I will highly apprecite it. The Business Situation Concrete Helmet Company...

    Please help with part 4-9. I will highly apprecite it. The Business Situation Concrete Helmet Company is a newly formed company that manufactures bicycle helmets. The company began operations January 1, 2020. Its accountant quit the second week of operations, and the company is searching for a replacement. The company has decided to test the knowledge and ability of all candidates interviewing for the position Each candidate will be provided with the information below and then asked to prepare a...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT