Question

A corporate project under consideration has an IRR of 15% and a Beta of 0.5. The...

A corporate project under consideration has an IRR of 15% and a Beta of 0.5. The

      risk-free rate is 6% (T-Bill Rate). The expected rate of return for the market

      portfolio is 17%. Should the project be accepted? Should it be accepted if now the

      Beta is 1.5? Why does your answer change? (Show ALL calculations).

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Expected rate of return on project = risk free rate + beta * (expected rate of return for the market portfolio - risk free rate)

= 6% + .5 * (17% - 6%)

= 6% + .5 * 11%

= 6% + 5.5%

= 11.5%

Since the expected rate of reutn on the project is less than IRR we should not accpet the project.

Expected rate of when beta is 1.5 = risk free rate + beta * (expected rate of return for the market portfolio - risk free rate)

= 6% + 1.5 * (17% - 6%)

= 6% + 1.5 * 11%

= 22.5%

Once the beta increased to 1.5 then we should accpet the project.

We should accpet the project because the expected return on the project is higher than the IRR.

Add a comment
Know the answer?
Add Answer to:
A corporate project under consideration has an IRR of 15% and a Beta of 0.5. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A project under consideration has an internal rate of return of 18% and a beta of 0.5. The risk-free rate is 6%, and the...

    A project under consideration has an internal rate of return of 18% and a beta of 0.5. The risk-free rate is 6%, and the expected rate of return on the market portfolio is 18%. a. What is the required rate of return on the project? (Do not round intermediate calculations. Enter your answer as a whole percent.) b. Should the project be accepted? c. What is the required rate of return on the project if its beta is 1.50? (Do...

  • A project under consideration has an internal rate of return of 15% and a beta of...

    A project under consideration has an internal rate of return of 15% and a beta of 0.9. The risk-free rate is 5%, and the expected rate of return on the market portfolio is 15%. a. What is the required rate of return on the project? (Do not round intermediate calculations. Enter your answer as a whole percent.) b. Should the project be accepted? Yes No c. What is the required rate of return on the project if its beta is...

  • A project under consideration has an internal rate of return of 14% and a beta of...

    A project under consideration has an internal rate of return of 14% and a beta of 0.6. The risk-free rate is 9%, and the expected rate of return on the market portfolio is 14%. a-1. Calculate the required return.   Required return %   a-2. Should the project be accepted?         Yes   No b-1. Calculate the required return if its beta is 1.6.   Required return %   b-2. Should the project be accepted?         Yes  ...

  • Currently under consideration is a project with a beta of 1.50

    Currently under consideration is a project with a beta of 1.50. At this time, the risk free rate of return is 7% and the return on the market portfolio of assets is 10%.The project is actually expected to earn an annual rate of return of 11%.a. If the return on the market portfolio were to increase by 10%, what would be the expected to happen to the project’s required return? What if the market return were to decline by 10%?b....

  • An all-equity firm is considering the following projects: Project Beta IRR W 0.80 9.4% X .95...

    An all-equity firm is considering the following projects: Project Beta IRR W 0.80 9.4% X .95 10.9% Y 1.15 13.0% Z 1.45 14.2% The firm’s overall cost of capital is 11%. Assume T -bill rate is 3.5 percent, and the expected return on the market is 11 percent. a. Which projects should be accepted? And Why?

  • 17. SML and WACC [LO1] An all-equity firm is considering the following projects: Project Beta IRR...

    17. SML and WACC [LO1] An all-equity firm is considering the following projects: Project Beta IRR W 8.9% X .85 .92 1.09 1.35 10.8 12.8 < 13.3 N The T-bill rate is 4 percent, and the expected return on the market is 11 percent. a. Which projects have a higher expected return than the firm's 11 percent cost of capital? b. Which projects should be accepted? c. Which projects would be incorrectly accepted or rejected if the firm's overall cost...

  • project A has beta of .69 and an IRR of 9.27. project B has 1.13 beta...

    project A has beta of .69 and an IRR of 9.27. project B has 1.13 beta and an IRR of 11.58%. which of these projects will you accept and which will you reject if the risk free rate of return is 3.6% and the market rate return is 10.8%. A. accept project a and b B. reject project a and b C. accept project a and reject ptoject b D. reject project A and accept project b

  • An all-equity firm is considering the following projects: Project Beta .89 76 141 IRR 10.3% 108...

    An all-equity firm is considering the following projects: Project Beta .89 76 141 IRR 10.3% 108 143 173 1.52 The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. a. Which projects have a higher/lower expected return than the firm's 12.3 percent cost of capital? expected return, Project X has a expected return, Project Y has a Project W has a expected return, and Project Z has a expected return b. Which projects should...

  • An all-equity firm is considering the following projects: Project Beta 80 90 1.10 1.35 IRR 9.3%...

    An all-equity firm is considering the following projects: Project Beta 80 90 1.10 1.35 IRR 9.3% 11.4 12.1 15.1 The T-bill rate is 4 percent, and the expected return on the market is 12 percent. a. Which projects have a higher expected return than the firm's 12 percent cost of capital? expected retum, Project X has a Project W has a expected return, and Project Z has a expected return, Project Y has a expected return. b. Which projects should...

  • An all-equity firm is considering the following projects: Project Beta IRR W .64     9.5 % X...

    An all-equity firm is considering the following projects: Project Beta IRR W .64     9.5 % X .75     10.6 Y 1.31     14.1 Z 1.42     17.2 The T-bill rate is 5.2 percent, and the expected return on the market is 12.2 percent. a. Which projects have a higher/lower expected return than the firm’s 12.2 percent cost of capital? b. Which projects should be accepted? c. Which projects will be incorrectly accepted/rejected or correctly accepted/rejected if the firm's overall cost of capital were...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT