Solution:
(1) OCR:
Over cosolidation ratio is the ratio of past maximum pressure to the present pressure.
here past maximum pressure was at that time when building A did not remove.
Pressure when building was there = Building pressure + Soil pressure at the middle of clay layer
= 13.64+15*2+20*4
= 123.64 kN/m2
Preseent pressure after removing building A is due to soil only which is equal to 110 kN.
(2) The void ratio of clay layer:
(a) Immediately after removing building A:
(b) After long time from removing building A:
(3) Final consolidation settlement of Building B if to be constructed:
(a) Immediately after removing building A:
(b) After long time from removing building A:
(4) Time required to achieve half consolidation settlement after constructing Building B:
Tv= time factor... here for 50% consolidation its value is 0.196
d = drainage path = 10m
Cv = 0.5 ( given in data)
subject / soil mechanics i want the solution as soon as possible Q3:- The old building...
subject: soil mechanics 03:- The old building (A) is to be removed and replaced by a new building (B), as shown in Figure (Q3). The vertical pressure at the center of the clay layer from the building (A) and building (B) is equal to 13.64 kN/m² and 23.3 kN/mº respectively, Find:- 1. O.C.R after removing building (A). 2. The void ratio (e) of the clay layer: a. Immediately after removing building (A). b. After a very long time from removing...
Soil mechanical Soil mechanical Q3:- The old building (A) is to be removed and replaced by a new building (B), as shown in Figure (93). The vertical pressure at the center of the clay layer from the building (A) and building (B) is equal to 13.64 kN/m' and 23.3 kN/mrespectively, Find:- 1. O.C.R after removing building (A). 2. The void ratio (e) of the clay layer: a. Immediately after removing building (A). b. After a very long time from removing...
Q3:- The old building (A) is to be removed and replaced by a new building (B), as shown in Figure (03). The vertical pressure at the center of the clay layer from the building (A) and building (B) is equal to 13.64 kN/m² and 23.3 kN/m” respectively, Find:- 1. O.C.R after removing building (A). 2. The void ratio (e) of the clay layer: a. Immediately after removing building (A). b. After a very long time from removing building (A). 3....
hello, could anyone help me with this question, please. Q3:- The old building (A) is to be removed and replaced by a new building (B), as shown in Figure (Q3). The vertical pressure at the center of the clay layer from the building (A) and building (B) is equal to 13.64 kN/m² and 23.3 kN/mº respectively, Find 1. O.C.R after removing building (A). 2. The void ratio (e) of the clay layer: a. Immediately after removing building (A). b. After...
soil mechanics Q1) An oedometer test was performed on a 2 cm thick clay sample drained on both sides taken from the mid clay layer shown below, after 10 minutes 50% consolidation is reached. a) How long time in days would the same degree of consolidation(50%) be reached in the field ? b) How much the final settlement would be reached in the clay layer.? c) How much the preconsolidation pressure of a specimen. ? Sm 2m Sand surcharge y...
subject / soil mechanics i want the solution as soon as possible Q2:- The depth of water in a well is 3 m. Below the bottom of the well lies a layer of sand 5 meters thick overlying a clay deposit as shown in Figure (Q2). The saturated unit weight of the sand and clay are respectively 19.5 kN/m' and 20.64 kN/m'. Determine the effective stress at points A and B. 1 AN Figure (Q2) 3 m Sand 5 m...
soil Q1) An oedometer test was performed on a 2 cm thick clay sample drained on both sides taken from the mid clay layer shown below, after 10 minutes 50% consolidation is reached . a) How long time in days would the same degree of consolidation(50%) be reached in the field ?. b) How much the Final settlement would be reached in the clay layer.? c) How much the preconsolidation pressure of a specimen. ? 3m 2m Sand surcharge Y...
Q1) An oedometer test was performed on a 2 cm thick clay sample drained on both sides taken from the mid clay layer shown below , after 10 minutes 50% consolidation is reached. a) How long time in days would the same degree of consolidation(50%) be reached in the field ?. b) How much the Final settlement would be reached in the clay layer.? c) How much the preconsolidation pressure of a specimen. ? 3m 2m Sand surcharge Y= 17...
For the soil profile shown below, calculate the final settlement due to the placement of the sand fill. Estimate the excess pore pressure at a depth of 1.5 m into the third clay layer 1.5 years after the fill is placed. Assume the coefficient of consolidation is Cv = 1.8 m2/yr. Fill y = 16.0 kN/m² (3m thick) Clay 1 (3m thick) Sand (0.5m thick) Clay 2 (2m thick) Sand (0.5m thick) Clay 3 (4m thick) Sand (0.5m thick) eo...
I want solution! 3. A laboratory consolidation test was conducted on a specimen collected form the middle of the overconsolidated clay layer and the field consolidation curve is given below. The effective overburden pressure was 40.95 kN/m²at the middle of the clay layer. Calculate a) the recompression index, b) the compression index, and c) the consolidation settlement when the average vertical stress increment at the middle of the clay layer is 50kN/m² due to a foundation load. The thickness of...