Soil mechanical Soil mechanical Q3:- The old building (A) is to be removed and replaced by...
Q3:- The old building (A) is to be removed and replaced by a new building (B), as shown in Figure (03). The vertical pressure at the center of the clay layer from the building (A) and building (B) is equal to 13.64 kN/m² and 23.3 kN/m” respectively, Find:- 1. O.C.R after removing building (A). 2. The void ratio (e) of the clay layer: a. Immediately after removing building (A). b. After a very long time from removing building (A). 3....
subject: soil mechanics
03:- The old building (A) is to be removed and replaced by a new building (B), as shown in Figure (Q3). The vertical pressure at the center of the clay layer from the building (A) and building (B) is equal to 13.64 kN/m² and 23.3 kN/mº respectively, Find:- 1. O.C.R after removing building (A). 2. The void ratio (e) of the clay layer: a. Immediately after removing building (A). b. After a very long time from removing...
subject / soil mechanics
i want the solution as soon as
possible
Q3:- The old building (A) is to be removed and replaced by a new building (B), as shown in Figure (03). The vertical pressure at the center of the clay layer from the building (A) and building (B) is equal to 13.64 kNm and 23.3 kN/m” respectively, Find:- 1. O.C.R after removing building (A). 2. The void ratio (e) of the clay layer: a. Immediately after removing building...
hello, could anyone help me with this question,
please.
Q3:- The old building (A) is to be removed and replaced by a new building (B), as shown in Figure (Q3). The vertical pressure at the center of the clay layer from the building (A) and building (B) is equal to 13.64 kN/m² and 23.3 kN/mº respectively, Find 1. O.C.R after removing building (A). 2. The void ratio (e) of the clay layer: a. Immediately after removing building (A). b. After...
soil
Q1) An oedometer test was performed on a 2 cm thick clay sample drained on both sides taken from the mid clay layer shown below, after 10 minutes 50% consolidation is reached . a) How long time in days would the same degree of consolidation(50%) be reached in the field ?. b) How much the Final settlement would be reached in the clay layer.? c) How much the preconsolidation pressure of a specimen. ? 3m 2m Sand surcharge Y...
soil mechanics
Q1) An oedometer test was performed on a 2 cm thick clay sample drained on both sides taken from the mid clay layer shown below, after 10 minutes 50% consolidation is reached. a) How long time in days would the same degree of consolidation(50%) be reached in the field ? b) How much the final settlement would be reached in the clay layer.? c) How much the preconsolidation pressure of a specimen. ? Sm 2m Sand surcharge y...
For the soil profile shown below, calculate the final settlement due to the placement of the sand fill. Estimate the excess pore pressure at a depth of 1.5 m into the third clay layer 1.5 years after the fill is placed. Assume the coefficient of consolidation is Cv = 1.8 m2/yr. Fill y = 16.0 kN/m² (3m thick) Clay 1 (3m thick) Sand (0.5m thick) Clay 2 (2m thick) Sand (0.5m thick) Clay 3 (4m thick) Sand (0.5m thick) eo...
Q1) An oedometer test was performed on a 2 cm thick clay sample drained on both sides taken from the mid clay layer shown below , after 10 minutes 50% consolidation is reached. a) How long time in days would the same degree of consolidation(50%) be reached in the field ?. b) How much the Final settlement would be reached in the clay layer.? c) How much the preconsolidation pressure of a specimen. ? 3m 2m Sand surcharge Y= 17...
A 2-m thick of compacted soil of unit weight 20 kN/m3 will be placed on the top of the ground surface. Δσ y 14.0 kN/m3 3.0 m Sand Y 17.5 kN/m3 2.0 m 3.0m A Soft clay y= 13.5 kN/m3 6.0 m Medium clay y=15.0 kN/m3 B 4.0 m Bedrock a) Before placing the compacted soil, what are the overconsolidation ratios (OCR) for point A and B? b) When placing the compacted soil, what external load Ag would be? c)...
Figure P3 shows the soil profile at a site for a proposed office building. It is expected that the vertical stress at the top of the clay will increase by 150 kPa and at the bottom by 90 kPa. Assurning a linear stress distribution within the clay: (a) Calculate the consolidation settlement. You should divide the clay into five layers, compute the settlement for each layer, and then find the total settlement. Assume G = 2.7 for both sand and...