Question
subject: soil mechanics
03:- The old building (A) is to be removed and replaced by a new building (B), as shown in Figure (Q3). The vertical pressure
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Building B) fold Building (A) 13 64 kN/m2 7 23.3 kN/m2 (for new NGL 2m Sand, I 2 18 kN/m² y C = 9-es om Clay, I = 20 kN/m² W

le 20.806 C volt ratio after evemoval of A) 30 as. After immedlately removal of A to +A5 AH= Cc Ho teo logia 18694 2002x8 1 +

Total settlement 162.6+ 110.3 22729 mm 4. Tome for% 50%. Tv - U? Tigo 20.196 4 TV a Cut d² Bo 1962 0.5 mHyr xt ţ t = 0.19 688

Add a comment
Know the answer?
Add Answer to:
subject: soil mechanics 03:- The old building (A) is to be removed and replaced by a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Soil mechanical Soil mechanical Q3:- The old building (A) is to be removed and replaced by...

    Soil mechanical Soil mechanical Q3:- The old building (A) is to be removed and replaced by a new building (B), as shown in Figure (93). The vertical pressure at the center of the clay layer from the building (A) and building (B) is equal to 13.64 kN/m' and 23.3 kN/mrespectively, Find:- 1. O.C.R after removing building (A). 2. The void ratio (e) of the clay layer: a. Immediately after removing building (A). b. After a very long time from removing...

  • subject / soil mechanics i want the solution as soon as possible Q3:- The old building...

    subject / soil mechanics i want the solution as soon as possible Q3:- The old building (A) is to be removed and replaced by a new building (B), as shown in Figure (03). The vertical pressure at the center of the clay layer from the building (A) and building (B) is equal to 13.64 kNm and 23.3 kN/m” respectively, Find:- 1. O.C.R after removing building (A). 2. The void ratio (e) of the clay layer: a. Immediately after removing building...

  • Q3:- The old building (A) is to be removed and replaced by a new building (B),...

    Q3:- The old building (A) is to be removed and replaced by a new building (B), as shown in Figure (03). The vertical pressure at the center of the clay layer from the building (A) and building (B) is equal to 13.64 kN/m² and 23.3 kN/m” respectively, Find:- 1. O.C.R after removing building (A). 2. The void ratio (e) of the clay layer: a. Immediately after removing building (A). b. After a very long time from removing building (A). 3....

  • hello, could anyone help me with this question, please. Q3:- The old building (A) is to...

    hello, could anyone help me with this question, please. Q3:- The old building (A) is to be removed and replaced by a new building (B), as shown in Figure (Q3). The vertical pressure at the center of the clay layer from the building (A) and building (B) is equal to 13.64 kN/m² and 23.3 kN/mº respectively, Find 1. O.C.R after removing building (A). 2. The void ratio (e) of the clay layer: a. Immediately after removing building (A). b. After...

  • soil mechanics Q1) An oedometer test was performed on a 2 cm thick clay sample drained...

    soil mechanics Q1) An oedometer test was performed on a 2 cm thick clay sample drained on both sides taken from the mid clay layer shown below, after 10 minutes 50% consolidation is reached. a) How long time in days would the same degree of consolidation(50%) be reached in the field ? b) How much the final settlement would be reached in the clay layer.? c) How much the preconsolidation pressure of a specimen. ? Sm 2m Sand surcharge y...

  • soil Q1) An oedometer test was performed on a 2 cm thick clay sample drained on...

    soil Q1) An oedometer test was performed on a 2 cm thick clay sample drained on both sides taken from the mid clay layer shown below, after 10 minutes 50% consolidation is reached . a) How long time in days would the same degree of consolidation(50%) be reached in the field ?. b) How much the Final settlement would be reached in the clay layer.? c) How much the preconsolidation pressure of a specimen. ? 3m 2m Sand surcharge Y...

  • Q1) An oedometer test was performed on a 2 cm thick clay sample drained on both...

    Q1) An oedometer test was performed on a 2 cm thick clay sample drained on both sides taken from the mid clay layer shown below , after 10 minutes 50% consolidation is reached. a) How long time in days would the same degree of consolidation(50%) be reached in the field ?. b) How much the Final settlement would be reached in the clay layer.? c) How much the preconsolidation pressure of a specimen. ? 3m 2m Sand surcharge Y= 17...

  • A 2-m thick of compacted soil of unit weight 20 kN/m3 will be placed on the top of the ground surface. Δσ y...

    A 2-m thick of compacted soil of unit weight 20 kN/m3 will be placed on the top of the ground surface. Δσ y 14.0 kN/m3 3.0 m Sand Y 17.5 kN/m3 2.0 m 3.0m A Soft clay y= 13.5 kN/m3 6.0 m Medium clay y=15.0 kN/m3 B 4.0 m Bedrock a) Before placing the compacted soil, what are the overconsolidation ratios (OCR) for point A and B? b) When placing the compacted soil, what external load Ag would be? c)...

  • soil mechanics Q4) From the figure and soil profile as below find the following: 1) the...

    soil mechanics Q4) From the figure and soil profile as below find the following: 1) the final consolidation for clay layer under the center of bridge pier as shown below. use the approximate method to calculate the increasing stress in soil. 2) the coefficient of volume compressibility (mv) of clay layer. mass= 2*106 kg footing =10m x 8m 3m y=16.62kN/m3 2m They WT 7m 10m Sand and graver Ysat=19.8kN/m3 Clay Cc=0.33,w=30%,Gs=2.7, Ysat=19.8kN/m3 sand and gravel 4m

  • subject / soil mechanics i want the solution as soon as possible Q2:- The depth of...

    subject / soil mechanics i want the solution as soon as possible Q2:- The depth of water in a well is 3 m. Below the bottom of the well lies a layer of sand 5 meters thick overlying a clay deposit as shown in Figure (Q2). The saturated unit weight of the sand and clay are respectively 19.5 kN/m' and 20.64 kN/m'. Determine the effective stress at points A and B. 1 AN Figure (Q2) 3 m Sand 5 m...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT