Question

hello, could anyone help me with this question, please.

Q3:- The old building (A) is to be removed and replaced by a new building (B), as shown in Figure (Q3). The vertical pressure

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Building B) fold Building (A) 13 64 kN/m2 7 23.3 kN/m2 (for new NGL 2m Sand, I 2 18 kN/m² y C = 9-es om Clay, I = 20 kN/m² W

le 20.806 C volt ratio after evemoval of A) 30 as. After immedlately removal of A to +A5 AH= Cc Ho teo logia 18694 2002x8 1 +

Total settlement 162.6+ 110.3 22729 mm 4. Tome for% 50%. Tv - U? Tigo 20.196 4 TV a Cut d² Bo 1962 0.5 mHyr xt ţ t = 0.19 688

Add a comment
Know the answer?
Add Answer to:
hello, could anyone help me with this question, please. Q3:- The old building (A) is to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Soil mechanical Soil mechanical Q3:- The old building (A) is to be removed and replaced by...

    Soil mechanical Soil mechanical Q3:- The old building (A) is to be removed and replaced by a new building (B), as shown in Figure (93). The vertical pressure at the center of the clay layer from the building (A) and building (B) is equal to 13.64 kN/m' and 23.3 kN/mrespectively, Find:- 1. O.C.R after removing building (A). 2. The void ratio (e) of the clay layer: a. Immediately after removing building (A). b. After a very long time from removing...

  • Q3:- The old building (A) is to be removed and replaced by a new building (B),...

    Q3:- The old building (A) is to be removed and replaced by a new building (B), as shown in Figure (03). The vertical pressure at the center of the clay layer from the building (A) and building (B) is equal to 13.64 kN/m² and 23.3 kN/m” respectively, Find:- 1. O.C.R after removing building (A). 2. The void ratio (e) of the clay layer: a. Immediately after removing building (A). b. After a very long time from removing building (A). 3....

  • subject / soil mechanics i want the solution as soon as possible Q3:- The old building...

    subject / soil mechanics i want the solution as soon as possible Q3:- The old building (A) is to be removed and replaced by a new building (B), as shown in Figure (03). The vertical pressure at the center of the clay layer from the building (A) and building (B) is equal to 13.64 kNm and 23.3 kN/m” respectively, Find:- 1. O.C.R after removing building (A). 2. The void ratio (e) of the clay layer: a. Immediately after removing building...

  • subject: soil mechanics 03:- The old building (A) is to be removed and replaced by a...

    subject: soil mechanics 03:- The old building (A) is to be removed and replaced by a new building (B), as shown in Figure (Q3). The vertical pressure at the center of the clay layer from the building (A) and building (B) is equal to 13.64 kN/m² and 23.3 kN/mº respectively, Find:- 1. O.C.R after removing building (A). 2. The void ratio (e) of the clay layer: a. Immediately after removing building (A). b. After a very long time from removing...

  • Q1) An oedometer test was performed on a 2 cm thick clay sample drained on both...

    Q1) An oedometer test was performed on a 2 cm thick clay sample drained on both sides taken from the mid clay layer shown below , after 10 minutes 50% consolidation is reached. a) How long time in days would the same degree of consolidation(50%) be reached in the field ?. b) How much the Final settlement would be reached in the clay layer.? c) How much the preconsolidation pressure of a specimen. ? 3m 2m Sand surcharge Y= 17...

  • soil mechanics Q1) An oedometer test was performed on a 2 cm thick clay sample drained...

    soil mechanics Q1) An oedometer test was performed on a 2 cm thick clay sample drained on both sides taken from the mid clay layer shown below, after 10 minutes 50% consolidation is reached. a) How long time in days would the same degree of consolidation(50%) be reached in the field ? b) How much the final settlement would be reached in the clay layer.? c) How much the preconsolidation pressure of a specimen. ? Sm 2m Sand surcharge y...

  • soil Q1) An oedometer test was performed on a 2 cm thick clay sample drained on...

    soil Q1) An oedometer test was performed on a 2 cm thick clay sample drained on both sides taken from the mid clay layer shown below, after 10 minutes 50% consolidation is reached . a) How long time in days would the same degree of consolidation(50%) be reached in the field ?. b) How much the Final settlement would be reached in the clay layer.? c) How much the preconsolidation pressure of a specimen. ? 3m 2m Sand surcharge Y...

  • For the soil profile shown below, calculate the final settlement due to the placement of the...

    For the soil profile shown below, calculate the final settlement due to the placement of the sand fill. Estimate the excess pore pressure at a depth of 1.5 m into the third clay layer 1.5 years after the fill is placed. Assume the coefficient of consolidation is Cv = 1.8 m2/yr. Fill y = 16.0 kN/m² (3m thick) Clay 1 (3m thick) Sand (0.5m thick) Clay 2 (2m thick) Sand (0.5m thick) Clay 3 (4m thick) Sand (0.5m thick) eo...

  • 1. An 8-m thick normally consolidated clay layer is doubly drained as shown below. (This means...

    1. An 8-m thick normally consolidated clay layer is doubly drained as shown below. (This means that a very pervious layer compared to the clay exists on top of and under the clay layer) The embankment applied an average vertical stress increase of 100 kPa to the clay layer. The water table is located at the mid depth of the sand layer. Assume the sand above the water table is dry 0 Pore water pressure, u (kPa) 20 40 60...

  • X1=3000 X2=7 X3=8 X4=6 X5=3 I: The Stratum of the clay and loading shown in Figure...

    X1=3000 X2=7 X3=8 X4=6 X5=3 I: The Stratum of the clay and loading shown in Figure below: Find: 1- Consolidation settlement after 2 years of the construction (Cv=0.3 m-/year). 2- Time factor at consolidation settlement of 90%. 3- Time to reach a 45% consolidation settlement. 4- Draw he, hp, and ht distributions. Weight of tankt water + Weight of the columns =X1 KN Tank Columns Fill yu 17 kN/m (x2*X, *1) m Footing 4" Sandy= 18 kN/m', 9= 25 Clay,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT