ACTIVITY | TIME LIMIT |
1-2-3-6-8-9-10 | 18 |
1-2-3-6-8-10 | 17 |
1-2-3-6-10 | 11 |
1-4-6-10 | 15 |
1-4-6-8-10 | 21 |
1-4-6-8-9-10 | 22 |
1-5-7-9-10 | 10 |
1-7-9-10 | 8 |
From the time limit obtained, it is clear that the shortest event for the network diagram will be the path 1-7-9-10 and the longest path will be 1-4-6-8-9-10 for which their time limit 8 and 22 respectively. Thus inorder to clarify the shortest event as the earliest event :
1
7
9
10
(0,_) (2,1) (5,7) (8,9). These are the nodes given for start point and finish point for each activity where 8 as the total duration
1
4
6
8
9
10
(0,_) (6,1) (12,4) (16,6) (19,8) (22,9). These are the nodes given for the start point and finish point for each activity where 22 as the total duration
Since 1 -7 -9 - 10 is the earliest event, with a total duration of 8
1 - 4 - 6 - 8 - 9 - 10 is the latest event with a total duration of 22
So the duration for the project will be 8.
A network for a project is shown below. Activity times, in days, are indicated by the...
.8-6. A project consists of 12 activities, represented by the project network below, where number by each arc represents the duration (in days) of the associated activity 4 12 4 12 10 a) Find the earliest time, latest time, and slack for each event as well as the slack for each activity. Also identify the critical path. (b) The project has been scheduled to be completed in the minimum possible time.If all previous activities have begun as early as possible...
Given is a CPM project network diagram as shown below.
Activity
Start
A
B
C
D
E
F
G
H
End
day
0
5
6
9
6
9
8
5
4
0
a) The Project Completion time = days.
b) The Earliest Start time, ES, of Activity G = days.
c) The Latest Finish time, LF, of Acitivity C = days..
d) The critical activities are = (ex. Fill in answer as: ABCD)
End Start
a.) Create project network for activites A thru G
b.) Then compute on the network above, the correct Activity on
Arrow format (AOA), the earliest start, earliest finish, latest
start, and latest finish times for project.
a n b b Activity C, E E A Activity А 6 B 2 с 8 D 5 E 6 8 8 12 6 3 9 E Immediate Predecessor(s) G 3 3 5 Н 2 2 2 I 5 5 5 J 4 7...
QUESTION 5 Given is a CPM project network diagram as shown below. A F Start H End B D G B Activity days Start 0 A 2 H D 3 E 4 F 2 G 3 6 8 End 0 2 a) The Project Completion time days. b) The Earliest Start time, ES, of Activity G - days. c) The Latest Finish time, LF, of Acitivity C- days. d) The critical activities are (ex. Fill in answer as: ABCD)
Basic Project Management Lesson 6. Exercises 1. The AOA diagram of a project is shown below. The duration of each activity in days is shown by its side. a. Calculate the earliest and latest schedules of each event. b. Show the critical path by thickening the critical arrows. c. Fill in the Slack Table. -- a 15 Start Finish 11 13 Slack Table: Task 1-2 1-3 2-3 2-4 Slack TTT 2-5 3-5 | 3-7 | 4-6 5-6 5-7 5-8 6-8...
Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates (months) Activity Activity Predecessor а т 4 12 A B 6 10 15 С 2 10 14 1 D A 4 13 E A 3 F В 3 6 18 G 2 8 12 Н С.Е.F С.Е.F 15 22 I 5 12 21 J D 20 25 K G.I 5 12 L Н.К 3 20 Expected activity times b. Variance times а. c. Earliest...
Problem 5: For the given activity network, if there are 35 days required to complete the project, find the following Complete the network by filling in ES, LS, EF and LF Earliest start for activities D, E, F, H, G, L, M ill. Earliest finish for activities D, E, F, H,G,L,M Latest start for activities D, E, F, H, G, LM V. Latest finish activities D, E, F.H.GLM vi. Slack/Float time for each activities D, E, F, H, G, LM...
Given is a CPM project network diagram as shown below. A וד H End Start التا B D G A F H Activity day Start 0 B 8 с 3 D 5 E 6 وانما | End 0 8 4 a) The Project Completion time = days b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days d) The critical activities are = (ex. Fill in answer as:...
A project network is shown below. All activity times are given in days. Suppose C could be shortened by three days (i.e., C takes 3 days to complete instead of 6) and F could be shortened by one day (i.e., F takes 7 days instead of 8). With these changes in activity times of C and F how long will it take to complete the project? BS) (C(61) AC G(3) (D( (4) F(8) none of the choices are correct 23...
QUESTION 1 The following table provides information about a particular project:ActivityDuration (Days)PrecedingActivityA5_B6_C4AD3AE1AF4EG14D,EH12B,CI2G,H (a) Represent the project by means of a simple network diagram. (b) Prepare in tabular form, an activity schedule showing the following details: Earliest-start, earliest-finish, latest-start, latest-finish and slack times. (c) Identify the critical path. ...