Question

A project network is shown below. All activity times are given in days. Suppose C could be shortened by three days (i.e., C t
0 0
Add a comment Improve this question Transcribed image text
Answer #1

6) Using given data, activity on node (Aon) diagram becomes : 3 (B) 6 7 (A 3 7 (E Path Duration ABCD 7+5+3+ 6 = 21 AEGCD 7+4+

Add a comment
Know the answer?
Add Answer to:
A project network is shown below. All activity times are given in days. Suppose C could...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A network for a project is shown below. Activity times, in days, are indicated by the...

    A network for a project is shown below. Activity times, in days, are indicated by the figure that appears under the activity. 3 6 6 5 2 3 6 8 10 2 3 5 2 2 3 2 (i) Analyze the network and determine the earliest and latest EVENT times and the duration of the project.

  • 15. Given the following project (all times are in days): Pre- Normal Normal Crash Crash Activity...

    15. Given the following project (all times are in days): Pre- Normal Normal Crash Crash Activity decessor Time Cost Time Cost $50 200 160 a, c a, c 290 100 180 (a) Draw the network and find the critical path, time, and (b) Calculate the crash cost-per-day (all activities may be (c) Find the optimal way of getting an 18-day delivery (d) Find the optimal way of getting a 16-day delivery (e) Calculate the shortest delivery time for the project....

  • Given is a CPM project network diagram as shown below. Activity Start A B C D...

    Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End day 0 5 6 9 6 9 8 5 4 0 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days.. d) The critical activities are = (ex. Fill in answer as: ABCD) End Start

  • Engineering Management rash C Duration (day) Cost (SR) Cost Slope (Skany) 300 500 Normal Activity by...

    Engineering Management rash C Duration (day) Cost (SR) Cost Slope (Skany) 300 500 Normal Activity by Duration .com (day) on A - 7 3600 BA55500 CB96350 DB 19 4700 Е в 10 | 2050 FC 8 1200 G F 5 7200 Γ Η Τ Ε Ι 9450 I D, G, H 4500 Cost (SK) 3900 6500 7200 4900 2200 1450 7200 10000 4600 ABD OTO D ESTU It is required to crash the project duration from its original duration to...

  • Given the following activity list and times in days: (15 points) Activity           Optimistic       Most Likely     Pessimistic...

    Given the following activity list and times in days: (15 points) Activity           Optimistic       Most Likely     Pessimistic                         Time                Time                Time A                     7                      10                    12 B                     6                      8                      14 C                     5                      9                      12 D                     12                    14                    21 E                      10                    12                    15 F                      4                      5                      8 G                     1                      3                      8 H                     12                    15                    17 NOTE 1: ASSUME THE CRITTCAL PATH IS “B-E-H”. Calculate the schedule duration of the critical path in days. What is the probability of the project being completed...

  • QUESTION 5 Given is a CPM project network diagram as shown below. А C F Start...

    QUESTION 5 Given is a CPM project network diagram as shown below. А C F Start E Н. End B D G A B D E F G H Activity day Start 0 с 8 End 0 6 3 7 4 9 4 6 a) The Project Cor etion time = days b) The Earliest Start time, ES, of Activity G- days. c) The Latest Finish time, LF, of Acitivity - days. d) The critical activities are = (ex. Fill...

  • Problem 1 While performing scheduling work on a project you have determined that one activity has...

    Problem 1 While performing scheduling work on a project you have determined that one activity has a great deal of variability. A sample of times (30) the task has been completed is provided the table below. Assume that the task is considered to be "late" if the task duration is two days greater than the mean value (rounded to the nearest whole day), and "early" if the task duration is two days less than the mean value (rounded to the...

  • QUESTION 5 Given is a CPM project network diagram as shown below. A с F Start...

    QUESTION 5 Given is a CPM project network diagram as shown below. A с F Start E H End B D Start A B E H End Activity day с 7 D 3 F 5 G 6 0 2 4 3 0 a) The Project Completion time = days. b) The Earliest Start time, Es, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C - days. d) The critical activities are (ex. Fill in answer...

  • QUESTION 5 Given is a CPM project network diagram as shown below. А F Start E...

    QUESTION 5 Given is a CPM project network diagram as shown below. А F Start E H End B D G Start A B C D E F G H End Activity day 0 6 زر 8 7 4 9 4 6 0 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G= days. c) The Latest Finish time, LF, of Acitivity C = days. d) The critical activities are = (ex. Fill in...

  • Given is a CPM project network diagram as shown below. A וד H End Start التا...

    Given is a CPM project network diagram as shown below. A וד H End Start التا B D G A F H Activity day Start 0 B 8 с 3 D 5 E 6 وانما | End 0 8 4 a) The Project Completion time = days b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days d) The critical activities are = (ex. Fill in answer as:...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT