Question

The R&D department is planning to bid on a large project for the development of a new communication system for commercial pla
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Draw the table listing ES, LS, EF, LF and Slack time of each Job Earliest Start (ES) is calculated by forward pass method as

b.

List alternative paths and their respective time.

Path Time
A-B-E-I 17
A-C-F-G-I 24
A-D-F-G-I 24
A-D-G-I 21
A-D-H-I 18

Time of each path is equal to the sum of activity times.

The longest path is the critical path. We see that two paths, viz. A-C-F-G-I and A-D-F-G-I have the longest time. So, these are critical paths

ANSWER:   A-C-F-G-I and A-D-F-G-I

-----------------------------------------------------------------------

c.

ANSWER:  G, C, D

Activities on critical paths need to be shortened. since each of the activities can be shortened by one week. Activity G is o both the critical paths. Shortening it by one week, will shorten the two critical paths by 1 week. so, project duration will be 23 weeks. Duration of all other paths is lesser than 23. Shortening activity C and D by one week each, will again shorten each of the critical paths by one week each. And the project completion time will be 22 weeks.

-----------------------------------------------------------------------

d-1.

New critical paths are same as in (b)

ANSWER:   A-C-F-G-I and A-D-F-G-I

This is already explained in part (c)

-----------------------------------------------------------------------

d-2.

Completion time = 22 weeks

This is already explained in part (c)

Add a comment
Know the answer?
Add Answer to:
The R&D department is planning to bid on a large project for the development of a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The R&D department is planning to bid on a large project for the development of a...

    The R&D department is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activities, times, and sequences required: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 6 B A 3 C A 4 D A 4 E B 3 F C D 3 G D F 2 H D 3 I E G H 5 b. What is the critical path? (You may select more than one...

  • Problem 5-9 (Algo) The R&D department is planning to bid on a large project for the...

    Problem 5-9 (Algo) The R&D department is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activities, times, and sequences required ACTIVITY IPEDIATE PREDECESSORTIE (WEEKS) C. E.G .H b. What is the critical path? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question...

  • A construction project is broken down into the following 10 activities:

    Problem 5-13 A construction project is broken down into the following 10 activities:b-1. What is the critical path? 1-4-7-9-10 1-3-6-9-10 1-2-5-8-10 1-3-5-8-10 b-2. How many weeks will the project take to complete? Number of weeks _______ c. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of $10,000 per week, which activities would you shorten to cut the project by four weeks? (You may select more than one answer. Single-click the...

  • Problem 5-13 A construction project is broken down into the following 10 activities: ACTIVITY IMMEDIATE PREDECESSOR...

    Problem 5-13 A construction project is broken down into the following 10 activities: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) 1 — 5 2 1 3 3 1 4 4 1 2 5 2,3 6 6 3 4 7 4 2 8 5 4 9 6,7 7 10 8,9 5 b-1. What is the critical path? 1-3-5-8-10 1-3-6-9-10 1-4-7-9-10 1-2-5-8-10 b-2. How many weeks will the project take to complete? Number of weeks             c. If activities 1 and 10 cannot be shortened,...

  • (d) When sales increase by 7%, which of the following should also increase by 7% in...

    (d) When sales increase by 7%, which of the following should also increase by 7% in a merchandising company? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.) Variable cost Fixed cost Gross margin Contribution...

  • The Suboptimal Glass Company uses a process of capital rationing in its decision making. The firm's...

    The Suboptimal Glass Company uses a process of capital rationing in its decision making. The firm's cost of capital is 10 percent. It will only invest $74,000 this year. It has determined the internal rate of return for each of the following projects. Project ject $11,000 31,000 26,000 11,000 11,000 21,000 16,000 Internal Rate of Return 23% 19 13 16 20 18 a. Pick out the projects that the firm should accept. (You may select more than one answer. Single...

  • Please explain your choices? I wanted to double check to see if I understood the questions...

    Please explain your choices? I wanted to double check to see if I understood the questions correctly (d) When sales increase by 21%, which of the following should also increase by 21% in a merchandising company? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left...

  • A service company has the following costs

    A service company has the following costs(You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.)? direct materials? overhead costs? product costs? expensed in the period incurred

  • Identify which of the following accounts would be included in a post-closing trial balance. (You may...

    Identify which of the following accounts would be included in a post-closing trial balance. (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.) Office Equipment Haircutting Revenue Note Receivable Prepaid Insurance Rental Revenue Cash

  • Knowledge Check 01 Identify cash equivalents from the listed items. (You may select more than one...

    Knowledge Check 01 Identify cash equivalents from the listed items. (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.) Money market funds Supplies Three-month Treasury bills Accounts receivable Prepaid rent

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT