A project has three activities A, B, and C that must be carried out sequentially, that...
A project has three activities A, B, and C that must be carried out sequentially; that is, A -> -> C. The probability distributions of the times required to complete each of the activities A, B, and C are uniformly distributed in intervals (1,6], [2,3] and (3,6) respectively. Find the total project completion time and run 1000 simulation trials in Excel. The project completion time" is a(n)... Select one: O a. Input of the simulation b. Decision variable in the...
Answer next 3 questions using following information: A project has three activities A, B, and C that must be carried out sequentially. The probability distributions of the times required to complete each of the activities A, B, and C have uniform probability distribution in the following ranges:. Activity Completion Time A 1 to 5 B 2 to 3 C 3 to 6 Find the total project completion time and run 500 simulation trials in Excel. 1/ The “project completion time”...
project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Time (weeks) Activity Probability A 0.29 0.30 10 0.28 11 0.13 0.24 4 0.53 6 0.23 12 0.12 0.20 14 0.35 16 18 0.15 20 0.18 6 0.69 0.31 a. Provide the base-case, worst-case, and best-case calculations for the time to complete the project. Worst case Best case Activity...
A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Time (weeks) 5 Activity A Probability 0.30 6 0.35 7 0.26 8 0.09 B 6 0.21 8 0.53 10 0.26 с 5 0.09 7 0.27 9 0.40 11 0.19 13 0.05 D 6 0.66 8 0.34 a. Provide the base-case, worst-case, and best-case calculations for the time to...
(All answers were generated using 1,000 trials and native Excel functionality.) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 5 0.25 6 0.35 7 0.25 8 0.15 B 3 0.20 5 0.55 7 0.25 C 10 0.10 12 0.25 14 0.40 16 0.20 18 0.05 D 8 0.60 10 0.40 (a)...
Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 6 0.29 7 0.38 8 0.27 9 0.06 B 3 0.21 5 0.53 7 0.26 C 6 0.06 8 0.26 10 0.37 12 0.22 14 0.09 D 11 0.63 13 0.37 Provide the base-case, worst-case, and best-case calculations for the...
Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 4 0.28 5 0.37 6 0.29 7 0.06 B 6 0.24 8 0.57 10 0.19 C 10 0.13 12 0.25 14 0.41 16 0.16 18 0.05 D 11 0.72 13 0.28 Provide the base-case, worst-case, and best-case calculations for the...
Question 1 10 points Save Answer A project consists of three activities: A, B, and C. Activities A and B can begin at time 0 (start of the project), but activity C can only start after B is completed. The project ends when all activities are completed. The durations of the activities were simulated 10 times and the following values were obtained: Run 1 A Duration B Duration C Duration 51 48 17 60 48 19 2 3 30 39...
5. A project has critical path activities A, B, and C. A is the predecessor of B. B is the predecessor of C. The duration estimate for activity A, B and C is shown in the following table. Fill the table with mean duration, standard deviation, and variance for activities and the whole project (critical path). Determine what is the probability of completing this project within 80 days? (10 points) Activity Optimistic Pessimistic Most likely Mean Standard Variance deviation duration...
eCourses Fall2018_MGMT5123201-1910-10776 Question 3 A project with 7 activities is shown below Not yet Marked out of 1.00 F Flag FIN The duration of activities A B, C, and D are 20, 20, 15, and 27 days, respectively On the other hand, the duration of activities E, F, and G are 18, 21, and 32 days Assuming the project starts at the end of day o, the project completion time will be days Previous page