The project consists of three sequential activities. Therefore, A is carried out first. This is followed by B, which is then followed by C. Eac of the activities follows a uniform distribution in their respective intervals. A lies in the interval [1, 6]. B lies in the interval [2, 3], and C lies in the interval [3, 6]. We are to determine the total project completion time as would be predicted by running Excel 1000 trial simulations.
1. The simulation will involve creating 1000 trials each for activities A, B, and C. The project completion trail will be the sum of the times required to complete each of the three activities. Therefore, the project completion time will be the output of the simulation. Therefore, the answer is d.
2. Each of the activities are uniformly distributed. Hence, they have an equal probability to occur throughout their interval. Excel has a function called RAND() which can be used for this purpose. RAND() also draws values from a uniform distribution but of unit size in the range 0 to 1. In order to increase the width of the scale, we can simply multiply the output by the desired width. So say for instance, I want the size of the distribution to be of 100 units, I can simply use 100 * RAND() and then the output will lie in the uniform distribution of range [0, 100]. In order to change the lower limit of the range from 0 to some other value x, we can simply add x to the RAND() function. Therefore, in order to get a uniform distribution in the range [10, 110], the command would be 10 + 100 * RAND().
Now in the question, each of the activities follow a uniform distribution with the ranges mentioned. Therefore, a random number can be drawn from the desired uniform distribution by summing the lower limit of the the distribution with the product of the size of the distribution (the difference between the maximum and the minimum values) and the RAND() function.
Therefore, for acitivity A we have 1 + 5 * RAND(), for activity B we have 2 + 1 * RAND(), and for activity C we have 3 + 3 * RAND().
Hence, the answer is b.
3. The output of the simulation will be the sum of the times taken for each of the three activities. Therefore, it can be obtained using the SUM() function of excel. In order to perform 1000 simulations, the formula from the first row can simply be dragged down for 1000 cells. In order to compute the standard deviation of the output time, we can use the excel function STDEV() and provide it with the range of the output. In my case it came out to be 1.6879, which is very close to 1.70 given in the options. Repeating the simulation should give you similar results. Therefore, the answer is d.
4. RAND() is a pseudo-random number generator as mentioned above, and it gives values between 0 and 1. If 1000 cells have this function, then 1000 values will be drawn from this interval. Therefore, the probability of getting a value less than or equal to 0.2 will be:
For 1000 cells, the frequency will be 1000 * 0.2 = 200.
Therefore, the number of cells that will have value less than or equal to 0.2 will be close to 200.
Hence, the correct answer is b.
asdfa
A project has three activities A, B, and C that must be carried out sequentially; that...
A project has three activities A, B, and C that must be carried out sequentially, that is, A -> -> C. The probability distributions of the times required to complete each of the activities A, B, and C are uniformly distributed in intervals (1,6), (2,3) and (3,6) respectively. Find the total project completion time and run 1000 simulation trials in Excel. The "project completion time" is a(n)... Select one: O a. Input of the simulation O b. Decision variable in...
Answer next 3 questions using following information: A project has three activities A, B, and C that must be carried out sequentially. The probability distributions of the times required to complete each of the activities A, B, and C have uniform probability distribution in the following ranges:. Activity Completion Time A 1 to 5 B 2 to 3 C 3 to 6 Find the total project completion time and run 500 simulation trials in Excel. 1/ The “project completion time”...
project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Time (weeks) Activity Probability A 0.29 0.30 10 0.28 11 0.13 0.24 4 0.53 6 0.23 12 0.12 0.20 14 0.35 16 18 0.15 20 0.18 6 0.69 0.31 a. Provide the base-case, worst-case, and best-case calculations for the time to complete the project. Worst case Best case Activity...
A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Time (weeks) 5 Activity A Probability 0.30 6 0.35 7 0.26 8 0.09 B 6 0.21 8 0.53 10 0.26 с 5 0.09 7 0.27 9 0.40 11 0.19 13 0.05 D 6 0.66 8 0.34 a. Provide the base-case, worst-case, and best-case calculations for the time to...
Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 6 0.29 7 0.38 8 0.27 9 0.06 B 3 0.21 5 0.53 7 0.26 C 6 0.06 8 0.26 10 0.37 12 0.22 14 0.09 D 11 0.63 13 0.37 Provide the base-case, worst-case, and best-case calculations for the...
Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 4 0.28 5 0.37 6 0.29 7 0.06 B 6 0.24 8 0.57 10 0.19 C 10 0.13 12 0.25 14 0.41 16 0.16 18 0.05 D 11 0.72 13 0.28 Provide the base-case, worst-case, and best-case calculations for the...
(All answers were generated using 1,000 trials and native Excel functionality.) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 5 0.25 6 0.35 7 0.25 8 0.15 B 3 0.20 5 0.55 7 0.25 C 10 0.10 12 0.25 14 0.40 16 0.20 18 0.05 D 8 0.60 10 0.40 (a)...
Question 1 10 points Save Answer A project consists of three activities: A, B, and C. Activities A and B can begin at time 0 (start of the project), but activity C can only start after B is completed. The project ends when all activities are completed. The durations of the activities were simulated 10 times and the following values were obtained: Run 1 A Duration B Duration C Duration 51 48 17 60 48 19 2 3 30 39...
eCourses Fall2018_MGMT5123201-1910-10776 Question 3 A project with 7 activities is shown below Not yet Marked out of 1.00 F Flag FIN The duration of activities A B, C, and D are 20, 20, 15, and 27 days, respectively On the other hand, the duration of activities E, F, and G are 18, 21, and 32 days Assuming the project starts at the end of day o, the project completion time will be days Previous page
The following activities of a hospital expansion project has been identified in the following table. First, all activities of the project are listed. Next, the immediate predecessor(s) of each activity is identified (activity relationships). Please plot the activity network diagram and answer the following questions. Hospital Expansion Project Activity Description Immediate predecessor(s) Activity Time (Weeks) A Select administrative and medical staff - 12 B Select site and do site survey - 9 C Select equipment A 10 D Prepare final...