You would like to construct an aggregate production plan for four quarters of 2021.

Product name: TRX3010

Cost of regular production = 50 $/u

Cost of overtime production = 65 $/u Inventory holding cost = 5 $/u/qtr

Cost of increasing production = 40 $/u Cost of decreasing production = 45 $/u Previous quarter's regular production = Beginning inventory level = 250 u

4200 u

The forecasted demand for the next four quarters is 3700, 4000, 2600, and 3900 units.

You want to set the quarterly regular production constant at 3200 units.

When needed, you will use overtime production.

You will keep inventory as low as possible but it must be at least 260 units per quarter. Stockouts are not allowed. In other words, quarterly demand must always be satisfied. You must perform all necessary calculations and summarize results in tabular form.

You must show clearly the regular production, overtime production, inventory, changes in regular production, and costs.

A brief explanation is needed. Explain if it is sufficient.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Aggregate plan based on level production with overtime strategy is following:

F H 1 Decrease (units) 4 5 A B с D E Level production with overtime Regular Overtime Ending Increase Quarter Demand 2 Product

EXCEL FORMULA:

А. B 1 3 с D E F G Level production with overtime Regular Quarter Demand 2 Production Overtime Production Ending Inventory In

Brief explanation:

Regular production in the next four quarters is constant at 3200 units

Ending inventory of quarter 1,2 and 4 is 260 units; of quarter 3 is 860 units

Total increase and decrease in the next four quarters is 0 and 1000 respectively.

Total regular production cost is $ 640,000

Total overtime production cost is $ 91,650

Total inventory carrying cost is $ 8,200

Total cost of increasing production is $ 0

Total cost of decreasing production is $ 45,000

Total cost of the plan is $ 784,850

The plan is sufficient to meet the demand.

Add a comment
Know the answer?
Add Answer to:
You would like to construct an aggregate production plan for four quarters of 2021. Product name:...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Answer Part B using excel and show equations that were used. explain if the problem is...

    Answer Part B using excel and show equations that were used. explain if the problem is suffiecent or not. You would like to construct an aggregate production plan for four quarters of 2021. Product name: TRX3010 Cost of regular production = 50 $/u Cost of overtime production = 65 $/u Inventory holding cost = 5 $/u/qtr Cost of increasing production = 40 $/u Cost of decreasing production = 45 $/u Previous quarter's regular production = 4200 u Beginning inventory level...

  • You would like to construct an aggregate production plan for product X341 for the next four...

    You would like to construct an aggregate production plan for product X341 for the next four quarters. Cost of regular production = 60 $/u Cost of overtime production = 90 $/u Inventory holding cost = 10 $/u/qtr Cost of increasing production = 70 $/u Cost of decreasing production = 120 $/u Subcontracting cost = 115 $/u Stockout cost = 130 $/u Previous quarter's regular output = 225 u Beginning inventory level = 25 u The forecasted demand for the next...

  • You would like to construct an aggregate production plan for product X341 for the next four...

    You would like to construct an aggregate production plan for product X341 for the next four quarters. Cost of regular production 100 $/u Cost of overtime production 150 $u Inventory holding cost 15 S/u/qtr Cost of increasing production 120 $/u Cost of decreasing production 160 $/u Subcontracting cost 170 $/u Stockout cost 180 $/u Previous quarter's regular output 1500 u Beginning inventory level-30 u The forecasted demand for the next four quarters are: 1000, 300, 600, and 900 units. Suppose...

  • A manufacturer wants to develop a production plan for the month of February through June. The...

    A manufacturer wants to develop a production plan for the month of February through June. The forecasted demand for those months are 2500, 3700, 3900, 5000, and 2000 units, respectively. The regular-time production capacity in February and March are 3000 units and 2500 units, respectively. The overtime production capacity in February and March are 600 units and 500 units, respectively. The regular production cost is $30 per unit and the overtime production cost is $45 per unit. The cost of...

  • Plan production for a four-month period: February through May. For February and March, you should produce...

    Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...

  • Problem 8-8 Plan production for a four-month period: February through May. For February and March, you...

    Problem 8-8 Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply,...

  • Plan production for a four-month period: February through May. For February and March, you should produce...

    Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...

  • Develop a production plan and calculate the annual cost for a firm whose demand forecast is...

    Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 11,000; winter, 7,700; spring, 6,700; summer, 13,000. Inventory at the beginning of fall is 550 units. At the beginning of fall you currently have 30 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular workforce on...

  • Company AAA produces only one product which other manufacturers purchase as a component for their final...

    Company AAA produces only one product which other manufacturers purchase as a component for their final products. The operations manager wants to plan the production and inventory quantities of the product for the first six months of the next year. The monthly demand is forecasted as follows. January February March April May June 1200 1400 1800 2400 2600 2200 The company has three production options: regular production, overtime production, and subcontracting. Production cost per unit during regular time is $80...

  • Problem 8-7 Develop a production plan and calculate the annual cost for a firm whose demand...

    Problem 8-7 Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 10,700; winter, 8,300; spring, 6,900; summer, 12,700. Inventory at the beginning of fall is 535 units. At the beginning of fall you currently have 35 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT