Part 1 Job A-200 Total Manufacturing Cost | ||
A | Direct Material | $ 120.00 |
B | Direct Labour | $ 110.00 |
C | Direct Labour Hour ($110/11) | 10.00 |
D | Predetermined Overhead Rate | $ 17.00 |
E | Fixed Overhead Cost (C*D) | $ 170.00 |
F | Total Manufacturing Cost Assigned (A+B+E) | $ 400.00 |
Part 2 Job A-200 Average cost Per Unit | ||
A | Total Manufacturing Cost | $ 400.00 |
B | No of Units | 40 |
B | Average Cost Assigned to each unit (A/B) | $ 10.00 |
Weaver Company's predetermined overhead rate is $17.00 per direct labour-hour, and its direct labour wage rate...
Weaver Company’s predetermined overhead rate is $20.00 per direct labour-hour, and its direct labour wage rate is $15.00 per hour. The following information pertains to Job A-200: Direct materials $240 Direct labour $180 Required: 1. What is the total manufacturing cost assigned to Job A-200? 2. If Job A-200 consists of 55 units, what is the average cost assigned to each unit included in the job?
Weaver Company’s predetermined overhead rate is $15.00 per direct labour-hour, and its direct labour wage rate is $10.00 per hour. The following information pertains to Job A-200: Direct materials $315 Direct labour $210 Required: 1. What is the total manufacturing cost assigned to Job A-200? 2. If Job A-200 consists of 40 units, what is the average cost assigned to each unit included in the job? Score answer Visit question map Question 1 of 2 Total
Weaver Company’s predetermined overhead rate is $15.00 per direct labour-hour, and its direct labour wage rate is $10.00 per hour. The following information pertains to Job A-200: Direct materials $315 Direct labour $210 Required: 1. What is the total manufacturing cost assigned to Job A-200? 2. If Job A-200 consists of 40 units, what is the average cost assigned to each unit included in the job? Score answer Visit question map Question 1 of 2 Total
Exercise 5-2 Computing Job Costs [LO2] Weaver Company's predetermined overhead rate is $15.00 per direct labour-hour, and its direct labour wage rate is $10.00 per hour. The following information pertains to Job A-200: $405 Direct materials Direct labour $270 Required: 1. What is the total manufacturing cost assigned to Job A-2002 Total manufacturing cost 2. If Job A-200 consists of 40 units, what is the average cost assigned to each unit included in the job? Average cost per unit
Weaver Company's predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate is $13.00 per hour. The following information pertains to Job A-200: Direct materials Direct labor $230 $195 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost 2. If Job A-200 consists of 40 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.) Average cost per unit
Weaver Company's predetermined overhead rate is $23.00 per direct labor-hour and its direct labor wage rate is $12.00 per hour. The following information pertains to Job A-200: Direct materials Direct labor $240 $60 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost 2. If Job A-200 consists of 80 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.) Average cost per unit
Weaver Company's predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate is $13.00 per hour. The following information pertains to Job A- 200: Direct materials Direct labor $250 $130 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost $ 385 2. If Job A-200 consists of 70 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.) Average...
Weaver Company's predetermined overhead rate is $24.00 per direct labor-hour and its direct labor wage rate is $16.00 per hour. The following information pertains to Job A-200: Direct materials Direct labor $230 $160 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost 2. If Job A-200 consists of 60 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.) Average cost per unit
Weaver Company's predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate is $12.00 per hour. The following information pertains to Job A-200: Direct materials Direct labor $250 $240 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost 2. If Job A-200 consists of 40 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.) Average cost per unit...
Weaver Company's predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage rate is $15.00 per hour The following information pertains to Job A-200 Direct materals Direct labor $290 $300 Required 1. What is the total manufacturing cost assigned to Job A-200 2 If Job A-200 consists of 00 unts, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places) per unt