Weaver Company’s predetermined overhead rate is $15.00 per direct labour-hour, and its direct labour wage rate is $10.00 per hour. The following information pertains to Job A-200:
Direct materials | $315 |
Direct labour | $210 |
Required:
1. What is the total manufacturing cost assigned to Job A-200?
2. If Job A-200 consists of 40 units, what is the average cost assigned to each unit included in the job?
Score answer Visit question map
Question 1 of 2 Total
1.
Direct labor hours used in Job A-200= Direct labor cost/ Direct labor rate
= 210/10
= 21
Overhead applied = Direct labor used x Predetermined overhead rate
= 21 x 15
= $315
Job Cost Sheet ( Job A-200)
Direct material | 315 |
Direct labor | 210 |
Applied overhead | 315 |
Total Cost | $840 |
2.
Cost per unit = Total cost/ Number of units
= 840/40
= $21
Kindly comment if you need further assistance. Thanks‼!
Weaver Company’s predetermined overhead rate is $15.00 per direct labour-hour, and its direct labour wage rate...
Weaver Company’s predetermined overhead rate is $15.00 per direct labour-hour, and its direct labour wage rate is $10.00 per hour. The following information pertains to Job A-200: Direct materials $315 Direct labour $210 Required: 1. What is the total manufacturing cost assigned to Job A-200? 2. If Job A-200 consists of 40 units, what is the average cost assigned to each unit included in the job? Score answer Visit question map Question 1 of 2 Total
Weaver Company’s predetermined overhead rate is $20.00 per direct labour-hour, and its direct labour wage rate is $15.00 per hour. The following information pertains to Job A-200: Direct materials $240 Direct labour $180 Required: 1. What is the total manufacturing cost assigned to Job A-200? 2. If Job A-200 consists of 55 units, what is the average cost assigned to each unit included in the job?
Weaver Company's predetermined overhead rate is $17.00 per direct labour-hour, and its direct labour wage rate is $11.00 per hour. The following information pertains to Job A-200: Direct materials Direct labour $120 $110 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost 2. If Job A-200 consists of 40 units, what is the average cost assigned to each unit included in the job? Average cost per unit
Exercise 5-2 Computing Job Costs [LO2] Weaver Company's predetermined overhead rate is $15.00 per direct labour-hour, and its direct labour wage rate is $10.00 per hour. The following information pertains to Job A-200: $405 Direct materials Direct labour $270 Required: 1. What is the total manufacturing cost assigned to Job A-2002 Total manufacturing cost 2. If Job A-200 consists of 40 units, what is the average cost assigned to each unit included in the job? Average cost per unit
Weaver Company's predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage rate is $15.00 per hour The following information pertains to Job A-200 Direct materals Direct labor $290 $300 Required 1. What is the total manufacturing cost assigned to Job A-200 2 If Job A-200 consists of 00 unts, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places) per unt
Weaver Company's predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate is $13.00 per hour. The following information pertains to Job A-200: Direct materials Direct labor $230 $195 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost 2. If Job A-200 consists of 40 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.) Average cost per unit
Weaver Company's predetermined overhead rate is $23.00 per direct labor-hour and its direct labor wage rate is $12.00 per hour. The following information pertains to Job A-200: Direct materials Direct labor $240 $60 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost 2. If Job A-200 consists of 80 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.) Average cost per unit
Weaver Company's predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate is $13.00 per hour. The following information pertains to Job A- 200: Direct materials Direct labor $250 $130 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost $ 385 2. If Job A-200 consists of 70 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.) Average...
Weaver Company's predetermined overhead rate is $24.00 per direct labor-hour and its direct labor wage rate is $16.00 per hour. The following information pertains to Job A-200: Direct materials Direct labor $230 $160 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost 2. If Job A-200 consists of 60 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.) Average cost per unit
Weaver Company's predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate is $12.00 per hour. The following information pertains to Job A-200: Direct materials Direct labor $250 $240 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost 2. If Job A-200 consists of 40 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.) Average cost per unit...