Question

Weaver Company’s predetermined overhead rate is $15.00 per direct labour-hour, and its direct labour wage rate...

Weaver Company’s predetermined overhead rate is $15.00 per direct labour-hour, and its direct labour wage rate is $10.00 per hour. The following information pertains to Job A-200:

    
  Direct materials $315
  Direct labour $210

Required:

1. What is the total manufacturing cost assigned to Job A-200?

2. If Job A-200 consists of 40 units, what is the average cost assigned to each unit included in the job?

Score answer Visit question map

Question 1 of 2 Total

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

1.

Direct labor hours used in Job A-200= Direct labor cost/ Direct labor rate

= 210/10

= 21

Overhead applied = Direct labor used x Predetermined overhead rate

= 21 x 15

= $315

Job Cost Sheet ( Job A-200)

Direct material 315
Direct labor 210
Applied overhead 315
Total Cost $840

2.

Cost per unit = Total cost/ Number of units

= 840/40

= $21

Kindly comment if you need further assistance. Thanks‼!

Add a comment
Know the answer?
Add Answer to:
Weaver Company’s predetermined overhead rate is $15.00 per direct labour-hour, and its direct labour wage rate...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Weaver Company’s predetermined overhead rate is $15.00 per direct labour-hour, and its direct labour wage rate is $10.00...

    Weaver Company’s predetermined overhead rate is $15.00 per direct labour-hour, and its direct labour wage rate is $10.00 per hour. The following information pertains to Job A-200:        Direct materials $315   Direct labour $210 Required: 1. What is the total manufacturing cost assigned to Job A-200? 2. If Job A-200 consists of 40 units, what is the average cost assigned to each unit included in the job? Score answer Visit question map Question 1 of 2 Total

  • Weaver Company’s predetermined overhead rate is $20.00 per direct labour-hour, and its direct labour wage rate...

    Weaver Company’s predetermined overhead rate is $20.00 per direct labour-hour, and its direct labour wage rate is $15.00 per hour. The following information pertains to Job A-200:        Direct materials $240   Direct labour $180 Required: 1. What is the total manufacturing cost assigned to Job A-200?       2. If Job A-200 consists of 55 units, what is the average cost assigned to each unit included in the job?         

  • Weaver Company's predetermined overhead rate is $17.00 per direct labour-hour, and its direct labour wage rate...

    Weaver Company's predetermined overhead rate is $17.00 per direct labour-hour, and its direct labour wage rate is $11.00 per hour. The following information pertains to Job A-200: Direct materials Direct labour $120 $110 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost 2. If Job A-200 consists of 40 units, what is the average cost assigned to each unit included in the job? Average cost per unit

  • Exercise 5-2 Computing Job Costs [LO2] Weaver Company's predetermined overhead rate is $15.00 per direct labour-hour,...

    Exercise 5-2 Computing Job Costs [LO2] Weaver Company's predetermined overhead rate is $15.00 per direct labour-hour, and its direct labour wage rate is $10.00 per hour. The following information pertains to Job A-200: $405 Direct materials Direct labour $270 Required: 1. What is the total manufacturing cost assigned to Job A-2002 Total manufacturing cost 2. If Job A-200 consists of 40 units, what is the average cost assigned to each unit included in the job? Average cost per unit

  • Weaver Company's predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage rate...

    Weaver Company's predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage rate is $15.00 per hour The following information pertains to Job A-200 Direct materals Direct labor $290 $300 Required 1. What is the total manufacturing cost assigned to Job A-200 2 If Job A-200 consists of 00 unts, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places) per unt

  • Weaver Company's predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate...

    Weaver Company's predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate is $13.00 per hour. The following information pertains to Job A-200: Direct materials Direct labor $230 $195 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost 2. If Job A-200 consists of 40 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.) Average cost per unit

  • Weaver Company's predetermined overhead rate is $23.00 per direct labor-hour and its direct labor wage rate...

    Weaver Company's predetermined overhead rate is $23.00 per direct labor-hour and its direct labor wage rate is $12.00 per hour. The following information pertains to Job A-200: Direct materials Direct labor $240 $60 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost 2. If Job A-200 consists of 80 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.) Average cost per unit

  • Weaver Company's predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate...

    Weaver Company's predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate is $13.00 per hour. The following information pertains to Job A- 200: Direct materials Direct labor $250 $130 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost $ 385 2. If Job A-200 consists of 70 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.) Average...

  • Weaver Company's predetermined overhead rate is $24.00 per direct labor-hour and its direct labor wage rate...

    Weaver Company's predetermined overhead rate is $24.00 per direct labor-hour and its direct labor wage rate is $16.00 per hour. The following information pertains to Job A-200: Direct materials Direct labor $230 $160 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost 2. If Job A-200 consists of 60 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.) Average cost per unit

  • Weaver Company's predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate...

    Weaver Company's predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate is $12.00 per hour. The following information pertains to Job A-200: Direct materials Direct labor $250 $240 Required: 1. What is the total manufacturing cost assigned to Job A-200? Total manufacturing cost 2. If Job A-200 consists of 40 units, what is the average cost assigned to each unit included in the job? (Round your answer to 2 decimal places.) Average cost per unit...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT