Solution:
Answer 12. The answer is $35,000 overapplied.
Applied overhead = 150% of direct labor cost
= 150% of $220,000 = $330,000
Actual overhead = $295,000
Applied overhead is higher than actual overhead so it is over applied overhead
Over applied overhead = $330,000 - $295,000 = $35,000
Answer 13. The answer is $1,008,000.
Calculation of total manufacturing costs for Job No. 501
Direct Material | $240,000 |
Direct Labor costs | $320,000 |
Manufacturing overhead (140% of direct labor costs) | 140% of $320,000 = $448,000 |
Total Manufacturing costs | $1,008,000 |
Please rate positive and comment in case of any doubt. I would be happy to help you further.
Facebook Facebook George Wilms During 2019. Mayco expected Job No. 59 to cost $300,000 of overhead,...
During 2017, XX company applied $300,000 of overhead cost to job #59. the company applied overhead based on direct labor cost. Actual production required an overhead cost $295,000. How much is the amount of over - or underapplied overhead? 1- $5,000 under applied 2- $ 5,000 over applied 3- $35,000 under applied 4- $35,000 under applied
Mayco applies overhead on the basis of $10 of direct labor hours. Job No. 501 is charged with $240,000 of direct materials costs and $320,000 of direct labor costs.. The labor took 10,000 hours. The total manufacturing costs for Job No. 501 is $660,000 O $695,000 $570,000 O $560,000 Question 15 5 pts Mayco applies overhead on the basis of $20 per machine hour. Job No. 501 is charged with $240,000 of direct materials costs and $120,000 of direct labor...
QUESTION 12 The predetermined overhead rate is based on the relationship between estimated annual costs and actual activity estimated annual costs and estimated annual activity actual monthly costs and actual annual activity estimated monthly costs and actual monthly activity QUESTION 13 During 2017, Cotte Manufacturing expected Job No 59 to cost $300,000 of overhead, 5500,000 of materials, and $200,000 in labor Cotte applied overhead based on direct labor cost. Actual production required an overhead cost of $295.000 5570.000 in materials...
Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company provided the following estimates at the beginning of the year: Molding Fabrication Total Machine-hours 21,000 31,000 52,000 Fixed manufacturing overhead costs $ 700,000 $ 300,000 $ 1,000,000 Variable manufacturing overhead cost per machine-hour $ 4.00 $ 1.50 During the year, the company had no beginning or ending inventories and it started, completed, and sold only two jobs—Job D-70 and Job C-200. It...
The predetermined overhead rate of 160% allocates overhead based on direct materials cost. If direct labor cost is $55,000 and direct materials cost is $85,000, how much overhead should be applied? 59 Multiple Choice $55,000. $136,000 $53,125 $34,375. Droit 14 View previous attempt D . 25:36 Job 100 was ordered by a customer on March 25. During the month of March, the job required: $1,900 of direct materials and • $3,400 of direct labor In April, the job required an...
Smithson Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company provided the following estimates at the beginning of the year: Molding Fabrication Total Machine-hours 23,000 33,000 56,000 Fixed manufacturing overhead costs $ 730,000 $ 220,000 $ 950,000 Variable manufacturing overhead per machine-hour $ 5.00 $ 5.00 During the year, the company had no beginning or ending inventories and it started, completed, and sold only two jobs—Job D-75 and Job C-100. It provided the following...
Sai Company uses a job order cost system and applies manufacturing overhead costs to jobs using a predetermined overhead rate based on direct labour-hours. The following data were extracted from the company's accounting records for Year 6 Estimated Actual Manufacturing overhead costs $50,000 $54,000 Direct labour-hours 20,000 24,000 hours hours Job #461 was completed during the year and the following costs had been incurred on that job: Direct materials $4,000 $1,500 (at $5 per direct Direct labour labour hour) What...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $117,000 of manufacturing overhead for an estimated allocation base of $90,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: $ 136,000 $ 86,000 Purchase of raw...
Exercise 2-15 (Algo) Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] [The following information applies to the questions displayed below.] Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company provided the following estimates at the beginning of the year: Molding Fabrication Total Machine-hours 24,000 32,000 56,000 Fixed manufacturing overhead cost $ 740,000 $ 200,000 $ 940,000 Variable manufacturing overhead cost per machine-hour $ 3.00 $ 1.50 During...
During 2016 Caruba Manufacturing expected Job 25 to cost $75,000 of overhead, $130,000 of material, and $25,000 in labour. Caruba applied overhead based on direct labour cost. Actual production required an overhead cost of $80,000, $140,000 in materials used; and $20,000 in labour. All of the goods were completed. What amount was transferred to Finished Goods? a) $240,000 b) $230,000 c) $220,000 d) $210,000 why the answer is C