On January 2, 2021, the Pilgrim Enterprise began construction of a building to be used as its office headquarters. The building was completed on December 31, 2021. Expenditures on on construction were as follows:
Date | Expenditure |
January 2, 2021 | $1,000,000 |
March 1 | 960,000 |
July 1 | 600,000 |
December 31 | 240,000 |
On January 2, 2021, the company obtained a $2 million construction loan with a 6% interest rate. In addition, the company has a $2.5 million general purpose bond with a 7% interest rate. The company’s fiscal year-end is December 31.
Required
Calculate the amount that Pilgrim should report as Building on its December 31, 2021 balance sheet and Interest Expense on its income statement for the year ending December 31, 2021. Your work should include calculations of weighted average capital expenditures, avoidable interest and actual interest.
Total cost incurred | 2,800,000 | |
Add: | Avoidable Interest | 130,500 |
Building on its December 31, 2021 | 2,930,500 | |
Actual interest paid | 295,000 | |
Less: | Avoidable Interest | 130,500 |
Interest Expense on its income statement | 164,500 |
Date | Expenditures | Mulatiply: Period in Fraction | Weighted-Average |
January 2, | 1,000,000 | 12/12 | 1,000,000 |
March 1 | 960,000 | 10/12 | 800,000 |
July 1 | 600,000 | 7/12 | 350,000 |
December 31 | 240,000 | 0/12 | - |
Total cost incurred | 2,800,000 | ||
Weighted-Average Accumulated Expenditures | 2,150,000 | ||
Weighted-Average Accumulated Expenditures | Applicable Interest rate | Avoidable Interest | |
Full amount | 2,000,000 | 6% | 120,000 |
2150000-2000000 | 150,000 | 7% | 10,500 |
2,150,000 | 130,500 | ||
Avoidable Interest | 130,500 | ||
Debt type | Interest rate | Amount | Remarks |
Construction loan | 6% | 120,000 | 2000000*6% |
General purpose bond | 7% | 175,000 | 2500000*7% |
Actual interest paid | 295,000 |
On January 2, 2021, the Pilgrim Enterprise began construction of a building to be used as...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,000,000 March 1, 2021 600,000 June 30, 2021 800,000 October 1, 2021 600,000 January 31, 2022 270,000 April 30, 2022 585,000 August 31, 2022 900,000 On January 1, 2021, the company obtained a $3 million construction loan with a 10% interest...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,500,000 March 1, 2021 1,200,000 June 30, 2021 1,400,000 October 1, 2021 1,200,000 January 31, 2022 360,000 April 30, 2022 693,000 August 31, 2022 990,000 On January 1, 2021, the company obtained a $4,000,000 construction loan with a 14% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,740,000 1,380,000 1, 580,000 1, 380,000 387,000 720,000 1, 017, 000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,310,000 March 1, 2021 1,020,000 June 30, 2021 1,220,000 October 1, 2021 1,020,000 January 31, 2022 333,000 April 30, 2022 666,000 August 31, 2022 963,000 On January 1, 2021, the company obtained a $3,700,000 construction loan with a 12% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,740,000 March 1, 2021 1,380,000 June 30, 2021 1,580,000 October 1, 2021 1,380,000 January 31, 2022 387,000 April 30, 2022 720,000 August 31, 2022 1,017,000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a 12% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,280,000 720,000 920,000 720,000 288,000 621,000 918,000 On January 1, 2021, the company obtained a $3,200,000 construction loan with a 15% interest rate. The...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 $2,050,000 1,800,000 2,000,000 1,800,000 450,000 783,000 1,080,000 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 On January 1, 2021, the company obtained a $5,000,000 construction loan with a 9% interest rate. The...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,740,000 March 1, 2021 1,380,000 June 30, 2021 1,580,000 October 1, 2021 1,380,000 January 31, 2022 387,000 April 30, 2022 720,000 August 31, 2022 1,017,000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a 12% interest rate....
On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2022. The company borrowed $2,350,000 at 9% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2021: $7,000,000, 14% bonds $3,000,000, 9% long-term note Construction expenditures incurred during 2021 were as follows: January 1 $ 960,000 March 31 1,560,000 June 30 1,232,000 September 30 960,000...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 $1,280,000 720,000 920,000 720,000 288,000 621,000 918,000 January 31, 2022 April 30, 2022 August 31, 2022 On January 1, 2021, the com 2021 and 2022. The company's other interest-bearing debt included two long-term...