Question

Five brothers Company’s budget and actual costs per unit are provided below for the most recent...

Five brothers Company’s budget and actual costs per unit are provided below for the most recent period. During this period, 800 units were actually produced.   

Product Budget Cost

Product Actual Cost

Materials

Metres

Unit Price Per Metre

     Budget

6

$5.00

$30.00

     Actual

6.2

$4.80

$29.76

Direct labour

Hours

Hourly Rate

     Budget

5

$5.00

$25.00

     Actual

4.8

$5.50

$26.40

Variable overhead

Hours

Hourly Rate

     Budget

5

$4.00

$20.00

     Actual

4.9

$4.10

$20.09

Total unit cost

$75.00

$76.25

Required:

Given the information above, compute the following variances. Also indicate if the variances are favorable or unfavorable.

1. Materials price variance

2. Materials quantity variance

3. Direct labour rate variance

4. Direct labour efficiency variance

5. Variable overhead rate variance

6. Variable overhead efficiency variance

7. Please give some managerial suggestions based on your calculation.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer

  • Working data

Actual DATA for

800

units

Quantity (AQ)

Rate (AR)

Actual Cost

Direct Material

4960

$                   4.80

$           23,808.00

Direct labor

3840

$                   5.50

$           21,120.00

Variable Overhead

3920

$                   4.10

$           16,072.00

Standard DATA for

800

units

Quantity (SQ)

Rate (SR)

Standard Cost

[A]

[B]

[A x B]

Direct Material

( 6 mtr x 800 units)=4800 mtr

$                   5.00

$       24,000.00

Direct labor

( 5 hours x 800 units)=4000 hours

$                   5.00

$       20,000.00

Variable Overhead

( 5 hours x 800 units)=4000 hours

$                   4.00

$       16,000.00

  • Requirements solved [maximum possible]

[1]

Material Price Variance

(

Standard Rate

-

Actual Rate

)

x

Actual Quantity

(

$                               5.00

-

$                       4.80

)

x

4960

992

Variance

$                  992.00

Favourable-F

[2]

Material Quantity Variance

(

Standard Quantity

-

Actual Quantity

)

x

Standard Rate

(

4800

-

4960

)

x

$                           5.00

-800

Variance

$                  800.00

Unfavourable-U

[3]

Labor Rate Variance

(

Standard Rate

-

Actual Rate

)

x

Actual Labor Hours

(

$                               5.00

-

$                       5.50

)

x

3840

-1920

Variance

$              1,920.00

Unfavourable-U

[4]

Labour Efficiency Variance

(

Standard Hours

-

Actual Hours

)

x

Standard Rate

(

4000

-

3840

)

x

$                           5.00

800

Variance

$                  800.00

Favourable-F

[5]

Variable Overhead Rate Variance

(

Standard Rate

-

Actual Rate

)

x

Actual Labor Hours

(

$                               4.00

-

$                       4.10

)

x

3920

-392

Variance

$                  392.00

Unfavourable-U

[6]

Variable Overhead Efficiency Variance

(

Standard Hours

-

Actual Hours

)

x

Standard Rate

(

4000

-

3920

)

x

$                           4.00

320

Variance

$                  320.00

Favourable-F

Add a comment
Know the answer?
Add Answer to:
Five brothers Company’s budget and actual costs per unit are provided below for the most recent...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 1: Five brothers Company's budget and actual costs per unit are provided below for the...

    Question 1: Five brothers Company's budget and actual costs per unit are provided below for the most recent period. During this period, 800 units were actually produced. Product Budget Cost Product Actual Cost Metres $30.00 $29.76 Unit Price Per Metre 6 $5.00 6.2. $4.80 Hourly Rate 5 $5.00 4.8 $5.50 Hours Materials Budget Actual Direct labour Budget Actual Variable overhead Budget Actual Total unit cost $25.00 $26.40 Hours Hourly Rate $20.00 5 4.9 $4.00 $4.10 $20.09 $76.25 $75.00 Required: Given...

  • Header Five brothers Company's budget and actual costs per unit are provided below for the most...

    Header Five brothers Company's budget and actual costs per unit are provided below for the most recent period. During this period, 800 units were actually produced, Product Budget Cost Product Actual Cost $30.00 Metres 6 6.2 Hours 5 4.8 Materials Budget Actual Direct labour Budget Actual Variable overhead Budget Actual Total unit cost Unit Price Per Metre $5.00 $4.80 Hourly Rate $5.00 $5.50 $29.76 $25.00 $26.40 Hours Hourly Rate 5 4.9 $20.00 $4.00 $4,10 $20.09 $76.25 $75.00 Required: Given the...

  • 6 Question 1: Five brothers Company's budget and actual costs per unit are provided below for...

    6 Question 1: Five brothers Company's budget and actual costs per unit are provided below for the most recent period. During this period, 800 units were actually produced. Product Budget Product Cost Actual Cost Materials Metres Unit Price Per Metre Budget $5.00 $30.00 Actual 6.2 $4.80 $29.76 Direct labour Hours Hourly Rate Budget 5 $5.001 $25.00 Actual 4.8 $5.50 $26.40 Variable overhead Hours Hourly Rate Budget $4.001 $20.00 Actual 4.9 $4.101 $20.09 Total unit cost $75.00 $76.25 S Required: Given...

  • Toronto Company's budget and actual costs per unit are provided below for the most recent period....

    Toronto Company's budget and actual costs per unit are provided below for the most recent period. During this period, 700 units were actually produced Product Budget Cost Product Actual Cost $22.00 $19.76 Materials Budget Actual Direct labour Budget Actual Variable overhead Budget Actual Total unit cost Metres 5.5 5.2 Hours 4 3.7 Unit Price Per Metre $4.00 $3.80 Hourly Rate $5.00 $5.50 $20.00 $20.35 Hours Hourly Rate 4 3.81 $14.00 $3.50 $3.10 $11.78 $51.89 $56.00 Required: Given the information above,...

  • Question 1: CNC Company's Budget and actual costs per unit are provided below for the most...

    Question 1: CNC Company's Budget and actual costs per unit are provided below for the most recent period. During this period, 600 units were actually produced. Product Product Standard Cost Actual Cost Materials Metres Unit Price Per Metre Standard 5 $2.00 $10.00 Actual 5.2 $2.20 $11.44 Direct labour Hours Hourly Rate Standard 3 $5.00 $15.00 Actual 3.2 $5.50 $17.60 Variable overhead Hours Hourly Rate Standard 4 $3.00 $12.00 Actual 4.2 $3.10 $13.02 Total unit cost $37.00 $42.06 Required: Given the...

  • yandard and actual costs per unit are provided below for the most recent period Brod 500...

    yandard and actual costs per unit are provided below for the most recent period Brod 500 units were acully produced Product Standard Cost Product Actual Cost $8.00 Metres 4 4.1 Hours 3 3.2 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 $7.79 $21.00 3 $20.80 Hours Hourly Rate $6.00 $3.00 $3.10 2.2 $6.82 $35.41 $35.00 Required: Given the information above, compute the following variances....

  • Page Break Question 1: CNC Company's Budget and actual costs per unit are provided below for...

    Page Break Question 1: CNC Company's Budget and actual costs per unit are provided below for the most recent period. During this period, 600 units were actually produced. Product Standard Cost Product Actual Cost Metres $10.00 5.2 $11.44 Unit Price Per Metre $2.00 $2.20 Hourly Rate $5.00 $5.50 Hours Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost 3 3.2 $15.00 $17.60 Hours Hourly Rate 4 4.2 $12.00 $3.00 $3.10 $13.02 $42.06 $37.00 I Required...

  • Page Break Question 1: CNC Company's Budget and actual costs per unit are provided below for...

    Page Break Question 1: CNC Company's Budget and actual costs per unit are provided below for the most recent period. During this period, 600 units were actually produced. Product Standard Cost Product Actual Cost $10.00 Metres 5 5.2 Hours 3 $11.44 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost Unit Price Per Metre $2.00 $2.20 Hourly Rate $5.00 $5.50 $15.00 3.2 $17.60 Hours Hourly Rate 4 $12.00 $3.00 $3.10 4.2 $13.02 $42.06 $37.00 Required:...

  • Triple Star Company's standard and actual costs per unit are provided below for the most recent...

    Triple Star Company's standard and actual costs per unit are provided below for the most recent period During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost Metres 4 $8.00 4.1 $7.79 Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 Hours Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost $21.00 3.2 $20.80 Hours Hourly Rate $6.00 $3.00 $3.10 2.2 1 $6.82 $35.41 $35.00 Required: Given the information above,...

  • Triple Star Company's standard and actual costs per unit are provided below for the most recent...

    Triple Star Company's standard and actual costs per unit are provided below for the most recent period. During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost $8.00 Metres 4 4.1 Hours 3 3.2 $7.79 Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 $21.00 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost I 3 $20.80 Hours Hourly Rate 2 2.2 $6.00 $3.00 $3.10 $6.82 $35.41 $35.00 Required: Given...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT