Question

6 Question 1: Five brothers Companys budget and actual costs per unit are provided below for the most recent period. During
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Direct Materials Variance Dividing Data ACTUAL COST Flexible Budget (Standard) Actual Quantity used Actual Quantity used 4960

Add a comment
Know the answer?
Add Answer to:
6 Question 1: Five brothers Company's budget and actual costs per unit are provided below for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 1: Five brothers Company's budget and actual costs per unit are provided below for the...

    Question 1: Five brothers Company's budget and actual costs per unit are provided below for the most recent period. During this period, 800 units were actually produced. Product Budget Cost Product Actual Cost Metres $30.00 $29.76 Unit Price Per Metre 6 $5.00 6.2. $4.80 Hourly Rate 5 $5.00 4.8 $5.50 Hours Materials Budget Actual Direct labour Budget Actual Variable overhead Budget Actual Total unit cost $25.00 $26.40 Hours Hourly Rate $20.00 5 4.9 $4.00 $4.10 $20.09 $76.25 $75.00 Required: Given...

  • Header Five brothers Company's budget and actual costs per unit are provided below for the most...

    Header Five brothers Company's budget and actual costs per unit are provided below for the most recent period. During this period, 800 units were actually produced, Product Budget Cost Product Actual Cost $30.00 Metres 6 6.2 Hours 5 4.8 Materials Budget Actual Direct labour Budget Actual Variable overhead Budget Actual Total unit cost Unit Price Per Metre $5.00 $4.80 Hourly Rate $5.00 $5.50 $29.76 $25.00 $26.40 Hours Hourly Rate 5 4.9 $20.00 $4.00 $4,10 $20.09 $76.25 $75.00 Required: Given the...

  • Five brothers Company’s budget and actual costs per unit are provided below for the most recent...

    Five brothers Company’s budget and actual costs per unit are provided below for the most recent period. During this period, 800 units were actually produced.          Product Budget Cost Product Actual Cost Materials Metres Unit Price Per Metre          Budget 6 $5.00 $30.00        Actual 6.2 $4.80   $29.76 Direct labour Hours Hourly Rate          Budget 5 $5.00 $25.00        Actual 4.8 $5.50   $26.40 Variable overhead Hours Hourly Rate          Budget 5 $4.00 $20.00        Actual 4.9 $4.10   $20.09 Total unit cost     $75.00 $76.25 Required:...

  • Toronto Company's budget and actual costs per unit are provided below for the most recent period....

    Toronto Company's budget and actual costs per unit are provided below for the most recent period. During this period, 700 units were actually produced Product Budget Cost Product Actual Cost $22.00 $19.76 Materials Budget Actual Direct labour Budget Actual Variable overhead Budget Actual Total unit cost Metres 5.5 5.2 Hours 4 3.7 Unit Price Per Metre $4.00 $3.80 Hourly Rate $5.00 $5.50 $20.00 $20.35 Hours Hourly Rate 4 3.81 $14.00 $3.50 $3.10 $11.78 $51.89 $56.00 Required: Given the information above,...

  • Question 1: CNC Company's Budget and actual costs per unit are provided below for the most...

    Question 1: CNC Company's Budget and actual costs per unit are provided below for the most recent period. During this period, 600 units were actually produced. Product Product Standard Cost Actual Cost Materials Metres Unit Price Per Metre Standard 5 $2.00 $10.00 Actual 5.2 $2.20 $11.44 Direct labour Hours Hourly Rate Standard 3 $5.00 $15.00 Actual 3.2 $5.50 $17.60 Variable overhead Hours Hourly Rate Standard 4 $3.00 $12.00 Actual 4.2 $3.10 $13.02 Total unit cost $37.00 $42.06 Required: Given the...

  • Page Break Question 1: CNC Company's Budget and actual costs per unit are provided below for...

    Page Break Question 1: CNC Company's Budget and actual costs per unit are provided below for the most recent period. During this period, 600 units were actually produced. Product Standard Cost Product Actual Cost Metres $10.00 5.2 $11.44 Unit Price Per Metre $2.00 $2.20 Hourly Rate $5.00 $5.50 Hours Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost 3 3.2 $15.00 $17.60 Hours Hourly Rate 4 4.2 $12.00 $3.00 $3.10 $13.02 $42.06 $37.00 I Required...

  • Page Break Question 1: CNC Company's Budget and actual costs per unit are provided below for...

    Page Break Question 1: CNC Company's Budget and actual costs per unit are provided below for the most recent period. During this period, 600 units were actually produced. Product Standard Cost Product Actual Cost $10.00 Metres 5 5.2 Hours 3 $11.44 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost Unit Price Per Metre $2.00 $2.20 Hourly Rate $5.00 $5.50 $15.00 3.2 $17.60 Hours Hourly Rate 4 $12.00 $3.00 $3.10 4.2 $13.02 $42.06 $37.00 Required:...

  • Header Question 1 Triple Star Company's standard and actual costs per unit are provided below for...

    Header Question 1 Triple Star Company's standard and actual costs per unit are provided below for the most recent period. During this period, 500 units were actually produced Product Product Standard Cont Actual Cost Materials Metres Unit Price Per Metre Standard 4 $2.00 $8.00 Actual $1.90 $7.79 Direct labour Hours Hourly Rate Standard $7.00 $21.00 Actual 3.2 $6.50 $20.80 Variable overhead Hours Hourly Rate Standard 2 $3.00 $6.00 Actual 2.2 $3.10 $6.82 Total unit cost $35.00 $35.41 Required: Given the...

  • Triple Star Company's standard and actual costs per unit are provided below for the most recent...

    Triple Star Company's standard and actual costs per unit are provided below for the most recent period During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost Metres 4 $8.00 4.1 $7.79 Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 Hours Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost $21.00 3.2 $20.80 Hours Hourly Rate $6.00 $3.00 $3.10 2.2 1 $6.82 $35.41 $35.00 Required: Given the information above,...

  • Triple Star Company's standard and actual costs per unit are provided below for the most recent...

    Triple Star Company's standard and actual costs per unit are provided below for the most recent per During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost Metres $8.00 4 4.1 $7.79 Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 Hours Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost $21.00 3 3.2 $20.80 Hours Hourly Rate $6.00 2 2.2 $3.00 $3.10 $6.82 $35.41 $35.00 Required: Given the information...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT