Question

A company’s projects extend over several years and collection of receivables is reasonably certain. Each of...

A company’s projects extend over several years and collection of receivables is reasonably certain. Each of its projects has a contract that specifies a price, and reliable estimates can be made of the extent of progress and cost to complete each project.

The method that the company should use to account for construction revenue is the:

Question 11 options:

Completed-contract method

Sales method

Installment method

Cost-to-cost method

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Option A Completed Contract method is the correct answer.

GAAPs allow completed contract method to account for the projects with the following characteristics:

'i. The project is long-term

ii. Collection of receivables is reasonably certain

iii. Having a contract which specifies price

iv. Possibility to make reliable estimates about completion and cost as the project progresses

The remaining options are wrong becasue the project with specified charecterstics are different form the given.

Add a comment
Know the answer?
Add Answer to:
A company’s projects extend over several years and collection of receivables is reasonably certain. Each of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • For each scenario, indicate how much revenue and, when applicable, expense are recognized in 2019. A. Company A enters into a contract for the provision of multiple deliverables to a customer in January, 2019. The selling price is $200,000. If each of th

    For each scenario, indicate how much revenue and, when applicable, expense are recognized in 2019.A. Company A enters into a contract for the provision of multiple deliverables to a customer in January, 2019. The selling price is $200,000. If each of the three components of the contract were sold separately, the selling price would be $120,000, $80,000, and $20,000. The first component is equipment, which was delivered in 2019. The second component is a software upgrade that will be provided...

  • Which of the following is least likely to be a reason why a long-term construction contract...

    Which of the following is least likely to be a reason why a long-term construction contract would qualify for revenue recognition over time? Multiple Choice The customer controls the asset as it is created. The seller is creating an asset that has no alternative use to the seller, and the seller has the legal right to receive payment for progress to date. The seller is constructing an addition to property that is owned by the customer. The customer consumes the...

  • 23) A right of return exists when: A) the customer is entitled to a full or...

    23) A right of return exists when: A) the customer is entitled to a full or partial refund. B) the customer is entitled to a credit against amounts owed. C) the customer is entitled to another product in exchange. D) any one of these conditions is met. 19) Noah Construction Company is building a large complex for a contract price of $5,000,000. This is a three-year project and the requirements for recognizing revenue over time are met. The total estimated...

  • In February 2020, Crane Construction signed a contract and commenced construction on a parking garage. The t...

    In February 2020, Crane Construction signed a contract and commenced construction on a parking garage. The total contract price was $89.8 million and was expected to be completed in July 2024 at a total estimated cost of $82.0 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project...

  • 1. Assurning a long-term construction project makes an overall profit, during the interim years, percentage of...

    1. Assurning a long-term construction project makes an overall profit, during the interim years, percentage of completion method accounting has impact on construction company's: Income Statement ONLY X Balance Sheet ONLY BOTH Income Statement and Balance Sheet None of the above 2. When a company write-off a bad debt under GAAP, it has impact on this company's: Income Statement ONLY Balance Sheet ONLY BOTH Income Statement and Balance Sheet Cash Flow Statement ONLY х 3. For a construction company working...

  • Case Study Revenue Recognition For this case, you are the lead analyst for a team considering...

    Case Study Revenue Recognition For this case, you are the lead analyst for a team considering the potential acquisition of three separate projects of a single company, Gasco. You are to determine if your team will acquire one, two, all three of the projects; or none of them. The team intends to acquire any project it deems profitable over the duration of the project. For purposes of this case, ignore purchase price of the projects. Gasco is a natural gas...

  • Problem 3-3 Revenue recognition over time and at a point in time under ASC Topic 606...

    Problem 3-3 Revenue recognition over time and at a point in time under ASC Topic 606 (LO3-4) MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows: 2020 $150,000 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year 2019 $290,000 145,000 260,000 240,000 265,000 285,000 Required: 1. Record the preceding transactions in MSK's books...

  • Bright Future signed a $700,000 contract to an d the project required three years to complete....

    Bright Future signed a $700,000 contract to an d the project required three years to complete. Bright Future estimated that total contract coswabe SGD 000 The financial information during 2031 203 related to the construction contracts as the following 2002 2003 Costs incurred to date $200.000 $370,000 $610,000 Estimated costs to complete 400 000 250.000 Progress bilings made during the year 210,000 315.000 175.000 Collections of billings during the year 200,000 320,000 180,000 Additional information: 1) The customer does not...

  • MULTIPLE-CHOICE questions E1-1.ABC Engineering use cost method to cart engineering use cost method to calculate the...

    MULTIPLE-CHOICE questions E1-1.ABC Engineering use cost method to cart engineering use cost method to calculate the stage of completion of its construction act. Total estimated contract costs of their contract are $100 million. In the first year of their contract, ABC Engineering has incurred the following costs: Cost of purchase of raw materials worth $10 million ($5 million of which are unused by the year end) 2. Payment of salaries and wages of $5 million ($1 million of accrued salaries...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT