Question

Which of the following is least likely to be a reason why a long-term construction contract...

Which of the following is least likely to be a reason why a long-term construction contract would qualify for revenue recognition over time?

Multiple Choice

  • The customer controls the asset as it is created.

  • The seller is creating an asset that has no alternative use to the seller, and the seller has the legal right to receive payment for progress to date.

  • The seller is constructing an addition to property that is owned by the customer.

  • The customer consumes the benefit of the seller's work as it is performed.

When using the cost recovery method of accounting for long-term construction contracts under IFRS:

Multiple Choice

  • Estimated losses on the overall contract are recognized before the contract is completed.

  • Companies can use the percentage-of-completion method if that is their preference.

  • Expenses are recorded each period, but revenue is only recognized when the contract is completed.

  • Neither gains nor losses are recognized until the contract is completed.

Under the realization principle, revenue should not be recognized until the earnings process is deemed virtually complete and:

Multiple Choice

  • Collection is reasonably certain.

  • Revenue is realized.

  • Collection is absolutely assured.

  • Any receivable is collected.

Summary data for Benedict Construction Co.'s (BCC) Job 1227, which was completed in 2021, are presented below:

Bid price $ 450,000
Contract cost: 2020 (180,000 )
2021 (195,000 )
Gross profit: 75,000


Estimated cost to complete:

12/31/2020 $ 200,000
12/31/2021 0


Assuming BCC recognizes revenue upon project completion, what would gross profit have been in 2020 and 2021 (rounded to the nearest thousand)?

2020 2021
a. $ 36,000 $ 39,000
b. $ 30,000 $ 45,000
c. $ 70,000 $ 5,000
d. $ 0 $ 75,000

Multiple Choice

  • option b

  • option d

  • option a

  • option c

Which of the following is a characteristic of a contract for purposes of revenue recognition?

Multiple Choice

  • Commercial substance.

  • Nonverbal.

  • Notarized within the company's state of incorporation.

  • Reasonable profit margin.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. Revenue Recognition over a period of time for a long Term construction Contract:

All the Four options given for this question are the criteria why a revenue is recognized over a period of time. When it comes to Long term construction contract one option which is least likely to be the reason is Option D - That the customer consumes the benefit of the sellers work as it is performed. Because incase of construction the customer cannot consume the benfit (i.e) use the building untill it is fully completed.

All other options are perfectly suitable for the long term construction contract.

Option A - Yes, The customer controls the asset as it is created. The builder has only temporary right to make construction on the site but the ownership is with the customer and he has the right to control the asset.

Option B - Yes, The Seller has no alternate use to the building he creates and he has legal obligation to receive the payment. The Seller (i.e) the buyer builds the building on the site of the customer according to his requirements and he cannot sell the building alone or use it.

Option D - Yes, The seller is creating an addition to the property that is owned by the buyer. The builder is creating addition to the site already owned by the customer.

Add a comment
Know the answer?
Add Answer to:
Which of the following is least likely to be a reason why a long-term construction contract...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $370 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 70 $ 110 $ 80 Estimated costs to complete as of...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows $ in millions): 2021 $ 70 2022 $60 30 2023 $30 Costs incurred during the year Estimated costs to complete as of December...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $400 million. The expected completion date is April 1, 2023. just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 60 $130 $55...

  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 S 30 140 $40...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 40 $80 $50...

  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $390 million. The expected completion date is April 1, 2020. lust in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2018 2019 2020 $ 60 $130 $70...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 $ 70 130 Costs incurred during the year Estimated costs to complete as of December 31 2022 $60 30...

  • On June 15, 2021. Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021. Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington D.C. for $350 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows (5 in millions): 2021 $ 3e 170 Costs incurred during the year Estimated costs to complete as of December 31 2022 $142 0...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $320 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 80 $ 40 $ 90 Estimated costs to complete as of...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $320 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 80 $ 40 $ 90 Estimated costs to complete as of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT