D 1:
Following is the cost per unit when output is 6400:
Particulars | Unit cost per week | Output | Total cost |
Parts purchased | $0.35+$0.30+$0.10=$0.75 | 6400 | $4800 |
Electricity | $0.01 | 6400 | $64 |
Assembly labor | 2 assemblies x $0.25=$0.5 | 6400 | $3200 |
Drilling labor | $0.15 | 6400 | $960 |
Overhead cost | $1600 | $1600 | |
Depreciation | $30 | $30 | |
Total cost per week | $10654 | ||
Units per week | 6400 | ||
Cost per unit | 1.6646875 |
The cost per unit is calculated using the following formula:
=Total cost per week/No.of units produced per week
=$10654/6400
=$1.6646875 per unit
D 2:
Following is the cost per unit when output is 7800:
Particulars | Unit cost per week | Output | Total cost |
Parts purchased | $0.35+$0.30+$0.10=$0.75 | 7800 | $5850 |
Electricity | $0.01 | 7800 | $78 |
Assembly labor | 2 assemblies x $0.25=$0.5 | 7800 | $3900 |
Drilling labor | $0.15 | 7800 | $1170 |
Overhead cost | $1600 | $1600 | |
Depreciation | $30 | $30 | |
Total cost per week | $12628 | ||
Units per week | 7800 | ||
Cost per unit | 1.61897435897 |
The cost per unit is calculated using the following formula:
=Total cost per week/No.of units produced per week
=$12628/7800
=$1.61897435897 per unit
i need help with d-1 d-2 and e please! Problem 7-15 Chec The Goodparts Company produces...
The Goodparts Company produces a component that is subsequently used in the aerospace industry. The component consists of three parts (A, B, and C) that are purchased from outside and cost 40, 35, and 15 cents per piece, respectively. Parts A and B are assembled first on assembly line 1, which produces 155 components per hour. Part C undergoes a drilling operation before being finally assembled with the output from assembly line 1. There are in total six drilling machines,...
Vizzini Company produces an automotive part. The part consists of three purchased raw materials (A, B, and C) that cost $0.40, $0.35, and $0.15 cents per unit, respectively. Parts A and B are assembled first on assembly line 1, which produces 140 sub-assemblies (A and B combined) per hour. Part C undergoes a drilling operation before being finally assembled with the output from assembly line 1. There are in total six drilling machines, but at present only three of them...
Q 5-8 Your company produces electronic connectors, which consist of a metal strip with multiple prongs assembled into a plastic housing. The manufacturing process is divided into four separate departments: 1) Injection molding, where the small plastic housings are produced; 2) Stamping, where the steel strips are punched out of thin coils of steel; 3) Plating, where the steel strips, after being stamped, are plated with tin or gold; and 4) Assembly, where the plated strips are inserted into the...
suppose that a second shift is added to the assembly department. what is the new capacity of the assembly department Below is the XYZ operation. Molded Parts Mold Parts Finished Componen Final Assembly Purchased Pary Vnventory Purchase Parts from Vendors Assumptions 1) One worker is needed to operate each machine in the molding dept. 2) The molding dept. has 10 machines. 3) Currently 6 workers in the molding dept., earning $15 per hour. 4) Each molding machine produces 25 parts...
d-1. Determine the cost per unit output for part b. 1.54 d-2. Determine the cost per unit output for part c. 1.50 e. The product is sold at $6 per unit. Assume that the cost of a drilling machine (fixed cost) is $34,000 and the company produces 7,400 units per week. Assume that four drilling machines are used for production. If the company had an option to buy the same part at $5 per unit, what would be the break-even...
I need help with my assignment please Way Cool produces two different models of air conditioners. The company produces the mechanical systems in their components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow Process Activity Components Changeover Machining Setups Overhead Cost Driver $ 547,350 Number of batches 358,316 Machine hours 145,200 Number of setups Quantity 890 7,640...
In the molding shop, there are 11 machines capable of molding the one part done in-house, but historically one machine is always being maintained or repaired at any given time. Each machine requires a full-time operator who earns an hourly wage of $15, though only 50 minutes of a molding operator's typical hour is occupied with the tasks of loading, unloading, actively monitoring, and adjusting the machine. The machines can each produce 25 parts per hour. The workers will work...
Hi, I am requesting your help. Thank you, Michelle _____________________________ You work at Ford Motor Company and are responsible for determining weekly production capacity for the Juarez, Mexico assembly plant. There are 21 days left in the production month. Your sales manager just informed you that 4725 vehicles need to be produced in the upcoming 21 days to meet projected sales demand in the United States. Your production capacity constraints are as follows: Each assembly line shift runs for eight...
Goode Perk Company The Goode Perk Company produces several models of coffee makers. There is little difference in the production time required for the various model coffee machines. The plant is designed to produce 160 coffee machines per eight-hour shift, and there are two shifts per working day. However, the plant does not operate for the full eight hours: the employees take two 12-minute breaks in each shift, one in the first four hours and one in the second four...
Question 2. Question 3. Laval produces lamps and home lighting fixtures. Its most popular product is a brushed aluminum desk lamp. This lamp is made from components shaped in the fabricating department and assembled in the assembly department Information related to the 26.000 desk lamps produced annually follows 5.200,000 Direct labor Fabricating department (0.000 DLH Assembly department (15,600 DLH 520 per DUH) 527 per OLH) 16.00 5421,200 Fabricating department Assembly department Expected overhead cost and related data for the two...