Question

Question 1 5 pts During the month the company completed 70,000 widgets, including the 10,000 widgets 50% complete of work in
Question 2 12.5 pts The company had 4000 gallons of ice cream in work in process 60% complete at the beginning of the month.
VCCs.edu ch The company uses a single plantwide factory overhead rate. The budgeted Factory Overhead Costs for the year are $
The company has two departments - Cutting and Sewing. The company uses the multiple production department factory overhead ra
Answers should be entered to a single decimal place (ex 3.5) with no signs or other punctuation Direct labor hours Cutting De
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Question 1

Correct answer-------------Units started and completed = 60,000 units

Working

Total Units
Units Transferred:
From WIP             10,000
From units started/Introduced             60,000
Total             70,000
Add a comment
Know the answer?
Add Answer to:
Question 1 5 pts During the month the company completed 70,000 widgets, including the 10,000 widgets...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The company has two departments – Cutting and Sewing. The company uses the multiple production department...

    The company has two departments – Cutting and Sewing. The company uses the multiple production department factory overhead rate method using direct labor hours. The budgeted factory overhead is $1,120,000 for the Cutting Department and $660,000 for the Sewing Department. The company plans to make 100,000 shirts and 60,000 pairs of pants. It takes 1 hour to cut and 1 hour to sew a shirt. It takes 1 hour to cut and 2 hours to sew a pair of pants....

  • The company has two departments – Cutting and Sewing. The company uses the multiple production department...

    The company has two departments – Cutting and Sewing. The company uses the multiple production department factory overhead rate method using direct labor hours. The budgeted factory overhead is $900,000 for the Cutting Department and $500,000 for the Sewing Department. The company plans to make 100,000 shirts and 50,000 pairs of pants. It takes 1 hour to cut and one hour to sew a shirt. It takes 1 hour to cut and 2 hours to sew a pair of pants....

  • The total factory overhead for Urban Styles, Inc. is budgeted for the year at $1,302,000, divided...

    The total factory overhead for Urban Styles, Inc. is budgeted for the year at $1,302,000, divided into two departments: Cutting, $1,176,000, and Sewing, $126,000. Urban Styles manufactures two types of men's pants: jeans and khakis. The jeans require three direct labor hours in Cutting and one direct labor hour in Sewing. The khakis require four direct labor hours in Cutting and one direct labor hour in Sewing. Each product is budgeted for 7,000 units of production for the year. When...

  • Direct Labor Variances Greeson Clothes Company produced 15,000 units during June of the current year. The...

    Direct Labor Variances Greeson Clothes Company produced 15,000 units during June of the current year. The Cutting Department used 2,900 direct labor hours at an actual rate of $12.10 per hour. The Sewing Department used 4,800 direct labor hours at an actual rate of $11.80 per hour. Assume that there were no work in process inventories in either department at the beginning or end of the month. The standard labor rate is $12.00. The standard labor time for the Cutting...

  • At the beginning of the year, Glaser Company estimated the following: Testing Assembly Department Department Total...

    At the beginning of the year, Glaser Company estimated the following: Testing Assembly Department Department Total Overhead $654,000 $719,400 $1,373,400 Direct labor hours 125,500 143,070 268,570 Machine hours 76.750 49,120 12870 Glaser uses departmental overhead rates. In the assembly department, overhead is applied on the basis of direct labor hours. In the testing department, overhead is applied a basis of machine hours. Actual data for the month of March are as follows: Testing Assembly Department Department Total Overhead $36,328 Direct...

  • Direct Labor Variances Greeson Clothes Company produced 17,000 units during June of the current year. The...

    Direct Labor Variances Greeson Clothes Company produced 17,000 units during June of the current year. The Cutting Department used 3,200 direct labor hours at an actual rate of $13.50 per hour. The Sewing Department used 5,300 direct labor hours at an actual rate of $13.20 per hour. Assume that there were no work in process inventories in either department at the beginning or end of the month. The standard labor rate is $13.40. The standard labor time for the Cutting...

  • Print Item Predetermined Departmental Overhead Rates, Applying Overhead to Production At the beginning of the year,...

    Print Item Predetermined Departmental Overhead Rates, Applying Overhead to Production At the beginning of the year, Hallett Company estimated the following: Cutting Department Overhead Total $240,000 Sewing Department $350,000 100,000 $590,000 Direct labor hours Machine hours 31,200 131,200 150,000 150,000 Hallett uses departmental overhead rates. In the cutting department, overhead is applied on the basis of machine hours. In the sewing department, overhead is applied on the basis of direct labor hours. Actual data for the month of June are...

  • Direct Labor Variances Greeson Clothes Company produced 24,000 units during June of the current year. The...

    Direct Labor Variances Greeson Clothes Company produced 24,000 units during June of the current year. The Cutting Department used 4,600 direct labor hours at an actual rate of $14.70 per hour. The Sewing Department used 7,600 direct labor hours at an actual rate of $14.40 per hour. Assume that there were no work in processinventories in either department at the beginning or end of the month. The standard labor rate is $14.60. The standard labor time for the Cutting and...

  • A factory makes 500,000 shirts and 1,000,000 pants. Direct materials are $3,500,000 and $2,000,000 for pants...

    A factory makes 500,000 shirts and 1,000,000 pants. Direct materials are $3,500,000 and $2,000,000 for pants and shirts, respectively. Direct Labor is $1,300,000 and $500,000 for pants and shirts, respectively. Factory overhead is $4,200,000. The firm pays $20 per hour. The allocation base is direct labor hours. Required: derive the unit costs for a pair of pants and a shirt. OH Cost OH Rate Total Allocation Base Allocation | Allocated Base Used | OH Object By Object II | Allocation...

  • Predetermined Departmental Overhead Rates, Applying Overhead to Production At the beginning of the year, Hallett Company...

    Predetermined Departmental Overhead Rates, Applying Overhead to Production At the beginning of the year, Hallett Company estimated the following: Cutting Department Sewing Department Total Overhead $240,000 $350,000 $590,000 Direct labor hours 31,200 100,200 131,400 Machine hours 150,000 — 150,000 Hallett uses departmental overhead rates. In the cutting department, overhead is applied on the basis of machine hours. In the sewing department, overhead is applied on the basis of direct labor hours. Actual data for the month of June are as...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT