Question

The balance in the WIP account on July 1 was $18,200 and on July 31 was...

The balance in the WIP account on July 1 was $18,200 and on July 31 was $15,120. Costs incurred during the month were as follows direct labor $24,300 and factory overhead $41,600. If the cost of goods completed during July was $125,230. What is the total manufacturing cost for July
a) $107,030
b) $65,900
c) $56,250
d) 122,150
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans:

Total manufacturing costs : Cost of goods completed during July + Ending WIP - Opening WIP

Cost of goods completed during July : $125,230

Ending WIP : $15,120

Opening WIP : $18,200

Total manufacturing costs : $125,230 + $15,120 - $18,200 = $122,150

You can ask your queries in comment section. Please rate if you found this helpful.

Add a comment
Know the answer?
Add Answer to:
The balance in the WIP account on July 1 was $18,200 and on July 31 was...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • O’Reilly Manufacturing Co.’s cost of goods sold for the month ended July 31 was $345,000. The...

    O’Reilly Manufacturing Co.’s cost of goods sold for the month ended July 31 was $345,000. The ending work in process inventory was 90% of the beginning work in process inventory. Factory overhead was 50% of the direct labor cost. No indirect materials were used during the period. Other information pertaining to O’Reilly’s inventories and production for July is as follows: REQUIRED: 1. Prepare a statement of cost of goods manufactured for the month of July. (Hint: Set up a statement...

  • 1. The following selected ledger accounts of the Reynolds Manufacturing Company are for July. Materials Inventory...

    1. The following selected ledger accounts of the Reynolds Manufacturing Company are for July. Materials Inventory July 1 balance …………………….. 150,000 July credits ……………………. 550,000 July debits ………………………….. 475,000 Manufacturing Overhead July debits ……………………...... 638,000 July 1 balance…………………… 50,000 July credits ……………………… 608,000 Work in Process Inventory July 1 balance …………………….. 100,000 July credits …………………… 1,650,000 July debits: Direct material …………………… 488,000 Direct labor ………………………… 675,000 Manufacturing overhead ………….. ? Wages Payable July debits …………………….. 850,000 July 1 balance……………………. 188,000...

  • Company X uses a job cost system and applies overhead to production on the basis of...

    Company X uses a job cost system and applies overhead to production on the basis of direct labor cost. On January 1, 2018, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: DM of TL27,000, DL of TL11,600, and MOH of TL15,008. As of January 1, Job 49 had been completed at a cost of TL85,004 and was part of finished goods inventory. There was a TL13,500 balance...

  • P15.1A (LO 1, 2, 3, 4,5), AP Lott Company uses a job order cost system and...

    P15.1A (LO 1, 2, 3, 4,5), AP Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2022, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20.000, direct labor $12,000, and manufacturing overhead $16,000. As of January 1, Job 49 had been completed at a cost of $90,000 and was part of...

  • Use below information for Questions 5 to 7: Company X uses a job cost system and...

    Use below information for Questions 5 to 7: Company X uses a job cost system and applies overhead to production on the basis of direct labor cost. On January 1, 2018, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: DM of TL27,000, DL of TL11,600, and MOH of TL15,003. As of January 1, Job 49 had been completed at a cost of TL85,007 and was part of...

  • Exercise 6 Our Co's packaging department started April with a beginning WIP inventory of 90 units....

    Exercise 6 Our Co's packaging department started April with a beginning WIP inventory of 90 units. During April, it transferred 540 units to finished goods and its ending WIP inventory consists of 60 units. Complete the physical unit flow information below. Physical Unit Flow Units to be accounted for: Beginning work in process Units started this period Total units to be account for Units accounted for as follows: Completed and transferred out Ending goods in process Total units accounted for...

  • Page 1 of 1 Job Order Costing (Practice B) man Manufacturing Company uses a job order...

    Page 1 of 1 Job Order Costing (Practice B) man Manufacturing Company uses a job order cost system. Degelman applies overhead to production on the basis of direct labor cost. man estimates total manufacturing overhead costs of $505,750, direct labor costs 395,000, and direct labor hours of 17,000 for the fiscal year ended January 31, 2020. on January 1, 2020. Job 50 was the only iob in process. The costs incurred prior to January 1 on Job 50 were as...

  • Cost data for Sandusky Manufacturing Company for the month ended January 31 are as follows: Inventories January 1...

    Cost data for Sandusky Manufacturing Company for the month ended January 31 are as follows: Inventories January 1 January 31 Materials $224,500 152,660 Work in process Finished goods $199,810 135,870 133,870 116,740 $404,100 431,040 43,100 Direct labor Materials purchased during January Factory overhead incurred during January: Indirect labor Machinery depreciation Heat, light, and power Supplies Property taxes Miscellaneous costs 26,040 8,980 7,180 6,290 11,670 a. Prepare a cost of goods manufactured statement for January Sandusky Manufacturing Company Statement of Cost...

  • Enter the following entries for the month of July. A. Cash sales of inventory: $800. The...

    Enter the following entries for the month of July. A. Cash sales of inventory: $800. The cost of inventory sold was $350. B. Selling and Administrative expenses incurred and paid: $1,200. C. Raw Materials purchased on account: $2,560. D. Materials requisitioned and used in production: $980. E. Direct Labor wages incurred during July: $2,875. Direct Labor wages actually paid in July were $2,000. F. Factory Overhead was allocated to Work in Process Inventory at a predetermined overhead allocation rate of...

  • 2. The following account appears in the ledger after only part of the postings have been...

    2. The following account appears in the ledger after only part of the postings have been completed for July the first month of the current fiscal year: Work in Process July | Balance 28.200 Direct materials2 74. CCO Direct labor 152,000 Factory overhead is applied to jobs at the rate of 40% of direct labor cost. The actual factory overhead incurred for July was $58,000. Jobs completed during the month totaled $298,200. (a) What is the balance of the factory...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT