1)
Overhead rates using thetraditional costing method = budgeted overhead costs/Machine hours
Overhead rates using the traditional costing method = 12306 /
2500
Overhead rates using the traditional costing method = $ 4.9224
Amount of overhead assigned to Sandy beach = 4.9224 * 1250 = $ 6153
Amount of overhead assigned to Rocky River = 4.9224 * 1250 = $ 6153
2)
Sandy Beach | Rocky River | |
Direct Material | 18.90 | 27.00 |
Direct Labor | 14.60 | 17.90 |
Overhead Cost [ 6153 / 1230 & 6153 / 980] | 5.00 | 6.28 |
Production cost per unit | 38.50 | 51.18 |
3)
Sandy beach
Gross Margin = Sale Price - Production cost per unit
Gross Margin = 82.40 - 38.50 = 43.90
Rocky River
Gross Margin = Sale Price - Production cost per unit
Gross Margin = 106 - 51.18 = 54.82
4)
Activity Cost Pool | Estimated Overhead |
Expected Use of Cost Drivers per Activity |
Activity Rate | |
[b] | [c] | [b/c] | ||
Setup costs | 3150 | 50 | 63.00 | per setup |
Quality control | 6206 | 535 | 11.60 | per inspection |
Maintenance | 2950 | 2500 | 1.18 | per MHR |
PA4-4 (Algo) Selecting Cost Drivers, Assigning Costs Using Activity Rates [LO 4-1,4-3, 4-4, 4-6) Keller Company...
Keller Company makes two models of battery operated boats, the Sandy Beach and the Rocky River. Basic production information follows: Direct materials cost per unit Direct labor cost per unit Sales price per unit Expected production per month Sandy Beach $19.10 15.10 83.70 1,240 units Rocky River $ 27.20 18.40 105.00 920 units Keller has monthly overhead of $11,756, which is divided into the following cost pools: Setup costs Quality control Maintenance Total $ 3,050 5,400 3,306 $ 11,756 The...
Pre-Built Problems Keller Company makes two models of battery operated boats, the Sandy Beach and the Rocky River Basic production information follows: Sandy Beach $19.60 HI 14.00 Rocky Riven 27.20 16. Direct materials cost per unit Direct labor cost per unit Sales price per unit Expected production per month 920 units Keller has monthly overhead of 511,632, which is divided into the following cost pools Quality control Maintenance Total The company has also compiled the following information about the chosen...
Keller Company makes two models of battery-operated boats, the Sandy Beach and the Rocky River. Basic production information follows: Sandy Beach $19.00 Rocky River $ 27.40 17.30 106.e0 Direct materials cost per unit Direct labor cost per unit Sales price per unit Expected production per month 14.60 82.30 1,210 units 910 units Keller has monthly overhead of S11,716, which is divided into the following cost pools: $ 2,135 5,626 3,955 $ 11,716 Setup costs Quality control Maintenance Total The company...
Keller Company makes two models of battery-operated boats, the Sandy Beach and the Rocky River. Basic production information follows: Rocky River $ 27.10 Sandy Beach Direct materials cost per unit $19.30 Direct labor cost per unit 13.30 Sales price per unit 83.90 Expected production per month 1, 240 units 18.60 105.00 9 10 units Keller has monthly overhead of $11,466, which is divided into the following cost pools: Setup costs Quality control Maintenance Total $ 1,920 6,212 3, 335 $...
Keller Company makes two models of battery-operated boats, the Sandy Beach and the Rocky River. Basic production information follows: Direct materials cost per unit Direct labor cost per unit Sales price per unit Expected production per month Sandy Beach $18.70 15.10 82.70 1,150 units Rocky River $ 28.10 18.90 106.00 960 units Keller has monthly overhead of $10,844, which is divided into the following cost pools: Setup costs Quality control Maintenance Total $ 2,600 5,220 3,024 $ 10,844 The company...
Direct materials cost per unit Direct labor cost per unit Sales price per unit Expected production per month Sandy Beach $18.50 14.20 83.70 1,220 units Rocky River $ 26.20 17.60 105.ee 990 units Keller has monthly overhead of $11.446, which is divided into the following cost pools: Setup costs Quality control Maintenance Total $ 2,790 5,506 3,150 $ 11,446 The company has also compiled the following Information about the chosen cost drivers: Sandy Beach Rocky River Number of setups Number...
Keller Company makes two models of battery-operated boats, the Sandy Beach and the Rocky River. Basic production information follows: Sandy Beach Rocky River Direct materials cost per unit $ 19.60 $ 27.30 Direct labor cost per unit 13.20 17.20 Sales price per unit 82.10 105.00 Expected production per month 1,250 units 950 units Keller has monthly overhead of $12,203, which is divided into the following cost pools: Setup costs $ 3,100 Quality control 5,487 Maintenance 3,616 Total $ 12,203...
Check my work Keller Company makes two models of battery-operated boats, the Sandy Beach and the Rocky River. Basic production information follows: Sandy Beach Direct materials cost per unit $18.60 Direct labor cost per unit 14.80 Sales price per unit 83.40 Expected production per month 1,230 units Rocky River $ 26.40 18.30 105.00 930 units Keller has monthly overhead of $13,493, which is divided into the following cost pools: Setup costs Quality control Maintenance Total $ 3, 250 6, 283...
PA4-3 (Algo) Selecting Cost Drivers, Assigning Costs Using Activity Rates [LO 4-1, 4-3,4-4, 4-6 ] Harbour Company makes two models of electronic tablets, the Home and the Work. Basic production information follows: Home Work Direct materials cost per unit $ 39 $ 67 Direct labor cost per unit 15 36 Sales price per unit 362 580 Expected production per month 760 units 300 units Harbour has monthly overhead of $181,260, which is divided into the following cost pools: Setup costs...
Keller Company makes two models of battery-operated boats, the Sandy Beach and the Rocky River. Basic production information follows: Sandy Beach Rocky River Direct materials cost per unit $ 19.30 $ 26.60 Direct labor cost per unit 14.80 19.10 Sales price per unit 83.40 105.00 Expected production per month 1,200 units 910 units Keller has monthly overhead of $11,104, which is divided into the following cost pools: Setup costs $ 2,400 Quality control 5,766 Maintenance 2,938 Total $ 11,104...