Labor cost budget:L | |||||||
Q1 | Q2 | Q3 | Q4 | Total | |||
Budgetd production units | 20,480 | 25,450 | 35,450 | 30,110 | 1,11,490 | ||
Multiply: Labor hour required per unit | 1.7 | 1.7 | 1.7 | 1.7 | 1.7 | ||
Budgeted Labor hours | 34,816 | 43,265 | 60,265 | 51,187 | 1,89,533 | ||
Multiply: Labor rate per Hour | 16 | 16 | 18 | 18 | |||
Budgeted Labor cost | 5,57,056 | 6,92,240 | 10,84,770 | 9,21,366 | 32,55,432 | ||
Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based...
Exercise 21-9 Rodriguez, Inc., is preparing its direct labor budget for 2017 from the following production budget based on a calendar year. Quarter Units Quarter Units 20,480 25,450 35,450 30,110 2 4 Each unit requires 1.70 hours of direct labor Prepare a direct labor budget for 2017. Wage rates are expected to be $16 for the first 2 quarters and $18 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.50.) RODRIQUEZ,...
Exercise 22-09 Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year. Quarter arter Units Quarter 20,4803 25,450 Units 35,450 30,110 Each unit requires 1.70 hours of direct labor. Prepare a direct labor budget for 2020. Wage rates are expected to be $16 for the first 2 quarters and $18 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.50.) RODRIQUEZ, INC....
Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year. Quarter Quarter Units 20,340 25,110 Units 35,440 30,500 4 Each unit requires 1.70 hours of direct labor. Prepare a direct labor budget for 2020. Wage rates are expected to be $15 for the first 2 quarters and $17 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.50.) RODRIQUEZ, INC. Direct Labor...
Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year. Quarter Units 20,330 25,370 Quarter Units 3 35,270 4 30,390 oport 2 Each unit requires 1.70 hours of direct labor. Prepare a direct labor budget for 2020. Wage rates are expected to be $17 for the first 2 quarters and $19 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.50.) RODRIQUEZ,...
Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year. Quarter Units 20,360 25,210 Quarter 3 Units 35,460 30,430 Each unit requires 1.60 hours of direct labor. Prepare a direct labor budget for 2020. Wage rates are expected to be $15 for the first 2 quarters and $17 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.50.) RODRIQUEZ, INC. Direct Labor...
Exercise 9-9 (Video) Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year Quarter Quarter Units 20,270 25.380 Units 35,130 30,140 Each unit requires 1.30 hours of direct labor Prepare a direct labor budget for 2020. Wage rates are expected to be $17 for the first 2 quarters and 519 for quarters 3 and 4. (Round Direct labo 52.50.) RODRIQUEZ, INC. Direct Labor Budget Quarter
Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year. Quarter Units Quarter Units 1 20,220 3 35,100 2 25,370 4 30,310 Each unit requires 1.80 hours of direct labor. Prepare a direct labor budget for 2020. Wage rates are expected to be $17 for the first 2 quarters and $19 for quarters 3 and 4
Your answer is partially correct. Try again. Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year. Quarter Units Quarter 20,4403 25,3204 Units 35,320 30,380 Each unit requires 1.70 hours of direct labor. Prepare a direct labor budget for 2020. Wage rates are expected to be $15 for the first 2 quarters and $17 for quarters 3 and 4. (Round Dire RODRIQUEZ, INC. Direct Labor Budget For the Year Ending...
Exercise 22-09 (Video) Pharoah, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year. Quarter Units Quarter Units 20,380 35,220 25,110 30,210 Each unit requires 1.60 hours of direct labor. Prepare a direct labor budget for 2020. Wage rates are expected to be $16 for the first 2 quarters and $18 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.50.) PHAROAH, INC....
Marigold, Inc., is preparing its direct labor budget for 2017 from the following production budget based on a calendar year. Quarter Units Quarter Units 1 20,110 3 35,370 2 25,410 4 30,440 Each unit requires 1.70 hours of direct labor. Prepare a direct labor budget for 2017. Wage rates are expected to be $18 for the first 2 quarters and $20 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.65.) MARIGOLD,...