Marigold, Inc., is preparing its direct labor budget for 2017 from the following production budget based on a calendar year. Quarter Units Quarter Units 1 20,110 3 35,370 2 25,410 4 30,440 Each unit requires 1.70 hours of direct labor. Prepare a direct labor budget for 2017. Wage rates are expected to be $18 for the first 2 quarters and $20 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.65.) MARIGOLD, INC. Direct Labor Budget Quarter 1 2 3 4 Year $ $ $ $ $ $ $ $ $
Direct labor budget
Quarter 1 | Quarter 2 | Quarter 3 | Quarter 4 | Year | |
Production unit | 20110 | 25410 | 35370 | 30440 | |
Labor hour per unit | 1.7 | 1.7 | 1.7 | 1.7 | |
Production labor hour | 34187 | 43197 | 60129 | 51748 | |
Rate per hour | 18 | 18 | 20 | 20 | |
Direct labor cost | 615366 | 777546 | 1202580 | 1034960 | 3630452 |
Marigold, Inc., is preparing its direct labor budget for 2017 from the following production budget based on a calendar y...
Thanks!
Indigo, Inc., is preparing its direct labor budget for 2017 from the following production budget based on a calendar year. Quarter 1 2 Units 20,440 25,320 Quarter 3 4 Units 35,320 30,380 Each unit requires 1.70 hours of direct labor. Prepare a direct labor budget for 2017. Wage rates are expected to be $15 for the first 2 quarters and $17 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.65.)
Culver, Inc., is preparing its direct labor budget for 2017 from the following production budget based on a calendar year. Quarter Units Quarter Units 35,240 1 20,200 3 25,280 4 30,120 Each unit requires 1.80 hours of direct labor. Prepare a direct labor budget for 2017. Wage rates are expected to be $18 for the first 2 quarters and $20 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.65.) CULVER, INC....
Exercise 13-9 Blue, Inc., is preparing its direct labor budget for 2017 from the following production budget based on a calendar year. Units Units Quarter Quarter 35,420 1 20,200 3 25,290 2 4 30,430 Each unit requires 1.70 hours of direct labor. Prepare a direct labor budget for 2017. Wage rates are expected to be $17 for the first 2 quarters and $19 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g....
Exercise 21-9 Rodriguez, Inc., is preparing its direct labor budget for 2017 from the following production budget based on a calendar year. Quarter Units Quarter Units 20,480 25,450 35,450 30,110 2 4 Each unit requires 1.70 hours of direct labor Prepare a direct labor budget for 2017. Wage rates are expected to be $16 for the first 2 quarters and $18 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.50.) RODRIQUEZ,...
Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year. Quarter Quarter Units 20,340 25,110 Units 35,440 30,500 4 Each unit requires 1.70 hours of direct labor. Prepare a direct labor budget for 2020. Wage rates are expected to be $15 for the first 2 quarters and $17 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.50.) RODRIQUEZ, INC. Direct Labor...
Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year Quarter Units Quarter Units 35,450 30,110 20,480 25,450 Each unit requires 1.70 hours of direct labor Prepare a direct labor budget for 2020. Wage rates are expected to be $16 for the first 2 quarters and $18 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.50.) RODRIQUEZ, INC. Direct Labor Budget...
Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year. Quarter Units 20,330 25,370 Quarter Units 3 35,270 4 30,390 oport 2 Each unit requires 1.70 hours of direct labor. Prepare a direct labor budget for 2020. Wage rates are expected to be $17 for the first 2 quarters and $19 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.50.) RODRIQUEZ,...
Sheffield, Inc., is preparing its direct labor budget for 2017
from the following production budget based on a calendar
year.
Quarter
Units
Quarter
Units
1
20,360
3
35,200
2
25,280
4
30,170
Each unit requires 1.80 hours of direct labor.
Prepare a direct labor budget for 2017. Wage rates are expected to
be $18 for the first 2 quarters and $20 for quarters 3 and 4.
(Round Direct labor time per unit answers to 2 decimal
places, e.g. 52.65.)
SHEFFIELD,...
Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year. Quarter Units Quarter Units 1 20,220 3 35,100 2 25,370 4 30,310 Each unit requires 1.80 hours of direct labor. Prepare a direct labor budget for 2020. Wage rates are expected to be $17 for the first 2 quarters and $19 for quarters 3 and 4
Exercise 22-09 Rodriguez, Inc., is preparing its direct labor budget for 2020 from the following production budget based on a calendar year. Quarter arter Units Quarter 20,4803 25,450 Units 35,450 30,110 Each unit requires 1.70 hours of direct labor. Prepare a direct labor budget for 2020. Wage rates are expected to be $16 for the first 2 quarters and $18 for quarters 3 and 4. (Round Direct labor time per unit answers to 2 decimal places, e.g. 52.50.) RODRIQUEZ, INC....